JONES SH 92 (0318-01-034)

Items: 32

County: JONES
Length: 0.0000 MILES
Highway: SH 92
District: ABILENE
Control Number: 0318-01-034
DBE Goal: 0.0%
Project: C 318-1-34
Guaranty: $100,000.00
Time: 108 WORKING DAYS
Engineer's Estimate: $8,479,584.01
Date: 09/05/2024 (1 year ago)
Contract Number: 9243010
Type: PREVENTIVE MAINTENANCE
Project ID: A00195509
Project Description: BASE REPAIR, RESURFACE, MBGF, AND PAVEMENT MARKINGS, ETC
Mail/Deliver Bids To: N/A
BRYCE TURENTINE
CHAD W CARTER
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (8)
E
Engineer's Estimate
$8,479,584.01
$6,794,417.72
Over/Under Est: -19.87% -$1,685,166.29
Over/Under Est: -10.6% -$898,598.75
Amt Left: 11.58% $786,567.54
$7,610,272.70
Over/Under Est: -10.25% -$869,311.31
Amt Left: 12.01% $815,854.98
Delta: -0.39% -$29,287.44
$7,751,448.60
Over/Under Est: -8.59% -$728,135.41
Amt Left: 14.09% $957,030.88
Delta: -1.86% -$141,175.90
$7,981,531.60
Over/Under Est: -5.87% -$498,052.41
Amt Left: 17.47% $1,187,113.88
Delta: -2.97% -$230,083.00
$8,112,647.90
Over/Under Est: -4.33% -$366,936.11
Amt Left: 19.4% $1,318,230.18
Delta: -1.64% -$131,116.30
$8,213,281.60
Over/Under Est: -3.14% -$266,302.41
Amt Left: 20.88% $1,418,863.88
Delta: -1.24% -$100,633.70
Over/Under Est: 3.36% $284,856.99
Amt Left: 28.99% $1,970,023.28
Delta: -6.71% -$551,159.40
Subcontractor Percentage Amount
FLAT LINE, INC. 2.75% $186,846.49
HJC FARMS, INC. 1.12% $76,097.48
WEST TEXAS ROCK RESOURCES, LLC 0.69% $46,881.48
CONTRACTORS SERVICE, LTD. 0.48% $32,613.21
Total: 5.04% $342,438.66

