JACK US 281 (0249-07-070)

Items: 172

County: JACK
Length: N/A
Highway: US 281
District: FORT WORTH
Control Number: 0249-07-070
DBE Goal: N/A
Project: C 249-7-70
Guaranty: N/A
Time: 384 WORKING DAYS
Engineer's Estimate: $23,212,119.19
Date: 03/08/2023 (3 years ago)
Contract Number: N/A
Type: CONSTRUCT NEW ROADWAY LANES
Mail/Deliver Bids To: N/A
EDREAN CHENG
OSCAR R CHAVEZ
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$23,212,119.19
$29,571,986.47
Over/Under Est: 27.4% $6,359,867.28
Over/Under Est: 32.52% $7,549,583.48
Amt Left: 4.02% $1,189,716.20
$34,566,334.05
Over/Under Est: 48.92% $11,354,214.86
Amt Left: 16.89% $4,994,347.58
Delta: -12.37% -$3,804,631.38
Over/Under Est: 68.29% $15,852,435.94
Amt Left: 32.1% $9,492,568.66
Delta: -13.01% -$4,498,221.08
Subcontractor Percentage Amount
JM YANEZ CONSTRUCTION, INC. 8.23% $2,462,128.96
RIGID CONSTRUCTORS, LLC 6.88% $2,058,256.04
RELIABLE PAVING INC. 5.02% $1,501,808.91
J. H. ODEN CONTRACTING COMPANY 2.38% $712,012.99
TRP CONSTRUCTION GROUP, LLC 0.89% $266,256.96
MICA CORPORATION 0.79% $236,340.45
DUSTIN ALLEN, INC. 0.74% $221,382.19
DURABLE SPECIALTIES, INC. 0.68% $203,432.28
TEXAS TRAFFIC AND BARRICADE, LLC 0.49% $146,590.91
HJC FARMS, INC. 0.47% $140,607.61
SOUTHERN CROSS CONTRACTORS, LLC 0.20% $59,833.02
PRIMATE CONSTRUCTION, LP 0.08% $23,933.21
SURFACE PREPARATION TECHNOLOGIES, LLC 0.07% $20,941.56
Total: 26.92% $8,053,525.09

Bid Items & Bid Tabulations

172 Total 0 of 172
JACK  |  US 281  |  FORT WORTH  |  0249-07-070  |  03/08/2023  |  $23,212,119.19  |  C 249-7-70  |  CONSTRUCT NEW ROADWAY LANES  |  384 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
AUSTIN BRIDGE & ROAD SERVICES, LP
JAY MILLS CONTRACTING, INCORPORATED
A. L. HELMCAMP, INC.
EUROVIA ATLANTIC COAST LLC
PREPARING ROW
STA 488.620 $400.000 $4,875.220 $2,000.000 $1,800.000 $1,000.000
REMOVING CONC (SIDEWALKS)
SY 340.000 $45.000 $19.240 $65.000 $27.000 $40.000
REMOVING CONC (DRIVEWAYS)
SY 87.000 $55.000 $35.000 $25.000 $55.000 $72.000
REMOVING CONC (CTB)
LF 180.000 $35.000 $47.180 $35.000 $55.000 $60.000
EXCAVATION (ROADWAY)
CY 45,560.000 $10.000 $21.200 $18.000 $19.000 $36.250
EMBANKMENT (FINAL)(DENS CONT)(TY B)
CY 20,175.000 $15.000 $6.170 $27.000 $11.000 $24.000
COMPOST MANUF TOPSOIL (4")
SY 169,305.000 $0.830 $5.900 $8.150 $1.700 $7.580
BLOCK SODDING
SY 468.000 $10.000 $7.000 $10.000 $7.500 $9.850
CELL FBR MLCH SEED(PERM)(RURAL)(SANDY)
SY 169,305.000 $0.500 $0.440 $0.500 $0.450 $0.600
CELL FBR MLCH SEED(TEMP)(WARM)
SY 84,652.000 $0.500 $0.400 $0.450 $0.410 $0.570
CELL FBR MLCH SEED(TEMP)(COOL)
SY 84,652.000 $0.500 $0.400 $0.450 $0.410 $0.570
