Job Info for 1090-01-027

County: JACKSON Highway: FM 530 Date: 03/04/2021 (3 years ago) Engineer's Estimate: $2,222,767 Control Number: 1090-01-027
Project: BR 2021(389) District: YOAKUM Time: 165 WORKING DAYS Type: REPLACE BRIDGE AND APPROACHES
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14
Plans

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $2,222,766.75
TREVWAY, INC.   $2,346,537.14 1
5.57% | $123,770.39
TIERRA LEASE SERVICE, LLC   $2,838,437.45 2
27.7% | $615,670.70
20.96% | $491,900.31
EARTH BUILDERS, L.P.   $2,996,709.65 3
34.82% | $773,942.90
27.71% | $650,172.51
5.58% | $158,272.20
FUQUA CONSTRUCTION CO., INC.   $3,259,587.02 4
46.65% | $1,036,820.27
38.91% | $913,049.88
8.77% | $262,877.37
Subcontractor Percentage Amount
SPECIALTY DRILLING, LLC 9.02% $211,657.65
SYLVA CONSTRUCTION, LLC 3.56% $83,536.72
DARKHORSE INDUSTRIES, L.L.C. 3.09% $72,508.00
HIGHWAY 1 LLC 2.38% $55,847.58
S & S BRIDGE PAINTING, INC. 1.56% $36,605.98
A K FUQUAY CONSTRUCTION 0.89% $20,884.18
A1 EROSION CONTROL 0.13% $3,050.50
Total: 20.63% $484,090.61

Bid Items

Items: 71, 0 filtered
JACKSON FM 530  |  YOAKUM  |  1090-01-027  |  03/04/2021  |  $2,222,767  |  BR 2021(389)  |  REPLACE BRIDGE AND APPROACHES  |  165 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate TREVWAY, INC. TIERRA LEASE SERVICE, LLC EARTH BUILDERS, L.P. FUQUA CONSTRUCTION CO., INC.
100 6002 PREPARING ROW STA 4.050 $3,000.000 $5,000.000 $5,000.000 $7,000.000 $16,487.340
110 6001 EXCAVATION (ROADWAY) CY 3,594.000 $14.000 $6.000 $10.000 $15.000 $16.530
132 6006 EMBANKMENT (FINAL)(DENS CONT)(TY C) CY 6,848.000 $7.500 $10.000 $25.000 $20.000 $16.270
150 6002 BLADING HR 50.000 $100.000 $15.000 $115.000 $125.000 $146.630
160 6003 FURNISHING AND PLACING TOPSOIL (4") SY 10,745.000 $1.000 $3.000 $3.500 $1.000 $4.210
164 6021 CELL FBR MLCH SEED(PERM)(RURAL)(SANDY) SY 29,576.000 $0.350 $0.420 $0.500 $0.500 $0.460
164 6029 CELL FBR MLCH SEED(TEMP)(WARM) SY 7,394.000 $0.350 $0.520 $0.400 $0.500 $0.460
164 6031 CELL FBR MLCH SEED(TEMP)(COOL) SY 7,394.000 $0.350 $0.520 $0.400 $0.500 $0.460
168 6001 VEGETATIVE WATERING MG 249.310 $40.000 $10.000 $10.000 $40.000 $48.220
169 6001 SOIL RETENTION BLANKETS (CL 1) (TY A) SY 3,090.000 $1.000 $2.000 $1.100 $2.500 $1.500
247 6057 FL BS (CMP IN PLC)(TYE GR1-2)(FNAL POS) CY 3,813.000 $65.000 $92.000 $90.000 $82.000 $79.420
275 6001 CEMENT TON 217.000 $150.000 $186.000 $155.000 $200.000 $170.400
275 6010 CEMENT TREAT (SUBGRADE) (8") SY 10,714.000 $3.000 $2.000 $1.750 $5.000 $6.750
310 6009 PRIME COAT (MC-30) GAL 1,779.000 $5.000 $7.000 $5.000 $7.000 $5.560
316 6246 AGGR(TY-PE GR-3 SAC-B) CY 105.000 $120.000 $290.000 $220.000 $330.000 $222.300
