JACKSON CR (0913-18-036)

Items: 51

County: JACKSON
Length: N/A
Highway: CR
District: YOAKUM
Control Number: 0913-18-036
DBE Goal: N/A
Project: BR 2021(255)
Guaranty: N/A
Time: 180 WORKING DAYS
Engineer's Estimate: $1,267,649.25
Date: 07/02/2021 (4 years ago)
Contract Number: N/A
Type: REPLACE BRIDGE AND APPROACHES
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Documents:
Bidders (3)
E
Engineer's Estimate
$1,267,649.25
1
$1,283,044.73
Over/Under Est: 1.21% $15,395.48
$1,289,800.00
Over/Under Est: 1.75% $22,150.75
Amt Left: 0.53% $6,755.27
Over/Under Est: 50.2% $636,363.00
Amt Left: 48.4% $620,967.52
Delta: -47.62% -$614,212.25
Subcontractor Percentage Amount
HEMPHILL WBE PILE DRIVING CO. 7.47% $97,073.97
SYLVA CONSTRUCTION, LLC 1.20% $15,594.21
LONESTAR TRAFFIC SAFETY, LLC 0.57% $7,407.25
Total: 9.24% $120,075.43

Bid Items & Bid Tabulations

51 Total 0 of 51
JACKSON  |  CR  |  YOAKUM  |  0913-18-036  |  07/02/2021  |  $1,267,649.25  |  BR 2021(255)  |  REPLACE BRIDGE AND APPROACHES  |  180 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
TREVWAY, INC.
CONSTAR CONSTRUCTION
DIAMOND X CONTRACTING, INC
PREPARING ROW
STA 6.630 $3,000.000 $1,000.000 $1,000.000 $9,000.000
REMOVING CONC (RIPRAP)
SY 45.000 $20.000 $30.000 $30.000 $60.000
EXCAVATION (ROADWAY)
CY 575.000 $20.000 $7.760 $20.000 $26.000
EXCAVATION (CHANNEL)
CY 482.000 $20.000 $9.260 $20.000 $30.000
EMBANKMENT (FINAL)(ORD COMP)(TY C)
CY 320.000 $25.000 $15.000 $25.000 $33.000
BLADING
HR 50.000 $100.000 $100.000 $110.000 $120.000
BROADCAST SEED (PERM) (RURAL) (CLAY)
SY 1,686.000 $2.000 $1.000 $1.000 $4.000
BROADCAST SEED (TEMP) (WARM)
SY 422.000 $2.000 $1.000 $1.000 $17.000
BROADCAST SEED (TEMP) (COOL)
SY 422.000 $2.000 $1.000 $1.000 $17.000
VEGETATIVE WATERING
MG 17.650 $25.000 $100.000 $150.000 $75.000
FL BS (CMP IN PLC)(TY A GR 5)(FNAL POS)
CY 499.000 $100.000 $122.000 $120.000 $160.000
CEM STABIL BKFL
CY 232.000 $100.000 $100.000 $75.000 $220.000
TEMPORARY SPL SHORING
SF 1,570.000 $19.000 $7.000 $14.000 $35.000
PRESTR CONC PIL (18 IN SQ)
LF 1,196.000 $125.000 $157.000 $174.000 $145.000
CL C CONC (ABUT)
CY 42.800 $1,100.000 $680.000 $1,000.000 $1,400.000
CL C CONC (CAP)
CY 22.600 $1,100.000 $900.000 $1,250.000 $1,600.000
REINF CONC SLAB (SLAB BEAM)
SF 4,520.000 $19.000 $17.000 $19.000 $27.000
PRESTR CONC SLAB BEAM (4SB12)
LF 628.000 $165.000 $172.000 $180.000 $216.000
PRESTR CONC SLAB BEAM (5SB12)
LF 370.000 $175.000 $175.000 $180.000 $216.000
RIPRAP (STONE COMMON)(DRY)(12 IN)
CY 38.000 $140.000 $251.000 $165.000 $260.000
RIPRAP (STONE PROTECTION)(12 IN)
CY 327.000 $160.000 $268.000 $165.000 $250.000
RAIL (TY T631)
LF 186.000 $100.000 $77.390 $140.000 $116.000
RAIL (TY SSTR) (W/DRAIN SLOTS)
LF 358.000 $80.000 $65.320 $140.000 $99.000
ARMOR JOINT (SEALED)
LF 101.000 $80.000 $90.320 $87.000 $190.000
CMP (GAL STL 18 IN)
LF 234.000 $85.000 $57.040 $52.000 $110.000
CMP (GAL STL 24 IN)
LF 160.000 $115.000 $61.380 $67.000 $130.000
CONC BOX CULV (10 FT X 7 FT)
LF 104.000 $1,000.000 $1,300.000 $1,170.000 $1,300.000
WINGWALL (PW-1) (HW=9 FT) (MOD)
EA 2.000 $35,000.000 $20,000.000 $21,000.000 $98,000.000
SET (TY II) (18 IN) (CMP) (6: 1) (P)
EA 2.000 $1,150.000 $1,641.060 $1,000.000 $1,900.000
SET (TY II) (18 IN) (HDPE) (6: 1) (P)
EA 6.000 $1,100.000 $1,000.000 $1,000.000 $1,900.000
SET (TY II) (24 IN) (CMP) (6: 1) (P)
EA 2.000 $1,400.000 $2,525.270 $1,100.000 $2,000.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 3.000 $20,000.000 $25,000.000 $9,000.000 $22,000.000
REMOV STR (PIPE)
EA 6.000 $400.000 $100.000 $450.000 $400.000
MOBILIZATION
LS 1.000 $113,400.000 $120,000.000 $96,000.000 $180,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 12.000 $2,500.000 $1,000.000 $900.000 $4,000.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,494.000 $3.000 $3.000 $5.000 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,494.000 $1.000 $0.500 $2.000 $3.000
DRIVEWAYS (BASE)
SY 144.000 $20.000 $37.270 $50.000 $25.000
MTL W-BEAM GD FEN (TIM POST)
LF 112.500 $22.000 $54.930 $43.000 $35.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 5.000 $2,000.000 $2,076.000 $2,300.000 $2,000.000
SHORT RADIUS
LF 50.000 $35.000 $67.890 $90.000 $72.000
DRIVEWAY TERMINAL ANCHOR SECTION
EA 2.000 $1,000.000 $1,490.000 $840.000 $700.000
MTL BEAM GD FEN TRANS (TL2) 28"
EA 2.000 $1,200.000 $2,494.420 $1,100.000 $915.000
GUARDRAIL END TREATMENT (INSTALL)
EA 9.000 $2,800.000 $2,864.910 $3,700.000 $3,100.000
CRASH CUSH ATTEN (INSTL)(R)(N)(TL3)
EA 1.000 $8,000.000 $27,155.800 $33,000.000 $27,000.000
WIRE FENCE (TY A)
LF 200.000 $15.000 $15.150 $22.000 $20.000
GATE (TY 1)
EA 1.000 $800.000 $2,525.250 $870.000 $2,800.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 12.000 $25.000 $5.050 $27.000 $22.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 19.000 $25.000 $11.370 $54.000 $38.000
DITCH CLEANING AND RESHAPING (FOOT)
LF 139.000 $18.000 $10.700 $9.000 $11.000
THERMO PIPE(18")(HDPE)(TY S)(CSB)
LF 134.000 $135.000 $52.240 $23.000 $150.000
Totals: $1,267,649.250 $1,283,044.735 $1,289,800.000 $1,904,012.250