JEFFERSON FM 365 (0932-01-090)

Items: 82

County: JEFFERSON
Length: N/A
Highway: FM 365
District: BEAUMONT
Control Number: 0932-01-090
DBE Goal: N/A
Project: BR 2018(955)
Guaranty: N/A
Time: 472 WORKING DAYS
Engineer's Estimate: $10,999,930.36
Date: 06/06/2018 (7 years ago)
Contract Number: N/A
Type: REPLACE BRIDGE AND APPROACHES
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (5)
E
Engineer's Estimate
$10,999,930.36
Over/Under Est: 33.23% $3,655,755.09
Over/Under Est: 40.12% $4,413,122.85
Amt Left: 5.17% $757,367.76
Over/Under Est: 45.6% $5,016,221.33
Amt Left: 9.28% $1,360,466.24
Delta: -3.91% -$603,098.48
Over/Under Est: 58.47% $6,431,388.95
Amt Left: 18.94% $2,775,633.86
Delta: -8.84% -$1,415,167.62
Over/Under Est: 115.52% $12,706,940.63
Amt Left: 61.76% $9,051,185.54
Delta: -36.00% -$6,275,551.68

Bid Items & Bid Tabulations

82 Total 0 of 82
JEFFERSON  |  FM 365  |  BEAUMONT  |  0932-01-090  |  06/06/2018  |  $10,999,930.36  |  BR 2018(955)  |  REPLACE BRIDGE AND APPROACHES  |  472 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
JENSEN CONSTRUCTION COMPANY OF TEXAS
RAGLE CONSTRUCTION, INC.
STERLING DELAWARE HOLDING COMPANY, INC.
OLDCASTLE MATERIALS TEXAS, INC.
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
PREPARING ROW
STA 23.500 $1,000.000 $15,000.000 $60,000.000 $33,000.000 $42,000.000 $100,000.000
EXCAVATION (ROADWAY)
CY 10,238.000 $10.000 $12.000 $18.000 $14.000 $11.000 $42.930
EMBANKMENT (FINAL)(DENS CONT)(TY A)
CY 4,052.000 $20.000 $15.000 $30.000 $22.000 $28.000 $42.930
EMBANKMENT (FINAL)(DENS CONT)(TY B)
CY 4,444.000 $5.000 $15.000 $40.000 $55.000 $28.000 $42.930
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 2,934.000 $12.000 $15.000 $50.000 $19.000 $29.000 $42.930
BLADING
HR 40.000 $70.000 $75.000 $25.000 $150.000 $160.000 $250.000
FURNISHING AND PLACING TOPSOIL (4")
SY 1,074.000 $1.000 $1.500 $2.500 $0.780 $5.600 $3.000
BROADCAST SEED (TEMP) (WARM)
SY 1,074.000 $0.300 $0.200 $0.200 $0.750 $0.800 $1.000
BROADCAST SEED (TEMP) (COOL)
SY 1,074.000 $0.300 $0.200 $0.250 $0.750 $0.800 $1.000
CELL FBR MLCH SEED(PERM)(RURAL)(CLAY)
SY 2,148.000 $0.300 $0.350 $0.300 $0.750 $0.800 $1.000
VEGETATIVE WATERING
MG 9.000 $15.000 $20.000 $150.000 $10.560 $250.000 $50.000
SOIL RETENTION BLANKETS (CL 1) (TY A)
SY 1,074.000 $1.000 $1.500 $2.000 $1.000 $1.050 $2.500
PROOF ROLLING
HR 40.000 $70.000 $75.000 $25.000 $60.000 $92.000 $150.000
FL BS (CMP IN PLC)(TYA GR1-2)(FNAL POS)
CY 1,690.000 $105.000 $75.000 $75.000 $85.000 $112.000 $100.000
ASPH (AC-20-5TR OR AC-20XP)
GAL 2,190.000 $3.050 $4.000 $4.500 $5.240 $11.000 $7.000
AGGR(TY-PD GR-4 OR TY-PL GR-4)
CY 48.000 $170.000 $200.000 $125.000 $104.740 $1,140.000 $135.000
D-GR HMA(SQ) TY-D PG76-22
TON 697.000 $170.000 $180.000 $100.000 $128.830 $175.000 $115.000
PLANE ASPH CONC PAV(0" TO 2")
SY 824.000 $2.000 $3.000 $4.600 $5.250 $6.650 $7.000
PLANE ASPH CONC PAV(8" TO 10")
SY 4,458.000 $3.000 $3.000 $6.250 $6.500 $7.100 $12.000
CEM STABIL BKFL
CY 161.100 $60.000 $65.000 $80.000 $85.000 $110.000 $60.000