316 6249 AGGR(TY-PE GR-4 SAC-B) CY 69.000 $125.000 $300.000 $190.000 $300.000 $284.580
316 6400 ASPH (AC-15P OR AC-10-2TR OR CRS-2P) GAL 6,582.000 $3.500 $3.000 $3.750 $4.600 $4.100
400 6005 CEM STABIL BKFL CY 194.000 $80.000 $85.000 $150.000 $220.000 $262.820
403 6001 TEMPORARY SPL SHORING SF 485.000 $20.000 $35.000 $32.000 $25.000 $44.760
416 6004 DRILL SHAFT (36 IN) LF 1,070.000 $220.000 $336.000 $250.000 $250.000 $358.560
420 6013 CL C CONC (ABUT) CY 67.700 $1,000.000 $500.000 $1,250.000 $1,500.000 $1,598.400
420 6029 CL C CONC (CAP) CY 41.400 $1,150.000 $650.000 $1,500.000 $1,500.000 $1,598.400
420 6037 CL C CONC (COLUMN) CY 25.000 $1,150.000 $866.000 $1,550.000 $1,500.000 $1,958.400
422 6001 REINF CONC SLAB SF 15,640.000 $18.000 $15.000 $24.250 $25.000 $27.560
425 6039 PRESTR CONC GIRDER (TX54) LF 2,031.040 $130.000 $152.000 $150.000 $195.000 $181.920
432 6033 RIPRAP (STONE PROTECTION)(18 IN) CY 412.000 $150.000 $135.000 $240.000 $230.000 $215.270
450 6006 RAIL (TY T223) LF 728.000 $120.000 $81.000 $130.000 $110.000 $115.820
454 6018 SEALED EXPANSION JOINT (4 IN) (SEJ - M) LF 86.000 $110.000 $100.000 $135.000 $120.000 $123.200
464 6008 RC PIPE (CL III)(36 IN) LF 32.000 $125.000 $92.000 $175.000 $180.000 $232.800
467 6454 SET (TY II) (36 IN) (RCP) (6: 1) (P) EA 2.000 $4,000.000 $3,216.000 $3,000.000 $2,200.000 $3,718.800
496 6010 REMOV STR (BRIDGE 100 - 499 FT LENGTH) EA 1.000 $80,000.000 $100,000.000 $85,000.000 $100,000.000 $93,600.000
500 6001 MOBILIZATION LS 1.000 $200,000.000 $200,000.000 $325,000.000 $300,000.000 $297,171.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 11.000 $3,800.000 $700.000 $2,000.000 $1,000.000 $3,850.000
506 6001 ROCK FILTER DAMS (INSTALL) (TY 1) LF 170.000 $35.000 $10.000 $20.000 $45.000 $42.000
506 6011 ROCK FILTER DAMS (REMOVE) LF 170.000 $10.000 $2.000 $10.000 $10.000 $12.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 3,050.000 $3.000 $2.000 $3.000 $4.000 $3.300
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 3,050.000 $1.000 $0.500 $1.250 $1.000 $0.900
510 6003 ONE-WAY TRAF CONT (PORT TRAF SIG) MO 11.000 $5,000.000 $3,500.000 $4,000.000 $5,600.000 $3,630.000
512 6029 PORT CTB (MOVE)(F-SHAPE)(TY 1) LF 990.000 $15.000 $3.000 $13.000 $20.000 $46.200
512 6041 PORT CTB (STKPL)(F-SHAPE)(TY 1) LF 840.000 $10.000 $10.000 $20.000 $20.000 $38.500
530 6006 DRIVEWAYS (SURF TREAT) SY 324.000 $35.000 $4.290 $35.000 $28.000 $4.080
540 6001 MTL W-BEAM GD FEN (TIM POST) LF 400.000 $25.000 $20.000 $22.500 $28.000 $30.000
540 6006 MTL BEAM GD FEN TRANS (THRIE-BEAM) EA 4.000 $1,850.000 $1,817.000 $2,000.000 $2,000.000 $1,920.000
542 6001 REMOVE METAL BEAM GUARD FENCE LF 200.000 $2.500 $6.310 $1.500 $4.000 $1.500
