REMOVING CONC (DRIVEWAYS)
|
SY
|
327.000
|
$14.000
|
$99.250
|
|
|
SUBGRADE WIDENING (ORD COMP)
|
STA
|
395.500
|
$600.000
|
$1,150.000
|
|
|
BACKFILL (TY A OR B)
|
STA
|
395.500
|
$200.000
|
$222.000
|
|
|
CELL FBR MLCH SEED(PERM)(URBAN)(SANDY)
|
SY
|
35,414.000
|
$0.750
|
$0.390
|
|
|
VEGETATIVE WATERING
|
MG
|
297.000
|
$20.000
|
$79.000
|
|
|
ASPH (AC-20-5TR OR AC-20XP)
|
GAL
|
47,536.000
|
$6.000
|
$5.500
|
|
|
AGGR (TY-PB GR-4 OR TY-PL GR-4 ( SAC-B)
|
CY
|
1,057.000
|
$130.000
|
$255.000
|
|
|
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
|
SY
|
1,000.000
|
$100.000
|
$185.000
|
|
|
CEM STABIL BKFL
|
CY
|
148.000
|
$100.000
|
$252.000
|
|
|
CUT & RESTORE ASPH PAVING
|
SY
|
33.000
|
$120.230
|
$216.000
|
|
|
TRENCH EXCAVATION PROTECTION
|
LF
|
112.000
|
$47.000
|
$367.500
|
|
|
TEMPORARY SPL SHORING
|
SF
|
180.000
|
$118.000
|
$304.500
|
|
|
RETAINING WALL (CAST - IN - PLACE)
|
SF
|
95.000
|
$106.000
|
$330.750
|
|
|
RIPRAP (CONC)(4 IN)
|
CY
|
3.000
|
$670.010
|
$1,207.500
|
|
|
RIPRAP (MOW STRIP)(5 IN)
|
CY
|
13.000
|
$130.000
|
$840.000
|
|
|
RC PIPE (CL III)(36 IN)
|
LF
|
152.000
|
$150.000
|
$302.000
|
|
|
SET (TY I) (24 IN) (4: 1) (C)
|
EA
|
2.000
|
$1,800.000
|
$1,575.000
|
|
|
SET (TY I) (30 IN) (4: 1) (C)
|
EA
|
1.000
|
$1,900.000
|
$2,130.000
|
|
|
SET (TY I) (36 IN) (4: 1) (C)
|
EA
|
6.000
|
$2,000.000
|
$3,570.000
|
|
|
REMOV STR (PIPE)
|
LF
|
152.000
|
$27.000
|
$35.700
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$500,000.000
|
$446,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
7.000
|
$3,500.000
|
$5,350.000
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (12")
|
LF
|
600.000
|
$6.000
|
$6.000
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
600.000
|
$1.500
|
$1.000
|
|
|
ONE-WAY TRAF CONT (PORT TRAF SIG)
|
MO
|
1.000
|
$7,000.000
|
$14,700.000
|
|
|
PORT CTB (FUR & INST)(F-SHAPE)(TY 1)
|
LF
|
90.000
|
$88.000
|
$176.000
|
|
|
PORT CTB (MOVE)(F-SHAPE)(TY 1)
|
LF
|
90.000
|
$14.000
|
$80.000
|
|
|
PORT CTB (REMOVE)(F-SHAPE)(TY 1)
|
LF
|
90.000
|
$16.000
|
$110.000
|
|
|
INTRSCT, DRVWAYS, & TURNOUT (ACP)
|
SY
|
632.000
|
$70.000
|
$93.000
|
|
|
DRIVEWAYS (BASE)
|
SY
|
827.000
|
$50.000
|
$67.000
|
|
|
RUMBLE STRIPS (SHOULDER)
|
LF
|
70,706.000
|
$0.250
|
$0.420
|
|
|
RUMBLE STRIPS (CENTERLINE)
|
LF
|
38,553.000
|
$0.180
|
$0.500
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
50.000
|
$40.000
|
$38.750
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
2.000
|
$2,000.000
|
$2,310.000
|
|
|
DOWNSTREAM ANCHOR TERMINAL SECTION
|
EA
|
1.000
|
$2,200.000
|
$1,575.000
|
|
|
TL-3 31" SHORT RADIUS (POSTS 2 THRU 7)
|
EA
|
1.000
|
$1,000.000
|
$19,215.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
1.000
|
$3,200.000
|
$3,255.000
|
|
|
CRASH CUSH ATTEN (MOVE & RESET)
|
EA
|
2.000
|
$2,800.000
|
$1,995.000
|
|
|
CRASH CUSH ATTEN (REMOVE)
|
EA
|
2.000
|
$1,300.000
|
$945.000
|
|
|
CRASH CUSH ATTEN (INSTL)(S)(W)(TL3)
|
EA
|
2.000
|
$9,000.000
|
$10,490.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
23.000
|
$436.000
|
$630.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
|
EA
|
2.000
|
$605.000
|
$729.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(P)
|
EA
|
4.000
|
$710.000
|
$939.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(T)
|
EA
|
2.000
|
$770.000
|
$1,044.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(U)
|
EA
|
1.000
|
$705.000
|
$1,207.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
34.000
|
$77.000
|
$132.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(P-1EXT)
|
EA
|
2.000
|
$710.000
|
$1,105.000
|
|
|
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
|
EA
|
9.000
|
$31.520
|
$27.000
|
|
|
INSTL DEL ASSM (D-SW)SZ (BRF)GF1
|
EA
|
7.000
|
$20.000
|
$26.000
|
|
|
INSTL OM ASSN (OM-2Z)(WFLX)(WAP)
|
EA
|
14.000
|
$100.000
|
$136.000
|
|
|
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
|
LF
|
870.000
|
$50.000
|
$4.250
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
|
EA
|
4,113.000
|
$1.000
|
$9.170
|
|
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
|
LF
|
104.000
|
$4.000
|
$1.420
|
|
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
|
LF
|
79,497.000
|
$0.700
|
$0.860
|
|
RE PM W/RET REQ TY I (Y)6"(BRK)(100MIL)
|
LF
|
6,200.000
|
$0.700
|
$0.810
|
|
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
|
LF
|
45,508.000
|
$0.700
|
$0.890
|
|
REFL PAV MRKR TY I-C
|
EA
|
6.000
|
$10.000
|
$6.300
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
891.000
|
$5.000
|
$6.300
|
|
|
D-GR HMA TY-B PG64-22
|
TON
|
19,428.000
|
$130.000
|
$160.000
|
|
|
D-GR HMA TY-D PG64-22
|
TON
|
2,431.000
|
$180.000
|
$183.000
|
|
|
TACK COAT
|
GAL
|
3,439.000
|
$6.000
|
$12.000
|
|
|
TMA (STATIONARY)
|
DAY
|
88.000
|
$350.000
|
$527.000
|
|
|
TMA (MOBILE OPERATION)
|
DAY
|
20.000
|
$400.000
|
$550.000
|
|
Totals: |
$4,864,202.340
|
$6,193,763.910
|