JOHNSON SH 171 (0019-01-153)
Items: 35
County: JOHNSON
Length: 1.5020 MILES
Highway: SH 171
District: FORT WORTH
Control Number: 0019-01-153
DBE Goal: 0.0%
Project: F 2026(863)
Guaranty: $43,000.00
Time: 54 WORKING DAYS
Engineer's Estimate: $2,135,136.14
Date: 07/02/2026 1:00 PM CDT (16 days ago)
Contract Number: 7263238
Type: REPAIR ROADWAY
Project ID: A00219620
Contract Type: FEDERAL
Project Description: MILL AND INLAY, FULL DEPTH REPAIR AND PAVEMENT MARKINGS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
JOHNSON SH 171 (0019-01-153)
Project Name: N/A
Project: F 2026(863)
Engineer's Estimate: $1,518,165.79
Length: 0.8600 MILES
Project Class: OVERLAY
Limits From: WILLINGHAM ST
Limits To: FM 1718
Project Description: MILL AND INLAY, FULL DEPTH REPAIR AND PAVEMENT MARKINGS
JOHNSON BU 67M (0259-05-086)
Project Name: BUS 67 M; FROM ENGLISH ST TO ALVARADO ST
Project: F 2026(863)
Engineer's Estimate: $616,970.35
Length: 0.6420 MILES
Project Class: OVERLAY
Limits From: ENGLISH ST.
Limits To: ALVARADO ST.
Project Description: MILL AND INLAY, FULL DEPTH REPAIR, AND PAVEMENT MARKINGS
Bidders (7)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$2,135,136.14 | |||
| $1,879,034.47 |
-11.99%
-$256,101.67
|
|||
| $2,032,482.89 |
-4.81%
-$102,653.25
|
8.17%
$153,448.42
|
||
| $2,098,358.90 |
-1.72%
-$36,777.24
|
11.67%
$219,324.43
|
-3.24%
-$65,876.01
|
|
| $2,122,024.00 |
-0.61%
-$13,112.14
|
12.93%
$242,989.53
|
-1.13%
-$23,665.10
|
|
| $2,177,485.25 |
1.98%
$42,349.11
|
15.88%
$298,450.78
|
-2.61%
-$55,461.25
|
|
| $2,291,701.60 |
7.33%
$156,565.46
|
21.96%
$412,667.13
|
-5.25%
-$114,216.35
|
|
| $2,903,535.32 |
35.99%
$768,399.18
|
54.52%
$1,024,500.85
|
-26.70%
-$611,833.72
|
E
Engineer's Estimate
$2,135,136.14
$1,879,034.47
Over/Under Est:
-11.99%
-$256,101.67
$2,032,482.89
Over/Under Est:
-4.81%
-$102,653.25
Amt Left:
8.17%
$153,448.42
$2,098,358.90
Over/Under Est:
-1.72%
-$36,777.24
Amt Left:
11.67%
$219,324.43
Delta:
-3.24%
-$65,876.01
$2,122,024.00
Over/Under Est:
-0.61%
-$13,112.14
Amt Left:
12.93%
$242,989.53
Delta:
-1.13%
-$23,665.10
$2,177,485.25
Over/Under Est:
1.98%
$42,349.11
Amt Left:
15.88%
$298,450.78
Delta:
-2.61%
-$55,461.25
$2,291,701.60
Over/Under Est:
7.33%
$156,565.46
Amt Left:
21.96%
$412,667.13
Delta:
-5.25%
-$114,216.35
$2,903,535.32
Over/Under Est:
35.99%
$768,399.18
Amt Left:
54.52%
$1,024,500.85
Delta:
-26.70%
-$611,833.72
Bid Items & Bid Tabulations
35
Total
0 of 35
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| CONTRACTOR FORCE ACCOUNT WORK (PART) | $10,000.00 |
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $5,000.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $10,000.00 |
| Total: | $25,000.00 |