542 6005 RM MTL BM GD FEN TRANS (T101) EA 4.000 $250.000 $315.000 $200.000 $250.000 $600.000
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 4.000 $2,800.000 $2,765.000 $2,700.000 $2,800.000 $3,240.000
544 6003 GUARDRAIL END TREATMENT (REMOVE) EA 4.000 $300.000 $97.000 $200.000 $350.000 $330.000
545 6003 CRASH CUSH ATTEN (MOVE & RESET) EA 2.000 $1,500.000 $1,894.000 $1,400.000 $3,500.000 $1,872.000
545 6004 CRASH CUSH ATTEN (STKPL) EA 2.000 $1,000.000 $631.000 $1,400.000 $2,000.000 $840.000
545 6019 CRASH CUSH ATTEN (INSTL)(S)(N)(TL3) EA 2.000 $7,500.000 $9,612.000 $9,000.000 $8,500.000 $10,200.000
644 6001 IN SM RD SN SUP&AM TY10BWG(1)SA(P) EA 1.000 $500.000 $1,022.000 $1,000.000 $600.000 $600.000
644 6060 IN SM RD SN SUP&AM TYTWT(1)WS(P) EA 6.000 $400.000 $453.860 $550.000 $450.000 $402.000
644 6061 IN SM RD SN SUP&AM TYTWT(1)WS(T) EA 2.000 $400.000 $515.000 $750.000 $450.000 $480.000
644 6076 REMOVE SM RD SN SUP&AM EA 9.000 $85.000 $86.000 $150.000 $200.000 $72.000
658 6014 INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI) EA 28.000 $20.000 $6.000 $30.000 $7.000 $24.000
658 6062 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) EA 14.000 $24.000 $171.000 $25.000 $137.000 $42.000
662 6063 WK ZN PAV MRK REMOV (W)4"(SLD) LF 15,100.000 $1.000 $0.910 $0.550 $0.850 $0.860
662 6075 WK ZN PAV MRK REMOV (W)24"(SLD) LF 24.000 $7.000 $6.320 $21.000 $6.000 $6.000
662 6093 WK ZN PAV MRK REMOV (Y)4"(BRK) LF 711.000 $1.000 $1.330 $0.600 $1.200 $1.260
662 6095 WK ZN PAV MRK REMOV (Y)4"(SLD) LF 16,910.000 $1.000 $0.910 $0.550 $0.850 $0.860
662 6111 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 EA 360.000 $2.000 $2.530 $1.050 $2.500 $2.640
666 6303 RE PM W/RET REQ TY I (W)4"(SLD)(100MIL) LF 13,200.000 $0.750 $0.630 $0.550 $0.550 $0.600
666 6312 RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL) LF 711.000 $0.750 $0.630 $0.550 $0.550 $0.600
666 6315 RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL) LF 9,710.000 $0.750 $0.630 $0.550 $0.550 $0.600
672 6009 REFL PAV MRKR TY II-A-A EA 157.000 $5.000 $5.000 $5.500 $5.000 $4.800
677 6001 ELIM EXT PAV MRK & MRKS (4") LF 19,900.000 $0.500 $0.510 $1.000 $0.450 $0.480
677 6007 ELIM EXT PAV MRK & MRKS (24") LF 24.000 $4.000 $2.530 $5.000 $2.000 $2.400
730 6107 FULL - WIDTH MOWING CYC 1.000 $2,600.000 $200.000 $2,500.000 $1,800.000 $3,960.000
6001 6002 PORTABLE CHANGEABLE MESSAGE SIGN EA 2.000 $8,500.000 $16,000.000 $10,000.000 $16,000.000 $24,420.000
6185 6002 TMA (STATIONARY) DAY 20.000 $300.000 $300.000 $200.000 $320.000 $366.000
6185 6005 TMA (MOBILE OPERATION) DAY 6.000 $400.000 $300.000 $250.000 $400.000 $780.000
Totals: $2,222,766.75 $2,346,537.14 $2,838,437.45 $2,996,709.65 $3,259,587.04