VEGETATIVE WATERING
MG 5,932.340 $25.000 $39.000 $23.000 $10.000 $47.500
FL BS (CMP IN PLACE)(TY A GR 1-2)(7")
SY 81,365.000 $18.000 $15.000 $12.650 $14.100 $25.500
LIME(HYD,COM OR QK)(SLRY)OR QK(DRY)
TON 1,584.000 $200.000 $297.000 $330.000 $220.000 $315.000
LIME TRT (EXST MATL)(8")
SY 94,657.000 $4.000 $7.500 $5.750 $4.000 $15.000
PRIME COAT (MC-30 OR EC-30)
GAL 30,271.000 $5.000 $0.070 $6.150 $6.500 $5.500
FLEX PAVEMENT STRUCTURE REPAIR (5"-10")
SY 13,703.000 $60.000 $44.290 $56.000 $98.000 $74.000
FLEX PAVEMENT STRUCTURE REPAIR (4"-5")
SY 91,701.000 $30.000 $29.420 $30.000 $49.000 $44.500
FLEX PAVEMNT STRUCTURE REPAIR (10"-16")
SY 10,470.000 $70.000 $77.700 $80.000 $152.000 $135.000
PLANE ASPH CONC PAV(0" TO 2")
SY 4,887.000 $2.000 $3.190 $4.500 $6.500 $6.000
CONC PVMT (CONT REINF - CRCP) (10")
SY 12,972.000 $90.000 $101.990 $115.000 $152.000 $167.550
CEM STABIL BKFL
CY 97.000 $231.070 $150.000 $225.000 $262.000 $275.000
CUT & RESTORE ASPH PAVING
SY 219.000 $75.000 $105.800 $150.000 $53.000 $155.000
TRENCH EXCAVATION PROTECTION
LF 4,639.000 $5.000 $3.730 $6.000 $16.000 $10.000
TEMPORARY SPL SHORING
SF 808.000 $25.000 $50.090 $80.000 $90.000 $80.000
DRILL SHAFT (TRF SIG POLE) (24 IN)
LF 12.000 $300.000 $890.000 $1,000.000 $940.000 $890.000
RIPRAP (CONC)(5 IN)
CY 75.500 $600.000 $765.560 $750.000 $740.000 $1,200.000
RIPRAP (STONE PROTECTION)(12 IN)
CY 233.900 $150.000 $130.000 $180.000 $130.000 $415.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 50.600 $260.480 $130.000 $185.000 $130.000 $380.000
RIPRAP (MOW STRIP)(4 IN)
CY 294.000 $690.000 $607.560 $950.000 $790.000 $710.000
CLEANING AND SEALING JOINTS
LF 96.000 $60.000 $57.710 $95.000 $61.000 $85.000
RAIL (HANDRAIL)(TY D)
LF 440.000 $160.000 $140.760 $150.000 $320.000 $138.000
CONC BOX CULV (3 FT X 2 FT)(EXTEND)
LF 30.000 $530.000 $1,876.760 $800.000 $710.000 $1,200.000
CONC BOX CULV (3 FT X 3 FT)(EXTEND)
LF 18.000 $634.360 $1,529.110 $550.000 $790.000 $1,530.000
CONC BOX CULV (4 FT X 3 FT)(EXTEND)
LF 15.000 $765.860 $1,819.100 $900.000 $940.000 $1,820.000
CONC BOX CULV (4 FT X 4 FT)(EXTEND)
LF 10.000 $671.750 $2,281.120 $800.000 $1,000.000 $2,400.000
CONC BOX CULV (5 FT X 2 FT)(EXTEND)
LF 5.000 $817.260 $2,399.110 $900.000 $930.000 $2,500.000
CONC BOX CULV (5 FT X 5 FT)(EXTEND)
LF 20.000 $873.560 $2,795.250 $1,200.000 $1,000.000 $2,400.000
RC PIPE (CL III)(18 IN)
LF 536.000 $80.000 $121.840 $150.000 $110.000 $100.000
RC PIPE (CL III)(24 IN)
LF 3,453.000 $93.460 $94.680 $165.000 $140.000 $128.000
RC PIPE (CL III)(30 IN)
LF 1,427.000 $120.000 $119.490 $200.000 $200.000 $200.000
INLET (COMPL)(CO)(5 FT)(FTW)
