JACKSON CR (0913-18-036)
Items: 51
County: JACKSON
Length: N/A
Highway: CR
District: YOAKUM
Control Number: 0913-18-036
DBE Goal: N/A
Project: BR 2021(255)
Guaranty: N/A
Time: 180 WORKING DAYS
Engineer's Estimate: $1,267,649.25
Date: 07/02/2021 (4 years ago)
Contract Number: N/A
Type: REPLACE BRIDGE AND APPROACHES
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (3)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$1,267,649.25 | |||
| $1,283,044.73 |
1.21%
$15,395.48
|
|||
| $1,289,800.00 |
1.75%
$22,150.75
|
0.53%
$6,755.27
|
||
| $1,904,012.25 |
50.2%
$636,363.00
|
48.4%
$620,967.52
|
-47.62%
-$614,212.25
|
E
Engineer's Estimate
$1,267,649.25
1
Awarded
$1,283,044.73
Over/Under Est:
1.21%
$15,395.48
$1,289,800.00
Over/Under Est:
1.75%
$22,150.75
Amt Left:
0.53%
$6,755.27
$1,904,012.25
Over/Under Est:
50.2%
$636,363.00
Amt Left:
48.4%
$620,967.52
Delta:
-47.62%
-$614,212.25
| Subcontractor | Percentage | Amount |
|---|---|---|
| HEMPHILL WBE PILE DRIVING CO. | 7.47% | $97,073.97 |
| SYLVA CONSTRUCTION, LLC | 1.20% | $15,594.21 |
| LONESTAR TRAFFIC SAFETY, LLC | 0.57% | $7,407.25 |
| Total: | 9.24% | $120,075.43 |