JEFFERSON US 69 (0200-14-093)

Items: 102

County: JEFFERSON
Length: N/A
Highway: US 69
District: BEAUMONT
Control Number: 0200-14-093
DBE Goal: N/A
Project: F 2022(893)
Guaranty: N/A
Time: 279 WORKING DAYS
Engineer's Estimate: $10,405,752.05
Date: 08/04/2022 (3 years ago)
Contract Number: N/A
Type: SURFACING/ROADWAY RESTORATION
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$10,405,752.05
$10,175,549.20
Over/Under Est: -2.21% -$230,202.85
Over/Under Est: 7.77% $808,526.10
Amt Left: 10.21% $1,038,728.95
Over/Under Est: 29.39% $3,058,408.69
Amt Left: 32.32% $3,288,611.54
Delta: -20.06% -$2,249,882.59
Subcontractor Percentage Amount
TEX-BRASKA, LLC 3.78% $376,987.41
AMERICAN REMEDIATION OPTIONS, INC. 1.18% $117,683.90
AREA WIDE PROTECTIVE, INC. 1.14% $113,694.62
PINNACLE GRINDING AND GROOVING LLC 0.82% $81,780.34
MASON CONSTRUCTION, LLC 0.60% $59,839.27
TRAFFIC SIGNS & LINES, LLC 0.42% $41,887.49
HOLES-GOLDEN TRIANGLE LLC 0.20% $19,946.42
HOLLIER CONSTRUCTION CO. 0.12% $11,967.85
TRP CONSTRUCTION GROUP, LLC 0.06% $5,983.93
Total: 8.32% $829,771.23

Bid Items & Bid Tabulations

102 Total 0 of 102
JEFFERSON  |  US 69  |  BEAUMONT  |  0200-14-093  |  08/04/2022  |  $10,405,752.05  |  F 2022(893)  |  SURF/ROADWAY RESTOR  |  279 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ELITE CONTRACTORS AND EQUIPMENT LTD
TEXAS MATERIALS GROUP, INC.
RAGLE CONSTRUCTION, INC.
REMOVING CONC (PAV)
SY 38,118.000 $13.000 $7.000 $8.000 $14.750
REMOVING CONC (DRIVEWAYS)
SY 963.000 $18.200 $10.000 $38.000 $20.000
REMOVING CONC (CURB)
LF 16,997.000 $10.120 $3.000 $1.100 $5.000
REMOVING STAB BASE & ASPH PAV (8"-10")
SY 698.000 $5.000 $6.000 $16.000 $12.000
EXCAVATION (ROADWAY)
CY 12,518.000 $20.970 $21.500 $23.000 $110.000
BACKFILL (TY B)
STA 91.900 $238.920 $400.000 $817.000 $200.000
BLOCK SODDING
SY 16,070.000 $4.940 $5.500 $5.100 $6.400
CELL FBR MLCH SEED(PERM)(URBAN)(CLAY)
SY 54,912.000 $0.360 $0.400 $0.380 $0.350
VEGETATIVE WATERING
MG 1,349.000 $22.010 $10.000 $15.000 $17.500
LIME (HYD, COM, OR QK(SLURRY))
TON 487.000 $329.210 $300.000 $395.000 $225.000
LIME TRT (SUBGRADE)(6")
SY 36,058.000 $4.820 $3.300 $6.250 $3.800
CM TRT(PT MX)(CL L)(TYD)(GR1-2)(FN POS)
CY 805.000 $70.000 $135.000 $164.000 $125.000
CEM TRT(PLNT MX) (CL L)(TYD)(GR1-2)(6")
SY 36,058.000 $14.000 $26.500 $26.500 $19.500
PRIME COAT (AE-P)
GAL 7,695.000 $3.960 $13.000 $10.000 $5.500
CONC PVMT (CONT REINF - CRCP) (10")
SY 34,614.000 $89.470 $100.000 $122.000 $111.000
CONC PVMT (CONT REINF)(FAST TRK)(13")
SY 5,049.000 $123.250 $150.000 $146.000 $250.000
CEM STABIL BKFL
CY 1,398.000 $168.090 $95.000 $117.000 $80.000
CUT & RESTORE CONC PAVING
SY 152.000 $287.170 $150.000 $455.000 $175.000
CEMENT STAB BACKFILL (INLET OR MH)
CY 213.000 $56.980 $95.000 $168.000 $56.000
TRENCH EXCAVATION PROTECTION
LF 2,083.000 $2.950 $3.000 $36.500 $1.000
CL C CONC (COLLAR)
EA 28.000 $1,010.000 $1,500.000 $610.000 $800.000
RIPRAP (CONC)(5 IN)
CY 26.000 $508.250 $600.000 $640.000 $575.000
RIPRAP (STONE COMMON)(DRY)(6 IN)
CY 4.000 $120.000 $1,000.000 $285.000 $600.000
CONC BOX CULV (4 FT X 4 FT)
