JIM HOGG SH 16 (0517-06-036)

Items: 20

County: JIM HOGG
Length: N/A
Highway: SH 16
District: PHARR
Control Number: 0517-06-036
DBE Goal: N/A
Project: STP 2B20(155)HES
Guaranty: N/A
Time: 256 WORKING DAYS
Engineer's Estimate: $5,588,167.60
Date: 08/05/2020 (5 years ago)
Contract Number: N/A
Type: IMPROVE GUARDRAIL
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$5,588,167.60
$4,952,063.28
Over/Under Est: -11.38% -$636,104.32
$6,089,108.38
Over/Under Est: 8.96% $500,940.78
Amt Left: 22.96% $1,137,045.10
$6,387,268.50
Over/Under Est: 14.3% $799,100.90
Amt Left: 28.98% $1,435,205.22
Delta: -4.90% -$298,160.12
Subcontractor Percentage Amount
HJC FARMS, INC. 72.62% $3,690,584.59
TEXAS ICON CONSTRUCTION, LLC 29.41% $1,494,630.86
TERRA CONSTRUCTION LLC 6.70% $340,497.34
JMG CONCRETE INC 5.76% $292,726.07
TREBOL TRAFFIC SAFETY GROUP LLC 3.55% $180,412.77
HIGHWAY BARRICADES AND SERVICES, LLC 0.18% $9,147.69
Total: 118.22% $6,007,999.32

Bid Items & Bid Tabulations

20 Total 0 of 20
JIM HOGG  |  SH 16  |  PHARR  |  0517-06-036  |  08/05/2020  |  $5,588,167.60  |  STP 2B20(155)HES  |  IMPROVE GUARDRAIL  |  256 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
VECTOR UTILITIES LLC
HJC FARMS, INC.
FNH CONSTRUCTION, LLC
BACKFILL (TY A)
LF 74,069.000 $6.000 $5.810 $7.000 $4.000
RIPRAP (MOW STRIP)(4 IN)
CY 3,451.470 $430.000 $480.410 $557.750 $500.000
MOBILIZATION
LS 1.000 $515,000.000 $317,220.220 $300,000.000 $630,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 16.000 $5,000.000 $9,252.260 $3,000.000 $8,500.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 14,790.000 $5.000 $5.620 $5.000 $15.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 14,790.000 $1.000 $0.930 $2.000 $9.000
MTL W-BEAM GD FEN (TIM POST)
LF 38,530.000 $24.000 $21.870 $30.280 $28.000
MTL W-BEAM GD FEN (STEEL POST)
LF 8,029.500 $45.000 $31.510 $36.410 $35.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 12.000 $2,500.000 $1,734.000 $1,897.500 $1,850.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 2.000 $2,100.000 $1,468.000 $1,523.750 $1,850.000
REMOVE METAL BEAM GUARD FENCE
LF 45,275.000 $7.000 $1.250 $5.750 $5.000
REMOVE TERMINAL ANCHOR SECTION
EA 44.000 $550.000 $99.510 $460.000 $500.000
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 12.000 $500.000 $99.480 $632.500 $500.000
GUARDRAIL END TREATMENT (INSTALL)
EA 320.000 $3,000.000 $2,985.000 $3,220.000 $2,850.000
GUARDRAIL END TREATMENT (REMOVE)
EA 280.000 $600.000 $99.510 $517.500 $1,500.000
INSTL OM ASSM (OM-3R)(FLX)GND
EA 322.000 $131.000 $79.310 $86.250 $100.000
REMOVE DELIN & OBJECT MARKER ASSMS
EA 1,456.000 $35.000 $6.610 $11.500 $50.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 1,511.000 $37.000 $33.040 $97.750 $50.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BR)
EA 20.000 $37.000 $66.000 $115.000 $100.000
TMA (STATIONARY)
DAY 256.000 $120.000 $197.000 $200.000 $350.000
Totals: $5,588,167.600 $4,952,063.288 $6,089,108.388 $6,387,268.500