Show Job Controls
Bid Cobra

JEFFERSON US 69 (0065-07-068)

Items: 76

County: JEFFERSON
Length: N/A
Highway: US 69
District: BEAUMONT
Control Number: 0065-07-068
DBE Goal: N/A
Project: F 2021(876)
Guaranty: N/A
Time: 71 WORKING DAYS
Engineer's Estimate: $1,163,978.22
Date: 08/04/2021 (4 years ago)
Contract Number: N/A
Type: HAZARD ELIMINATION & SAFETY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Documents:
Bidders (4)
E
Engineer's Estimate
$1,163,978.22
$1,241,805.44
Over/Under Est: 6.69% $77,827.22
Over/Under Est: 27.68% $322,194.24
Amt Left: 19.68% $244,367.02
$1,602,762.68
Over/Under Est: 37.7% $438,784.46
Amt Left: 29.07% $360,957.24
Delta: -7.84% -$116,590.22
$1,699,819.50
Over/Under Est: 46.04% $535,841.28
Amt Left: 36.88% $458,014.06
Delta: -6.06% -$97,056.82

Bid Items & Bid Tabulations

76 Total 0 of 76
JEFFERSON  |  US 69  |  BEAUMONT  |  0065-07-068  |  08/04/2021  |  $1,163,978.22  |  F 2021(876)  |  HAZARD ELIM & SAFETY  |  71 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
TEXAS MATERIALS GROUP, INC.
RAGLE CONSTRUCTION, INC.
PTSS INVESTMENTS, LLC
FNH CONSTRUCTION, LLC
REMOVING CONC (PAV)
SY 1,047.000 $8.500 $15.000 $14.000 $29.000 $20.000
REMOVING CONC (CURB)
LF 476.000 $6.000 $5.050 $6.000 $15.000 $20.000
OBLITERATING ABANDONED ROAD
SY 2,547.000 $15.000 $9.000 $6.010 $10.000 $20.000
EXCAVATION (ROADWAY)
CY 1,124.000 $15.000 $16.000 $45.000 $25.000 $20.000
BACKFILL (TY A OR B)
STA 10.410 $180.000 $340.000 $150.000 $400.000 $450.000
BLADING
HR 40.000 $150.000 $144.000 $100.000 $200.000 $200.000
CELL FBR MLCH SEED(PERM)(RURAL)(CLAY)
SY 1,652.000 $0.400 $1.030 $2.200 $2.000 $2.000
CELL FBR MLCH SEED(TEMP)(WARM)
SY 2,342.000 $0.400 $1.030 $1.370 $2.000 $2.000
VEGETATIVE WATERING
MG 13.800 $15.000 $70.000 $75.000 $10.000 $250.000
LIME TRT (SUBGRADE)(6")
SY 1,804.000 $5.000 $14.000 $9.000 $12.000 $15.000
PRIME COAT & BLOTTER (AE-P)
GAL 410.000 $6.000 $7.100 $6.000 $8.000 $10.000
D-GR HMA(SQ) TY-B PG64-22
TON 378.000 $100.000 $107.000 $150.000 $90.000 $100.000
D-GR HMA(SQ) TY-D PG64-22
TON 73.000 $100.000 $130.000 $220.000 $100.000 $140.000
CONC PVMT (CONT REINF - CRCP) (9")
SY 1,848.000 $80.000 $78.000 $115.000 $160.000 $85.000
CONC PVMT (CONT REINF)(FAST TRK)(14")
SY 1,288.000 $115.000 $119.000 $138.000 $165.000 $165.000
RIPRAP (STONE COMMON)(DRY)(6 IN)
CY 456.000 $180.000 $87.000 $175.000 $200.000 $185.000
BEDDING MATERIAL (3 IN)
CY 191.000 $82.000 $130.000 $20.000 $250.000 $80.000
RC PIPE (CL III)(18 IN)
LF 226.000 $85.000 $98.000 $80.000 $75.000 $18.000
JCTBOX(COMPL)(PJB)(4FTX4FT)
EA 2.000 $3,900.000 $7,050.000 $5,000.000 $6,000.000 $6,500.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 1.000 $1,605.000 $1,510.000 $1,500.000 $900.000 $1,850.000
ADJUSTING MANHOLES & INLETS
EA 2.000 $1,000.000 $3,525.000 $1,000.000 $1,500.000 $2,500.000
MOBILIZATION
LS 1.000 $100,000.000 $96,500.000 $140,000.000 $60,000.000 $170,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 5.000 $5,000.000 $1,800.000 $30,000.000 $8,500.000 $8,500.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 210.000 $4.500 $5.050 $11.600 $9.000 $18.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 210.000 $1.300 $1.030 $4.990 $2.000 $9.000
CONSTRUCTING DETOURS
SY 200.000 $80.000 $90.000 $50.000 $80.000 $45.000
PORT CTB (FUR & INST)(LOW PROF)(TY 1)
LF 580.000 $30.000 $71.000 $50.000 $95.000 $85.000
PORT CTB (FUR & INST)(LOW PROF)(TY 2)
LF 60.000 $30.000 $77.000 $55.000 $105.000 $85.000
PORT CTB (MOVE)(LOW PROF)(TY 1)
LF 580.000 $10.000 $8.000 $10.000 $9.000 $20.000
PORT CTB (MOVE)(LOW PROF)(TY 2)
LF 60.000 $10.000 $15.000 $10.000 $9.000 $20.000
PORT CTB (REMOVE)(LOW PROF)(TY 1)
LF 580.000 $10.000 $17.000 $11.000 $15.000 $20.000
PORT CTB (REMOVE)(LOW PROF)(TY 2)
LF 60.000 $10.000 $19.000 $11.000 $15.000 $20.000
COLORED TEXTURED CONC (6")