LF 944.000 $420.000 $370.000 $560.000 $450.000
CONC BOX CULV (5 FT X 4 FT)
LF 588.000 $600.000 $465.000 $735.000 $550.000
RC PIPE (CL III)(18 IN)
LF 36.000 $89.420 $100.000 $103.000 $260.000
RC PIPE (CL III)(24 IN)
LF 176.000 $103.760 $95.000 $121.000 $165.000
RC PIPE (CL III)(30 IN)
LF 188.000 $130.070 $120.000 $143.000 $120.000
RC PIPE (CL III)(36 IN)
LF 48.000 $147.820 $165.000 $172.000 $145.000
RC PIPE (CL III)(42 IN)
LF 8.000 $187.790 $300.000 $283.000 $395.000
RC PIPE (CL III)(60 IN)
LF 4.000 $420.960 $500.000 $1,610.000 $890.000
JCTBOX(COMPL)(PJB)(3FTX3FT)
EA 1.000 $3,948.790 $5,400.000 $6,750.000 $6,600.000
JCTBOX(COMPL)(PJB)(8FTX8FT)
EA 1.000 $15,269.120 $20,000.000 $23,150.000 $17,000.000
INLET (COMPL)(PCO)(3FT)(NONE)
EA 1.000 $5,641.820 $6,850.000 $6,975.000 $7,200.000
INLET (COMPL)(PCO)(3FT)(LEFT)
EA 1.000 $6,698.700 $8,000.000 $9,500.000 $8,400.000
INLET (COMPL)(PCO)(3FT)(RIGHT)
EA 6.000 $7,344.020 $7,400.000 $8,600.000 $8,400.000
INLET (COMPL)(PCO)(3FT)(BOTH)
EA 12.000 $12,200.000 $7,400.000 $8,900.000 $9,000.000
INLET (COMPL)(PSL)(FG)(4FTX4FT-4FTX4FT)
EA 3.000 $6,663.600 $7,500.000 $10,000.000 $8,400.000
INLET (COMPL)(PSL)(FG)(6FTX6FT-3FTX3FT)
EA 3.000 $7,738.200 $12,000.000 $12,700.000 $10,250.000
SET (TY II) (24 IN) (RCP) (3: 1) (C)
EA 2.000 $1,325.000 $1,500.000 $1,365.000 $1,875.000
PIPE (PVC) (SCH 80) (6 IN)
LF 519.000 $14.120 $50.000 $92.000 $18.000
REMOV STR (INLET)
EA 28.000 $667.400 $600.000 $1,215.000 $950.000
REMOV STR (PIPE)
LF 1,618.000 $20.700 $15.000 $29.500 $20.000
MOBILIZATION
LS 1.000 $1,357,272.010 $900,000.000 $538,100.000 $1,350,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 19.000 $8,987.770 $5,000.000 $3,800.000 $43,500.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 30.000 $32.800 $50.000 $51.000 $67.680
ROCK FILTER DAMS (REMOVE)
LF 30.000 $8.770 $20.000 $20.250 $29.580
TEMP SEDMT CONT FENCE (INSTALL)
LF 750.000 $2.730 $3.000 $3.530 $7.840
TEMP SEDMT CONT FENCE (REMOVE)
LF 945.000 $1.250 $1.000 $1.020 $1.050
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 345.000 $6.460 $5.000 $5.600 $8.850
BIODEG EROSN CONT LOGS (REMOVE)
LF 345.000 $1.120 $1.000 $1.520 $2.610
TEMP SDMT CONT FENCE (INLET PROTECTION)
LF 195.000 $10.150 $10.000 $7.100 $13.650
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
LF 200.000 $26.190 $130.000 $14.500 $110.000
PORT CTB (FUR & INST)(LOW PROF)(TY 1)
LF 3,560.000 $83.330 $85.000 $26.250 $110.000
PORT CTB (FUR & INST)(LOW PROF)(TY 2)
LF 140.000 $51.560 $85.000 $97.000 $110.000
PORT CTB (MOVE)(LOW PROF)(TY 1)
LF 12,780.000 $6.680 $6.000 $5.700 $8.500
PORT CTB (MOVE)(LOW PROF)(TY 2)
LF 560.000 $9.530 $6.000 $13.000 $12.000
PORT CTB (REMOVE)(SGL SLP)(TY 1)
LF 200.000 $7.800 $50.000 $36.500 $16.000
PORT CTB (REMOVE)(LOW PROF)(TY 1)
LF 3,560.000 $7.880 $8.000 $15.000 $10.000
PORT CTB (REMOVE)(LOW PROF)(TY 2)
LF 140.000 $9.190 $8.000 $25.500 $12.000
CONC CURB (MONO) (TY I)
LF 147.000 $4.080 $10.000 $58.000 $15.000
CONC CURB (MONO) (TY II)
LF 17,583.000 $15.330 $5.000 $10.250 $6.000
DRIVEWAYS (CONC)
SY 761.000 $86.690 $100.000 $135.000 $105.000