Bid Items & Bid Tabulations

32 Total 0 of 32
JONES  |  SH 92  |  ABILENE  |  0318-01-034  |  09/05/2024  |  $8,479,584.01  |  C 318-1-34  |  PREVENT MAINT  |  108 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
J. H. STRAIN & SONS, INC.
NOBLES ROAD CONSTRUCTION, INC.
DUININCK, INC.
CK NEWBERRY, LLC
REECE ALBERT, INC.
GILVIN-TERRILL, LTD.
RK HALL, LLC
BONTKE BROTHERS CONSTRUCTION COMPANY
BACKFILL (TY A)
STA 921.330 $300.000 $385.000 $420.000 $200.000 $225.000 $175.990 $115.000 $183.200 $550.000
SP MIXES SP-D SAC-B PG70-22
TON 37,947.000 $160.000 $135.930 $143.000 $145.550 $150.000 $164.100 $150.000 $164.370 $160.000
TACK COAT
GAL 46,057.000 $6.000 $3.000 $5.500 $5.650 $5.000 $3.700 $6.000 $5.070 $10.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(4")
SY 5,669.000 $65.000 $55.000 $58.000 $60.000 $55.000 $70.940 $55.000 $63.330 $65.000
PLANE & TEXT ASPH CONC PAV(1.5")
SY 38,982.000 $4.000 $2.500 $4.850 $2.950 $2.000 $3.310 $3.500 $4.810 $3.000
RAIL (TY T631)
LF 125.000 $120.000 $160.000 $116.000 $110.000 $115.000 $127.530 $110.000 $123.900 $175.000
MOBILIZATION
LS 1.000 $760,000.000 $250,000.000 $545,000.000 $650,000.000 $725,000.000 $448,883.120 $810,000.000 $368,729.300 $650,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $20,000.000 $10,000.000 $11,000.000 $33,000.000 $20,000.000 $4,615.420 $60,000.000 $30,919.740 $8,000.000
TMA (STATIONARY)
DAY 90.000 $300.000 $375.000 $250.000 $300.000 $400.000 $140.480 $675.000 $428.820 $300.000
TMA (MOBILE OPERATION)
DAY 26.000 $450.000 $375.000 $360.000 $1,000.000 $400.000 $501.950 $950.000 $609.290 $500.000
MILL RUMBLE STRIPS (ASPHALT) (SHLDR)
LF 174,672.000 $0.220 $0.180 $0.220 $0.080 $0.250 $0.180 $0.200 $0.190 $0.500
MILL RUMBLE STRIPS (ASPH) (CENTERLINE)
LF 86,931.000 $0.220 $0.250 $0.280 $0.080 $0.200 $0.180 $0.250 $0.260 $0.750
MTL W-BEAM GD FEN (TIM POST)
LF 800.000 $28.000 $33.000 $35.000 $30.000 $30.000 $34.920 $30.000 $33.930 $35.000
REMOVE METAL BEAM GUARD FENCE
LF 875.000 $3.000 $3.450 $3.300 $3.100 $3.000 $3.640 $3.000 $3.540 $5.000
GUARDRAIL END TREATMENT (INSTALL)
EA 8.000 $3,500.000 $4,025.000 $3,850.000 $3,600.000 $3,500.000 $4,251.040 $3,500.000 $4,130.000 $3,900.000
GUARDRAIL END TREATMENT (REMOVE)
EA 8.000 $350.000 $345.000 $330.000 $310.000 $300.000 $364.380 $300.000 $354.000 $350.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 17.000 $45.000 $57.500 $55.000 $52.000 $50.000 $60.730 $50.000 $59.000 $850.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 8,556.000 $3.000 $2.500 $2.000 $1.600 $1.000 $1.860 $2.000 $5.360 $1.000
REFL PAV MRK TY I (W)8"(BRK)(100MIL)
LF 50.000 $1.250 $2.300 $1.200 $1.150 $1.500 $1.820 $2.000 $1.770 $3.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 190.000 $1.250 $3.450 $1.000 $0.940 $1.500 $1.820 $3.000 $1.770 $4.000
REFL PAV MRK TY I (W)6"(SLD)(100MIL)
LF 189,084.000 $0.850 $0.710 $0.640 $0.590 $0.650 $0.790 $0.600 $0.770 $0.750
REFL PAV MRK TY I (Y)6"(BRK)(100MIL)
LF 23,580.000 $0.850 $0.680 $0.660 $0.620 $0.650 $0.780 $0.600 $0.760 $0.750
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
LF 45,467.000 $0.850 $0.680 $0.640 $0.600 $0.650 $0.780 $0.600 $0.760 $0.750
PREFAB PM TY C (W)(24")(SLD)
LF 820.000 $20.000 $25.300 $15.000 $14.000 $15.000 $17.610 $22.000 $17.110 $25.000
PREFAB PM TY C (W)(ARROW)
EA 6.000 $400.000 $345.000 $250.000 $230.000 $300.000 $364.380 $300.000 $354.000 $500.000
PREFAB PM TY C (W)(DBL ARROW)
EA 2.000 $400.000 $357.000 $360.000 $340.000 $450.000 $546.570 $310.000 $531.000 $500.000
PREFAB PM TY C (W)(WORD)
EA 6.000 $400.000 $368.000 $360.000 $310.000 $400.000 $485.830 $320.000 $472.000 $500.000
REFL PAV MRKR TY I-C
EA 12.000 $6.000 $4.900 $5.000 $4.150 $10.000 $12.150 $4.250 $11.800 $5.000
REFL PAV MRKR TY II-A-A
EA 1,866.000 $6.000 $4.850 $4.500 $4.050 $5.000 $6.070 $4.200 $5.900 $5.000
ELIM EXT PM & MRKS (24")
LF 800.000 $5.000 $2.300 $3.000 $2.600 $4.000 $4.860 $2.000 $4.720 $5.000
ELIM EXT PM & MRKS (ARROW)
EA 3.000 $60.000 $345.000 $77.000 $72.500 $100.000 $121.460 $300.000 $118.000 $500.000
ELIM EXT PM & MRKS (WORD)
EA 3.000 $80.000 $345.000 $77.000 $72.500 $100.000 $121.460 $300.000 $118.000 $500.000
Totals: $8,479,584.010 $6,794,417.720 $7,580,985.260 $7,610,272.700 $7,751,448.600 $7,981,531.607 $8,112,647.900 $8,213,281.606 $8,764,441.000