JONES US 83 (0033-05-095)

Items: 31

County: JONES
Length: N/A
Highway: US 83
District: ABILENE
Control Number: 0033-05-095
DBE Goal: N/A
Project: C 33-5-95
Guaranty: N/A
Time: 20 WORKING DAYS
Engineer's Estimate: $264,888.00
Date: 04/07/2021 (5 years ago)
Contract Number: N/A
Type: CONCRETE PAVEMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Documents:
Bidders (6)
E
Engineer's Estimate
$264,888.00
$251,560.40
Over/Under Est: -5.03% -$13,327.60
Over/Under Est: 26.58% $70,415.00
Amt Left: 33.29% $83,742.60
Over/Under Est: 30.62% $81,101.50
Amt Left: 37.54% $94,429.10
Delta: -3.19% -$10,686.50
Over/Under Est: 48.54% $128,583.54
Amt Left: 56.41% $141,911.14
Delta: -13.72% -$47,482.04
$393,522.25
Over/Under Est: 48.56% $128,634.25
Amt Left: 56.43% $141,961.85
Delta: -0.01% -$50.71
Over/Under Est: 61.47% $162,839.15
Amt Left: 70.03% $176,166.75
Delta: -8.69% -$34,204.90

Bid Items & Bid Tabulations

31 Total 0 of 31
JONES  |  US 83  |  ABILENE  |  0033-05-095  |  04/07/2021  |  $264,888.00  |  C 33-5-95  |  CONC PAVMT  |  20 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
O. TREVINO CONSTRUCTION, LLC
FNH CONSTRUCTION, LLC
SILVER CREEK CONSTRUCTION, INC.
GIBSON & ASSOCIATES, INC.
CK NEWBERRY, LLC
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
REMOVING CONC (PAV)
CY 225.000 $50.000 $100.000 $50.000 $200.000 $322.000 $75.000 $226.090
CONC PVMT (CONT REINF)(FAST TRK)(10")
SY 813.000 $200.000 $183.000 $200.000 $227.500 $200.000 $270.000 $234.950
MOBILIZATION
LS 1.000 $20,000.000 $25,000.000 $30,000.000 $30,000.000 $85,000.000 $80,000.000 $85,279.660
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 1.000 $20,000.000 $15,000.000 $25,000.000 $30,000.000 $28,600.000 $20,000.000 $27,165.100
WK ZN PAV MRK REMOV (REFL) TY I-C
EA 31.000 $5.000 $38.000 $5.000 $15.000 $38.500 $22.000 $42.740
WK ZN PAV MRK REMOV (REFL) TY II-A-A
EA 8.000 $5.000 $38.000 $5.000 $15.000 $38.500 $22.000 $54.940
WK ZN PAV MRK REMOV (TRAF BTN) TY W
EA 30.000 $5.000 $28.000 $5.000 $15.000 $27.500 $22.000 $31.880
WK ZN PAV MRK REMOV (TRAF BTN) TY Y
EA 24.000 $5.000 $28.000 $5.000 $15.000 $27.500 $22.000 $32.980
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 258.000 $3.000 $1.100 $10.000 $1.000 $2.200 $1.250 $2.710
PAVEMENT SEALER 4"
LF 2,184.000 $1.000 $1.100 $2.000 $1.000 $0.330 $1.250 $0.390
PAVEMENT SEALER 8"
LF 258.000 $1.500 $1.100 $6.000 $1.000 $1.100 $1.250 $1.610
PAVEMENT SEALER 24"
LF 410.000 $3.000 $2.800 $20.000 $2.500 $1.930 $3.000 $2.250
PAVEMENT SEALER (ARROW)
EA 4.000 $150.000 $84.000 $250.000 $75.000 $55.000 $85.000 $87.880
PAVEMENT SEALER (WORD)
EA 2.000 $150.000 $112.000 $250.000 $100.000 $82.500 $115.000 $148.260
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 1,950.000 $0.900 $1.100 $2.000 $1.000 $0.660 $1.250 $0.730
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 4,006.000 $1.000 $0.550 $2.000 $0.500 $0.660 $0.750 $0.690
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 360.000 $0.900 $1.100 $2.000 $1.000 $0.660 $1.250 $1.030
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 6,176.000 $0.900 $0.550 $2.000 $0.500 $0.660 $0.750 $0.680
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 476.000 $11.000 $16.800 $20.000 $15.000 $24.200 $17.000 $24.480
PREFAB PAV MRK TY C (W) (ARROW)
EA 4.000 $250.000 $224.000 $250.000 $200.000 $330.000 $250.000 $362.880
PREFAB PAV MRK TY C (W) (WORD)
EA 2.000 $475.000 $336.000 $250.000 $300.000 $495.000 $350.000 $560.760
REFL PAV MRKR TY I-C
EA 98.000 $5.000 $5.600 $5.000 $5.000 $4.950 $6.000 $6.290
REFL PAV MRKR TY II-A-A
EA 156.000 $5.000 $5.600 $5.000 $5.000 $4.950 $6.000 $5.790
PAV SURF PREP FOR MRK (4")
LF 239.000 $2.000 $1.100 $2.000 $1.000 $1.100 $1.250 $1.650
PAV SURF PREP FOR MRK (8")
LF 100.000 $4.000 $1.100 $6.000 $1.000 $2.200 $1.250 $3.520
PAV SURF PREP FOR MRK (24")
LF 162.000 $6.300 $1.100 $20.000 $1.000 $2.750 $1.250 $3.560
PAV SURF PREP FOR MRK (ARROW)
EA 4.000 $100.000 $55.000 $250.000 $50.000 $38.500 $75.000 $71.380
PAV SURF PREP FOR MRK (WORD)
EA 2.000 $100.000 $55.000 $250.000 $50.000 $49.500 $75.000 $115.260
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 72.000 $125.000 $100.000 $150.000 $150.000 $117.000 $75.000 $87.980
TMA (STATIONARY)
DAY 24.000 $250.000 $100.000 $350.000 $400.000 $250.000 $400.000 $735.620
TMA (MOBILE OPERATION)
DAY 30.000 $250.000 $100.000 $850.000 $400.000 $5.000 $400.000 $533.890
Totals: $264,888.000 $251,560.400 $335,303.000 $345,989.500 $393,471.540 $393,522.250 $427,727.150