JEFFERSON SH 82 (2367-01-063)

Items: 63

County: JEFFERSON
Length: N/A
Highway: SH 82
District: BEAUMONT
Control Number: 2367-01-063
DBE Goal: N/A
Project: STP 2023(585)HES
Guaranty: N/A
Time: 88 WORKING DAYS
Engineer's Estimate: $4,864,202.34
Date: 08/02/2023 (2 years ago)
Contract Number: N/A
Type: HAZARD ELIMINATION & SAFETY
Mail/Deliver Bids To: N/A
DAVE COLLINS
KEVIN GRISSOM
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (1)
E
Engineer's Estimate
$4,864,202.34
$6,193,763.91
Over/Under Est: 27.33% $1,329,561.57
Subcontractor Percentage Amount
NORMAN HIGHWAY CONSTRUCTORS, INC. 3.20% $197,195.73
TRP CONSTRUCTION GROUP, LLC 2.33% $143,583.14
AMERICAN REMEDIATION OPTIONS, INC. 1.83% $112,771.31
BARRICADES UNLIMITED 0.38% $23,416.99
PROFESSIONAL TRAFFIC CONTROL LLC 0.27% $16,638.39
Total: 8.01% $493,605.56

Bid Items & Bid Tabulations

63 Total 0 of 63
JEFFERSON  |  SH 82  |  BEAUMONT  |  2367-01-063  |  08/02/2023  |  $4,864,202.34  |  STP 2023(585)HES  |  HAZARD ELIM & SAFETY  |  88 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
TEXAS MATERIALS GROUP, INC.
REMOVING CONC (DRIVEWAYS)
SY 327.000 $14.000 $99.250
SUBGRADE WIDENING (ORD COMP)
STA 395.500 $600.000 $1,150.000
BACKFILL (TY A OR B)
STA 395.500 $200.000 $222.000
CELL FBR MLCH SEED(PERM)(URBAN)(SANDY)
SY 35,414.000 $0.750 $0.390
VEGETATIVE WATERING
MG 297.000 $20.000 $79.000
ASPH (AC-20-5TR OR AC-20XP)
GAL 47,536.000 $6.000 $5.500
AGGR (TY-PB GR-4 OR TY-PL GR-4 ( SAC-B)
CY 1,057.000 $130.000 $255.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
SY 1,000.000 $100.000 $185.000
CEM STABIL BKFL
CY 148.000 $100.000 $252.000
CUT & RESTORE ASPH PAVING
SY 33.000 $120.230 $216.000
TRENCH EXCAVATION PROTECTION
LF 112.000 $47.000 $367.500
TEMPORARY SPL SHORING
SF 180.000 $118.000 $304.500
RETAINING WALL (CAST - IN - PLACE)
SF 95.000 $106.000 $330.750
RIPRAP (CONC)(4 IN)
CY 3.000 $670.010 $1,207.500
RIPRAP (MOW STRIP)(5 IN)
CY 13.000 $130.000 $840.000
RC PIPE (CL III)(36 IN)
LF 152.000 $150.000 $302.000
SET (TY I) (24 IN) (4: 1) (C)
EA 2.000 $1,800.000 $1,575.000
SET (TY I) (30 IN) (4: 1) (C)
EA 1.000 $1,900.000 $2,130.000
SET (TY I) (36 IN) (4: 1) (C)
EA 6.000 $2,000.000 $3,570.000
REMOV STR (PIPE)
LF 152.000 $27.000 $35.700
MOBILIZATION
LS 1.000 $500,000.000 $446,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 7.000 $3,500.000 $5,350.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 600.000 $6.000 $6.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 600.000 $1.500 $1.000
ONE-WAY TRAF CONT (PORT TRAF SIG)
MO 1.000 $7,000.000 $14,700.000
PORT CTB (FUR & INST)(F-SHAPE)(TY 1)
LF 90.000 $88.000 $176.000
PORT CTB (MOVE)(F-SHAPE)(TY 1)
LF 90.000 $14.000 $80.000
PORT CTB (REMOVE)(F-SHAPE)(TY 1)
LF 90.000 $16.000 $110.000
INTRSCT, DRVWAYS, & TURNOUT (ACP)
SY 632.000 $70.000 $93.000
DRIVEWAYS (BASE)
SY 827.000 $50.000 $67.000
RUMBLE STRIPS (SHOULDER)
LF 70,706.000 $0.250 $0.420
RUMBLE STRIPS (CENTERLINE)
LF 38,553.000 $0.180 $0.500
MTL W-BEAM GD FEN (TIM POST)
LF 50.000 $40.000 $38.750
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 2.000 $2,000.000 $2,310.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 1.000 $2,200.000 $1,575.000
TL-3 31" SHORT RADIUS (POSTS 2 THRU 7)
EA 1.000 $1,000.000 $19,215.000
GUARDRAIL END TREATMENT (INSTALL)
EA 1.000 $3,200.000 $3,255.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 2.000 $2,800.000 $1,995.000
CRASH CUSH ATTEN (REMOVE)
EA 2.000 $1,300.000 $945.000
CRASH CUSH ATTEN (INSTL)(S)(W)(TL3)
EA 2.000 $9,000.000 $10,490.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 23.000 $436.000 $630.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 2.000 $605.000 $729.000
IN SM RD SN SUP&AM TYS80(1)SA(P)
EA 4.000 $710.000 $939.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 2.000 $770.000 $1,044.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 1.000 $705.000 $1,207.000
REMOVE SM RD SN SUP&AM
EA 34.000 $77.000 $132.000
IN SM RD SN SUP&AM TYS80(1)SA(P-1EXT)
EA 2.000 $710.000 $1,105.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 9.000 $31.520 $27.000
INSTL DEL ASSM (D-SW)SZ (BRF)GF1
EA 7.000 $20.000 $26.000
INSTL OM ASSN (OM-2Z)(WFLX)(WAP)
EA 14.000 $100.000 $136.000
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 870.000 $50.000 $4.250
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 4,113.000 $1.000 $9.170
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 104.000 $4.000 $1.420
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 79,497.000 $0.700 $0.860
RE PM W/RET REQ TY I (Y)6"(BRK)(100MIL)
LF 6,200.000 $0.700 $0.810
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
LF 45,508.000 $0.700 $0.890
REFL PAV MRKR TY I-C
EA 6.000 $10.000 $6.300
REFL PAV MRKR TY II-A-A
EA 891.000 $5.000 $6.300
D-GR HMA TY-B PG64-22
TON 19,428.000 $130.000 $160.000
D-GR HMA TY-D PG64-22
TON 2,431.000 $180.000 $183.000
TACK COAT
GAL 3,439.000 $6.000 $12.000
TMA (STATIONARY)
DAY 88.000 $350.000 $527.000
TMA (MOBILE OPERATION)
DAY 20.000 $400.000 $550.000
Totals: $4,864,202.340 $6,193,763.910