TEMPORARY SPL SHORING
SF 23,570.000 $15.000 $1.000 $5.000 $8.000 $22.000 $20.000
FOUNDATION LOAD TEST (D4945) (PILE)
EA 6.000 $2,500.000 $50,000.000 $5,500.000 $20,000.000 $6,725.000 $15,000.000
SHEET PILING (PZ - 27)
SF 47,261.000 $35.000 $63.000 $45.000 $58.000 $44.000 $125.000
SHEET PILING (PZ - 40)
SF 15,589.000 $50.000 $80.000 $51.000 $80.000 $70.000 $130.000
PRESTR CONC PIL (16 IN SQ)
LF 1,364.000 $90.000 $50.000 $85.000 $160.000 $156.000 $150.000
PRESTR CONC PIL (24 IN SQ)
LF 10,688.000 $120.000 $80.000 $105.000 $182.000 $160.000 $150.000
CL C CONC (ABUT)
CY 63.300 $840.000 $1,400.000 $1,000.000 $1,125.000 $1,800.000 $1,500.000
CL C CONC (CAP)
CY 565.800 $965.000 $1,400.000 $1,200.000 $1,070.000 $1,860.000 $1,500.000
REINF CONC SLAB
SF 72,240.000 $17.000 $22.000 $20.000 $21.000 $37.000 $25.000
APPROACH SLAB
CY 102.600 $450.000 $500.000 $390.000 $500.000 $1,190.000 $400.000
PRESTR CONC GIRDER (TX28)
LF 3,336.600 $110.000 $170.000 $170.000 $195.000 $160.000 $125.000
PRESTR CONC GIRDER (TX34)
LF 6,916.920 $130.000 $190.000 $175.000 $195.000 $160.000 $135.000
RIPRAP (CONC)(4 IN)
CY 161.000 $375.000 $300.000 $375.000 $400.000 $640.000 $550.000
RIPRAP (MOW STRIP)(4 IN)
CY 16.000 $500.000 $400.000 $420.000 $400.000 $730.000 $550.000
STR STEEL (MISC NON - BRIDGE)
LB 105,000.000 $7.000 $4.000 $1.500 $6.250 $3.500 $3.000
RAIL (TY T223)
LF 2,632.000 $100.000 $90.000 $80.000 $100.000 $180.000 $65.000
SEALED EXPANSION JOINT (4 IN) (SEJ - A)
LF 386.200 $92.000 $200.000 $75.000 $110.000 $105.000 $100.000
REMOV STR (BRIDGE 500 - 999 FT LENGTH)
EA 1.000 $400,000.000 $750,000.000 $1,500,000.000 $280,000.000 $580,000.000 $689,176.000
MOBILIZATION
LS 1.000 $515,318.110 $1,475,000.000 $1,500,000.000 $1,600,000.000 $1,601,000.000 $2,600,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 31.000 $5,750.000 $1,100.000 $19,250.000 $1,500.000 $5,100.000 $15,000.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 200.000 $28.000 $30.000 $28.000 $32.500 $33.000 $50.000
ROCK FILTER DAMS (REMOVE)
LF 200.000 $7.750 $8.000 $8.000 $8.000 $8.100 $10.000
BACKHOE WORK (EROSION & SEDMT CONT)
HR 40.000 $75.000 $110.000 $25.000 $125.000 $195.000 $150.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 3,086.000 $2.750 $6.000 $2.250 $2.750 $2.800 $5.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 3,086.000 $0.850 $2.000 $1.000 $0.750 $0.800 $1.000
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 180.000 $4.500 $7.000 $4.000 $4.500 $4.550 $10.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 180.000 $1.500 $2.000 $1.000 $1.000 $1.050 $2.000
CONSTRUCTING DETOURS
SY 552.000 $50.000 $100.000 $75.000 $120.000 $80.000 $100.000
ONE-WAY TRAF CONT (FLAGGER CONT)
HR 16.000 $60.000 $50.000 $150.000 $65.000 $56.000 $183.000
ONE-WAY TRAF CONT (PORT TRAF SIG)
MO 1.000 $1,000.000 $10,000.000 $10,000.000 $8,000.000 $6,360.000 $9,720.000
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
LF 3,120.000 $35.000 $70.000 $68.000 $70.000 $65.000 $50.000
PORT CTB (MOVE)(SGL SLP)(TY 1)
