Job Info for 0517-06-036

County: JIM HOGG Highway: SH 16 Date: 08/05/2020 (4 years ago) Engineer's Estimate: $5,588,168 Control Number: 0517-06-036
Project: STP 2B20(155)HES District: PHARR Time: 256 WORKING DAYS Type: IMPROVE GUARDRAIL
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $5,588,167.60
VECTOR UTILITIES LLC   $4,952,063.28 1
-11.38% | -$636,104.32
HJC FARMS, INC.   $6,089,108.38 2
8.96% | $500,940.78
22.96% | $1,137,045.10
FNH CONSTRUCTION, LLC   $6,387,268.50 3
14.3% | $799,100.90
28.98% | $1,435,205.22
4.90% | $298,160.12
Subcontractor Percentage Amount
HJC FARMS, INC. 74.52% $3,690,277.56
TEXAS ICON CONSTRUCTION, LLC 30.18% $1,494,532.70
DEPENDABLE FENCE & WELDING CO. INC. 10.09% $499,663.18
TERRA CONSTRUCTION LLC 6.87% $340,206.75
JMG CONCRETE INC 5.91% $292,666.94
TREBOL TRAFFIC SAFETY GROUP LLC 3.63% $179,759.90
HIGHWAY BARRICADES AND SERVICES, LLC 0.18% $8,913.71
Total: 131.38% $6,506,020.74

Bid Items

Items: 20, 0 filtered
JIM HOGG SH 16  |  PHARR  |  0517-06-036  |  08/05/2020  |  $5,588,168  |  STP 2B20(155)HES  |  IMPROVE GUARDRAIL  |  256 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate VECTOR UTILITIES LLC HJC FARMS, INC. FNH CONSTRUCTION, LLC
134 6006 BACKFILL (TY A) LF 74,069.000 $6.000 $5.810 $7.000 $4.000
432 6045 RIPRAP (MOW STRIP)(4 IN) CY 3,451.470 $430.000 $480.410 $557.750 $500.000
500 6001 MOBILIZATION LS 1.000 $515,000.000 $317,220.220 $300,000.000 $630,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 16.000 $5,000.000 $9,252.260 $3,000.000 $8,500.000
506 6041 BIODEG EROSN CONT LOGS (INSTL) (12") LF 14,790.000 $5.000 $5.620 $5.000 $15.000
506 6043 BIODEG EROSN CONT LOGS (REMOVE) LF 14,790.000 $1.000 $0.930 $2.000 $9.000
540 6001 MTL W-BEAM GD FEN (TIM POST) LF 38,530.000 $24.000 $21.870 $30.280 $28.000
540 6002 MTL W-BEAM GD FEN (STEEL POST) LF 8,029.500 $45.000 $31.510 $36.410 $35.000
540 6006 MTL BEAM GD FEN TRANS (THRIE-BEAM) EA 12.000 $2,500.000 $1,734.000 $1,897.500 $1,850.000
540 6016 DOWNSTREAM ANCHOR TERMINAL SECTION EA 2.000 $2,100.000 $1,468.000 $1,523.750 $1,850.000
542 6001 REMOVE METAL BEAM GUARD FENCE LF 45,275.000 $7.000 $1.250 $5.750 $5.000
542 6002 REMOVE TERMINAL ANCHOR SECTION EA 44.000 $550.000 $99.510 $460.000 $500.000
542 6004 RM MTL BM GD FENCE TRANS (THRIE-BEAM) EA 12.000 $500.000 $99.480 $632.500 $500.000
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 320.000 $3,000.000 $2,985.000 $3,220.000 $2,850.000
544 6003 GUARDRAIL END TREATMENT (REMOVE) EA 280.000 $600.000 $99.510 $517.500 $1,500.000
658 6056 INSTL OM ASSM (OM-3R)(FLX)GND EA 322.000 $131.000 $79.310 $86.250 $100.000
658 6060 REMOVE DELIN & OBJECT MARKER ASSMS EA 1,456.000 $35.000 $6.610 $11.500 $50.000
658 6062 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) EA 1,511.000 $37.000 $33.040 $97.750 $50.000
658 6063 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BR) EA 20.000 $37.000 $66.000 $115.000 $100.000
6185 6002 TMA (STATIONARY) DAY 256.000 $120.000 $197.000 $200.000 $350.000
Totals: $5,588,167.60 $4,952,063.29 $6,089,108.39 $6,387,268.50