Job Info for 0920-00-123

County: JEFFERSON Highway: VA Date: 10/03/2019 (5 years ago) Engineer's Estimate: $1,030,710 Control Number: 0920-00-123
Project: NH 2020(021) District: BEAUMONT Time: 259 WORKING DAYS Type: LANDSCAPING & SCENIC ENHANCEMENT

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $1,030,710.20
APEX LANDSCAPE & IRRIGATION, LLC   $924,999.88 1
-10.26% | -$105,710.32
TIGHT LINE CONSTRUCTION, LLC   $1,183,941.63 2
14.87% | $153,231.43
27.99% | $258,941.75
ENVIRONMENTAL SOUTHWEST   $1,353,282.00 3
31.3% | $322,571.80
46.3% | $428,282.12
14.30% | $169,340.37

Bid Items

Items: 23, 0 filtered
JEFFERSON VA  |  BEAUMONT  |  0920-00-123  |  10/03/2019  |  $1,030,710  |  NH 2020(021)  |  LANDSCAPING & SCENIC ENHAN  |  259 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate APEX LANDSCAPE & IRRIGATION, LLC TIGHT LINE CONSTRUCTION, LLC ENVIRONMENTAL SOUTHWEST
100 6001 PREPARING ROW AC 11.030 $10,000.000 $2,500.000 $7,500.000 $9,500.000
168 6001 VEGETATIVE WATERING MG 2,649.400 $10.000 $0.010 $0.010 $10.000
192 6003 PLANT MATERIAL (3-GAL) EA 7,985.000 $20.000 $23.000 $17.000 $25.000
192 6004 PLANT MATERIAL (5-GAL) EA 7,985.000 $25.000 $23.000 $28.000 $30.000
192 6006 PLANT MATERIAL (30-GAL) EA 549.000 $200.000 $225.000 $250.000 $290.000
192 6007 PLANT MATERIAL (45-GAL) EA 35.000 $300.000 $350.000 $400.000 $400.000
192 6012 MULCH CY 972.000 $50.000 $15.000 $45.000 $200.000
192 6071 PLANT MATERIAL (10-GAL) EA 3,774.000 $30.000 $80.000 $75.000 $60.000
193 6001 PLANT MAINTENANCE MO 9.000 $3,000.000 $3,500.000 $6,000.000 $4,000.000
193 6004 PLANT REPLACEMENT (3-GAL) EA 159.000 $20.000 $1.000 $1.000 $3.000
193 6005 PLANT REPLACEMENT (5-GAL) EA 159.000 $25.000 $1.000 $1.000 $3.000
193 6006 VEGETATIVE WATERING MG 14.800 $10.000 $0.010 $0.010 $10.000
193 6010 PLANT REPLACEMENT (30 GAL) EA 56.000 $200.000 $1.000 $225.000 $20.000
193 6016 PLANT REPLACEMENT (45 GAL) EA 5.000 $300.000 $1.000 $450.000 $30.000
193 6020 PLANT REPLACEMENT (10 GAL) EA 378.000 $30.000 $0.100 $1.000 $7.000
500 6001 MOBILIZATION LS 1.000 $91,428.200 $26,617.450 $175,000.000 $115,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 18.000 $2,500.000 $1,000.000 $1,000.000 $1,000.000
506 6002 ROCK FILTER DAMS (INSTALL) (TY 2) LF 100.000 $10.000 $1.000 $1.000 $6.000
506 6011 ROCK FILTER DAMS (REMOVE) LF 100.000 $5.000 $1.000 $1.000 $4.000
506 6030 BACKHOE WORK (EROSION & SEDMT CONT) HR 20.000 $100.000 $1.000 $1.000 $50.000
506 6042 BIODEG EROSN CONT LOGS (INSTL) (18") LF 400.000 $5.000 $1.000 $1.000 $5.000
506 6043 BIODEG EROSN CONT LOGS (REMOVE) LF 400.000 $1.000 $1.000 $1.000 $1.000
6185 6002 TMA (STATIONARY) DAY 259.000 $200.000 $1.000 $1.000 $40.000
Totals: $1,030,710.20 $924,999.89 $1,183,941.64 $1,353,282.00