LF 4,200.000 $20.000 $8.000 $5.000 $9.000 $6.500 $7.000
PORT CTB (STKPL)(SGL SLP)(TY 1)
LF 3,120.000 $5.500 $8.000 $6.000 $9.000 $15.000 $7.000
MTL W-BEAM GD FEN (STEEL POST)
LF 1,650.000 $22.000 $26.500 $26.500 $23.500 $24.000 $26.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $1,650.000 $1,854.000 $1,854.000 $1,635.000 $1,650.000 $1,900.000
REMOVE METAL BEAM GUARD FENCE
LF 714.000 $3.500 $4.000 $4.000 $2.500 $2.650 $5.500
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $2,250.000 $2,275.000 $2,275.000 $2,300.000 $2,400.000 $2,500.000
GUARDRAIL END TREATMENT (REMOVE)
EA 4.000 $400.000 $250.000 $250.000 $275.000 $280.000 $425.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 8.000 $1,750.000 $2,500.000 $2,047.440 $1,500.000 $1,510.000 $3,000.000
CRASH CUSH ATTEN (REMOVE)
EA 8.000 $1,000.000 $1,500.000 $911.190 $900.000 $910.000 $800.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 8.000 $10,000.000 $9,000.000 $9,100.000 $8,500.000 $8,600.000 $8,500.000
CONDT (HDPE) (4") BORE
LF 1,900.000 $25.000 $45.960 $20.000 $35.000 $21.000 $125.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 2.000 $450.000 $500.000 $474.470 $446.000 $450.000 $1,000.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 2.000 $565.000 $700.000 $564.190 $475.000 $480.000 $1,200.000
REMOVE SM RD SN SUP&AM
EA 4.000 $95.000 $90.000 $95.440 $75.000 $78.000 $250.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 28.000 $20.000 $28.000 $28.000 $15.000 $21.000 $10.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 20.000 $30.000 $45.000 $45.000 $27.500 $41.000 $20.000
WK ZN PAV MRK REMOV (REFL) TY II-A-A
EA 420.000 $3.500 $0.300 $3.490 $3.000 $3.050 $6.000
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 13,552.000 $0.600 $0.600 $0.650 $0.420 $0.450 $1.500
WK ZN PAV MRK REMOV (W)24"(SLD)
LF 20.000 $5.000 $20.000 $7.510 $6.000 $6.100 $9.000
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 16,752.000 $0.650 $0.700 $0.640 $0.420 $0.450 $1.500
PAVEMENT SEALER 4"
LF 530.000 $0.250 $0.300 $0.130 $0.150 $0.160 $0.380
RE PM W/RET REQ TY I (W)4"(SLD)(090MIL)
LF 2,757.000 $0.350 $0.400 $0.280 $0.410 $0.430 $0.750
RE PM W/RET REQ TY I (Y)4"(BRK)(090MIL)
LF 2,000.000 $0.350 $0.400 $0.300 $0.410 $0.430 $0.750
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
LF 12,840.000 $0.350 $0.400 $0.310 $0.380 $0.400 $0.750
REFL PAV MRKR TY II-A-A
EA 530.000 $3.750 $4.000 $2.980 $3.000 $3.100 $4.500
ELIM EXT PAV MRK & MRKS (4")
LF 8,160.000 $0.500 $0.600 $0.350 $0.350 $0.370 $1.500
PAV SURF PREP FOR MRK (4")
LF 7,980.000 $0.130 $0.020 $0.050 $0.010 $0.010 $0.380
WICK DRAINS
LF 107,445.000 $3.000 $0.750 $1.250 $0.630 $3.000 $4.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $8,750.000 $10,000.000 $16,000.000 $18,000.000 $22,635.000 $10.000
TMA (STATIONARY)
DAY 11.000 $220.000 $175.000 $175.000 $360.000 $750.000 $458.000
TMA (MOBILE OPERATION)
HR 24.000 $25.000 $40.000 $125.000 $70.000 $47.000 $126.000
Totals: $10,999,930.360 $14,655,685.450 $15,413,053.210 $16,016,151.690 $17,431,319.310 $23,706,870.990