SY 2,312.000 $95.000 $106.000 $115.000 $90.000 $115.000
CONC CURB (TY I)
LF 1,041.000 $20.000 $21.500 $8.000 $35.000 $35.000
CONC CURB (TY II)
LF 1,769.000 $20.000 $21.500 $11.000 $50.000 $35.000
CURB RAMPS (TY 1)
EA 4.000 $2,000.000 $1,390.000 $1,400.000 $2,000.000 $2,500.000
CURB RAMPS (TY 21)
SY 2.000 $2,500.000 $2,325.000 $2,000.000 $3,000.000 $2,850.000
CONC DIRECTIONAL ISLAND
SY 231.000 $50.000 $104.000 $70.000 $120.000 $125.000
REMOVE RD IL ASM (U/P)
EA 8.000 $200.000 $255.000 $159.000 $250.000 $500.000
IN RD IL (U/P) (TY 1) (150W EQ) LED
EA 8.000 $1,000.000 $1,080.000 $777.000 $1,600.000 $6,500.000
CONDT (PVC) (SCH 80) (2")
LF 585.000 $8.000 $12.250 $15.390 $20.000 $15.000
CONDT (PVC) (SCH 80) (2") (BORE)
LF 162.000 $20.000 $18.250 $17.440 $60.000 $40.000
CONDT (RM) (3/4")
LF 360.000 $18.000 $32.500 $14.580 $38.000 $65.000
ELEC CONDR (NO.10) BARE
LF 360.000 $2.000 $1.480 $1.200 $2.200 $3.000
ELEC CONDR (NO.10) INSULATED
LF 720.000 $1.000 $1.630 $1.220 $2.800 $3.000
ELEC CONDR (NO.8) BARE
LF 814.000 $1.050 $1.680 $1.210 $2.250 $3.000
ELEC CONDR (NO.8) INSULATED
LF 1,628.000 $1.300 $1.980 $1.510 $2.300 $3.000
GROUND BOX TY A (122311)W/APRON
EA 10.000 $800.000 $860.000 $631.000 $1,300.000 $1,120.000
ELC SRV TY A 240/480 060(NS)SS(T)TP(O)
EA 1.000 $7,000.000 $6,400.000 $4,523.000 $10,000.000 $8,500.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 14.000 $500.000 $610.000 $500.000 $750.000 $850.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 12.000 $580.000 $710.000 $620.000 $800.000 $850.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 2.000 $750.000 $730.000 $740.000 $1,000.000 $850.000
IN SM RD SN SUP&AM TYS80(1)SA(U-BM)
EA 4.000 $850.000 $1,100.000 $1,065.000 $1,200.000 $850.000
IN BRIDGE MNT CLEARANCE SGN ASSM(TY N)
EA 2.000 $1,700.000 $1,775.000 $2,100.000 $3,200.000 $1,500.000
REMOVE SM RD SN SUP&AM
EA 14.000 $80.000 $76.000 $60.000 $100.000 $150.000
INSTL OM ASSM (OM-2Z)(WFLX)GND
EA 4.000 $50.000 $77.250 $80.000 $110.000 $100.000
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 7,451.000 $0.420 $0.300 $0.290 $0.250 $1.000
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
LF 1,775.000 $0.420 $0.610 $0.600 $0.700 $6.000
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 7,451.000 $0.420 $0.300 $0.290 $0.250 $1.000
REFL PAV MRK TY I (W)8"(DOT)(090MIL)
LF 35.000 $2.500 $1.480 $1.470 $2.200 $6.000
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
LF 1,775.000 $1.000 $1.480 $1.470 $2.000 $6.000
PAVEMENT SEALER 4"
LF 4,042.000 $0.240 $0.200 $0.190 $0.200 $1.000
PAVEMENT SEALER 8"
LF 1,775.000 $0.300 $0.380 $0.370 $0.400 $5.000
RE PM W/RET REQ TY I (W)4"(SLD)(090MIL)
LF 1,853.000 $0.350 $0.750 $0.740 $0.400 $1.000
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
LF 2,189.000 $0.250 $0.750 $0.740 $0.420 $1.000
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 144.000 $14.000 $17.100 $17.040 $20.000 $20.000
PREFAB PAV MRK TY C (W) (ARROW)
EA 8.000 $200.000 $269.000 $267.450 $250.000 $250.000
PREFAB PAV MRK TY C (W) (DBL ARROW)
EA 3.000 $340.000 $500.000 $498.090 $500.000 $500.000
PREFAB PAV MRK TY C (W) (UTURN ARROW)
EA 2.000 $330.000 $515.000 $510.260 $450.000 $250.000
PREFAB PAV MRK TY C (W) (WORD)
EA 8.000 $360.000 $385.000 $382.910 $300.000 $250.000
PREFAB PAV MRK TY C (W) (36")(YLD TRI)
EA 20.000 $32.000 $33.000 $32.880 $40.000 $250.000
REFL PAV MRKR TY II-A-A
EA 112.000 $3.100 $2.870 $2.840 $4.400 $5.000
ELIM EXT PAV MRK & MRKS (4")
LF 13,192.000 $0.400 $0.560 $0.550 $0.500 $1.000
ELIM EXT PAV MRK & MRKS (8")
LF 3,130.000 $0.600 $1.120 $1.100 $1.000 $1.000
TMA (STATIONARY)
DAY 150.000 $240.000 $265.000 $150.000 $150.000 $250.000
TMA (MOBILE OPERATION)
DAY 5.000 $220.000 $101.000 $250.000 $300.000 $850.000
Totals: $1,163,978.220 $1,241,805.440 $1,486,172.460 $1,602,762.680 $1,699,819.500