County: JEFFERSON Highway: VA Date: 04/04/2023 (1 year ago) Engineer's Estimate: $1,669,968 Control Number: 0920-00-152
Project: F 2023(754) District: BEAUMONT Time: 58 WORKING DAYS Type: HAZARD ELIMINATION & SAFETY
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6 | 7
Plans: Plans | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $1,669,967.65
INTERSTATE BARRICADES & MARKINGS, INC.   $1,099,185.60 1
-34.18% | -$570,782.05
TRP CONSTRUCTION GROUP, LLC   $1,192,698.00 2
-28.58% | -$477,269.65
8.51% | $93,512.40

Bid Items

Items: 42, 0 filtered
JEFFERSON VA  |  BEAUMONT  |  0920-00-152  |  04/04/2023  |  $1,669,968  |  F 2023(754)  |  HAZARD ELIM & SAFETY  |  58 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate INTERSTATE BARRICADES & MARKINGS, INC. TRP CONSTRUCTION GROUP, LLC
500 6001 MOBILIZATION LS 1.000 $217,956.940 $50,000.000 $10,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 4.000 $8,447.780 $1.000 $250.000
666 6035 REFL PAV MRK TY I (W)8"(SLD)(090MIL) LF 6,520.000 $1.100 $0.750 $0.800
666 6161 RE PV MRK TY I(BLACK)6"(SHADOW)(090MIL) LF 103,020.000 $1.000 $0.650 $0.600
666 6225 PAVEMENT SEALER 6" LF 967,570.000 $0.180 $0.180 $0.150
666 6226 PAVEMENT SEALER 8" LF 6,520.000 $0.280 $0.220 $0.500
666 6228 PAVEMENT SEALER 12" LF 592.000 $0.990 $0.500 $1.000
666 6230 PAVEMENT SEALER 24" LF 7,490.000 $1.250 $1.000 $1.500
666 6231 PAVEMENT SEALER (ARROW) EA 323.000 $37.000 $10.000 $25.000
666 6232 PAVEMENT SEALER (WORD) EA 46.000 $46.000 $10.000 $25.000
666 6234 PAVEMENT SEALER (DBL ARROW) EA 5.000 $80.000 $15.000 $45.000
666 6236 PAVEMENT SEALER (UTURN ARROW) EA 4.000 $226.000 $20.000 $45.000
666 6242 PAVEMENT SEALER (RR XING) EA 12.000 $319.640 $50.000 $100.000
666 6243 PAVEMENT SEALER (YLD TRI) EA 54.000 $200.000 $1.000 $15.000
666 6305 RE PM W/RET REQ TY I (W)6"(BRK)(090MIL) LF 105,860.000 $0.490 $0.450 $0.600
666 6308 RE PM W/RET REQ TY I (W)6"(SLD)(090MIL) LF 359,020.000 $0.520 $0.450 $0.600
666 6317 RE PM W/RET REQ TY I (Y)6"(BRK)(090MIL) LF 40,650.000 $0.490 $0.450 $0.600
666 6320 RE PM W/RET REQ TY I (Y)6"(SLD)(090MIL) LF 359,020.000 $0.520 $0.450 $0.600
668 6074 PREFAB PAV MRK TY C (W) (12") (SLD) LF 592.000 $7.250 $4.000 $7.500
668 6076 PREFAB PAV MRK TY C (W) (24") (SLD) LF 2,405.000 $13.810 $8.000 $11.000
668 6077 PREFAB PAV MRK TY C (W) (ARROW) EA 323.000 $224.000 $175.000 $190.000
668 6078 PREFAB PAV MRK TY C (W) (DBL ARROW) EA 5.000 $325.000 $250.000 $275.000
668 6080 PREFAB PAV MRK TY C (W) (UTURN ARROW) EA 4.000 $446.000 $225.000 $300.000
668 6085 PREFAB PAV MRK TY C (W) (WORD) EA 46.000 $269.000 $200.000 $300.000
668 6089 PREFAB PAV MRK TY C (W) (RR XING) EA 12.000 $624.850 $550.000 $650.000
668 6092 PREFAB PAV MRK TY C (W) (36")(YLD TRI) EA 54.000 $28.000 $25.000 $50.000
668 6108 PREFAB PAV MRK TY C (Y) (24") (SLD) LF 5,085.000 $13.270 $8.000 $11.000
672 6007 REFL PAV MRKR TY I-C EA 4,835.000 $4.730 $5.000 $4.000
672 6009 REFL PAV MRKR TY II-A-A EA 4,119.000 $4.000 $5.000 $4.000
672 6010 REFL PAV MRKR TY II-C-R EA 460.000 $4.090 $5.000 $4.000
677 6001 ELIM EXT PAV MRK & MRKS (4") LF 967,570.000 $0.320 $0.190 $0.150
677 6003 ELIM EXT PAV MRK & MRKS (8") LF 6,520.000 $0.640 $0.300 $0.400
677 6005 ELIM EXT PAV MRK & MRKS (12") LF 592.000 $0.820 $0.400 $1.500
677 6007 ELIM EXT PAV MRK & MRKS (24") LF 7,490.000 $3.400 $0.500 $3.000
677 6008 ELIM EXT PAV MRK & MRKS (ARROW) EA 323.000 $25.000 $20.000 $35.000
677 6009 ELIM EXT PAV MRK & MRKS (DBL ARROW) EA 5.000 $27.600 $30.000 $50.000
677 6012 ELIM EXT PAV MRK & MRKS (WORD) EA 46.000 $30.000 $65.000 $45.000
677 6016 ELIM EXT PAV MRK & MRKS (RR XING) EA 12.000 $76.590 $100.000 $150.000
677 6019 ELIM EXT PAV MRK & MRKS (36")(YLD TRI) EA 54.000 $17.390 $10.000 $30.000
677 6036 ELIM EXT PAV MRK & MRKS (UTURN ARROW) EA 4.000 $43.000 $25.000 $100.000
6185 6002 TMA (STATIONARY) DAY 18.000 $188.250 $100.000 $250.000
6185 6005 TMA (MOBILE OPERATION) DAY 122.000 $400.000 $100.000 $150.000
Totals: $1,669,967.65 $1,099,185.60 $1,192,698.00