CRASH CUSH ATTEN (REMOVE)
EA 1.000 $958.220 $1,200.000 $910.000 $1,500.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 1.000 $10,636.840 $12,000.000 $9,900.000 $10,500.000
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 54.000 $650.000 $600.000 $514.000 $450.000
WK ZN PAV MRK REMOV (W)4"(BRK)
LF 5,440.000 $0.850 $3.000 $3.000 $2.970
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 10,059.000 $0.810 $2.000 $1.470 $1.450
WK ZN PAV MRK REMOV (W)8"(SLD)
LF 4,052.000 $1.450 $4.000 $2.920 $2.890
WK ZN PAV MRK REMOV (W)24"(SLD)
LF 17.000 $8.760 $25.000 $35.600 $35.210
REFL PAV MRK TY I (W)4"(DOT)(090MIL)
LF 69.000 $1.450 $2.000 $1.040 $1.000
REFL PAV MRK TY I (W)8"(DOT)(090MIL)
LF 240.000 $1.960 $3.000 $2.050 $2.000
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
LF 3,176.000 $0.970 $1.000 $1.520 $1.480
PAVEMENT SEALER 4"
LF 6,044.000 $0.150 $0.500 $0.230 $0.220
PAVEMENT SEALER 8"
LF 3,416.000 $0.280 $0.500 $0.440 $0.430
RE PM W/RET REQ TY I (W)4"(BRK)(090MIL)
LF 3,610.000 $0.440 $1.000 $0.750 $0.740
RE PM W/RET REQ TY I (W)4"(SLD)(090MIL)
LF 745.000 $0.380 $1.000 $0.750 $0.740
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
LF 1,620.000 $0.380 $1.000 $0.720 $0.710
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 357.000 $13.440 $22.000 $17.100 $16.910
PREFAB PAV MRK TY C (W) (UTURN ARROW)
EA 5.000 $350.000 $600.000 $512.000 $506.200
PREFAB PAV MRK TY C (W) (LNDP ARROW)
EA 3.000 $450.300 $700.000 $695.000 $684.780
PREFAB PAV MRK TY C (W) (WORD)
EA 5.000 $272.510 $400.000 $385.000 $379.960
PREFAB PAV MRK TY C (W) (RR XING)
EA 5.000 $667.330 $1,100.000 $735.000 $727.360
PREFAB PAV MRK TY C (W) (36")(YLD TRI)
EA 18.000 $36.560 $65.000 $32.950 $32.620
PREFAB PAV MRK TY C (Y) (24") (SLD)
LF 147.000 $12.060 $30.000 $18.300 $18.110
REFL PAV MRKR TY II-A-A
EA 12.000 $4.570 $10.000 $3.720 $3.670
REFL PAV MRKR TY II-C-R
EA 284.000 $3.800 $6.000 $3.720 $3.670
PAV SURF PREP FOR MRK (4")
LF 6,044.000 $0.200 $0.500 $0.100 $0.090
PAV SURF PREP FOR MRK (8")
LF 3,416.000 $0.130 $0.750 $0.160 $0.150
PAV SURF PREP FOR MRK (24")
LF 504.000 $0.860 $3.000 $0.920 $0.910
PAV SURF PREP FOR MRK (UTURN ARR)
EA 5.000 $35.980 $50.000 $12.400 $12.210
PAV SURF PREP FOR MRK (WORD)
EA 5.000 $18.840 $50.000 $9.150 $9.040
PAV SURF PREP FOR MRK (RR XING)
EA 5.000 $24.570 $60.000 $26.500 $26.220
PAV SURF PREP FOR MRK (SYMBOL)
EA 9.000 $22.890 $50.000 $32.900 $32.550
PAV SURF PREP FOR MRK (36")(YLD TRI)
EA 18.000 $9.470 $10.000 $0.690 $0.680
DITCH CLEANING AND RESHAPING (FOOT)
LF 75.000 $6.770 $20.000 $35.250 $20.000
DRAIN INLET CLEANING
EA 5.000 $195.970 $2,000.000 $5,810.000 $750.000
TACK COAT
GAL 3,847.000 $3.980 $13.000 $10.000 $8.000
D-GR HMA TY-D PG 64-22 (EXEMPT)
TON 2,116.000 $317.330 $280.000 $239.000 $175.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $10,621.260 $22,500.000 $23,000.000 $75,000.000
TMA (STATIONARY)
DAY 279.000 $268.730 $200.000 $322.000 $250.000
TMA (MOBILE OPERATION)
HR 80.000 $77.480 $100.000 $65.000 $60.000
Totals: $10,405,752.048 $10,175,549.200 $11,214,278.150 $13,464,160.740