EA 12.000 $5,500.000 $7,865.190 $8,500.000 $11,000.000 $15,000.000
INLET (COMPL)(CO)(10 FT)(FTW)
EA 1.000 $10,500.000 $10,324.370 $12,000.000 $17,000.000 $25,000.000
INLET (COMPL)(COB)(5 FT)(FTW)
EA 17.000 $6,900.000 $9,584.390 $10,500.000 $11,000.000 $16,000.000
INLET (COMPL)(COB)(10 FT)(FTW)
EA 2.000 $10,500.000 $11,823.550 $13,000.000 $15,000.000 $18,000.000
INLT (COMPL)(FG)(4'X 3'-3' X 3')(FTW)
EA 1.000 $8,925.000 $8,951.010 $10,000.000 $9,000.000 $15,000.000
INLET (COMPL)(AD)(3FT X 3FT)(FTW)
EA 2.000 $9,450.000 $7,814.990 $6,000.000 $7,900.000 $10,000.000
MANH (COMPL)(TY SD)(3FT X 3FT)(FTW)
EA 2.000 $7,350.000 $7,833.390 $7,500.000 $9,000.000 $9,000.000
JUNCT BOX (COMPL)(JB)(6FT X 4FT)(FTW)
EA 2.000 $8,000.000 $11,215.310 $10,500.000 $9,500.000 $10,500.000
WINGWALL (PW - 1) (HW=5 FT)
EA 1.000 $21,623.750 $45,000.000 $16,000.000 $37,000.000 $45,000.000
WINGWALL (PW - 1) (HW=6 FT)
EA 1.000 $25,000.000 $50,000.000 $18,000.000 $43,000.000 $50,000.000
WINGWALL (PW - 1) (HW=7 FT)
EA 3.000 $25,000.000 $57,000.000 $25,000.000 $30,000.000 $57,000.000
WINGWALL (PW - 1) (HW=9 FT)
EA 1.000 $30,000.000 $80,000.000 $36,000.000 $58,000.000 $80,000.000
SET (TY I)(S=3 FT)(HW=3FT)(3:1)(C)
EA 4.000 $6,600.000 $14,000.000 $7,500.000 $11,000.000 $14,000.000
SET (TY I)(S=3 FT)(HW= 4 FT)(3:1)(C)
EA 3.000 $7,185.830 $17,000.000 $11,000.000 $12,000.000 $17,000.000
SET (TY I)(S= 4 FT)(HW= 5 FT)(3:1) (C)
EA 1.000 $7,199.950 $23,000.000 $13,000.000 $17,000.000 $23,000.000
SET (TY I)(S= 5 FT)(HW= 3 FT)(3:1) (C)
EA 1.000 $10,706.500 $15,000.000 $7,000.000 $10,000.000 $15,000.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 36.000 $1,500.000 $1,276.680 $1,800.000 $1,500.000 $1,300.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 3.000 $2,141.180 $1,489.480 $2,000.000 $1,900.000 $1,700.000
SET (TY II) (30 IN) (RCP) (6: 1) (P)
EA 1.000 $3,000.000 $2,297.840 $3,000.000 $3,700.000 $7,500.000
CLEAN EXIST CULVERTS
EA 51.000 $2,571.430 $2,500.000 $4,000.000 $2,200.000 $2,500.000
REMOV STR (INLET)
EA 12.000 $1,000.000 $708.000 $2,000.000 $1,100.000 $400.000
REMOV STR (SET)
EA 24.000 $617.200 $708.000 $800.000 $1,100.000 $275.000
REMOV STR (WINGWALL)
EA 6.000 $1,757.830 $2,304.000 $2,000.000 $1,600.000 $1,200.000
REMOV STR (PIPE)
LF 2,492.000 $20.000 $31.480 $40.000 $13.000 $25.000
REMOV STR (BOX CULVERT)
LF 20.000 $70.840 $218.680 $100.000 $110.000 $500.000
MOBILIZATION
LS 1.000 $1,530,198.310 $2,957,198.640 $3,000,000.000 $3,000,000.000 $2,705,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 18.000 $10,000.000 $40,000.000 $25,000.000 $48,000.000 $37,000.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 320.000 $40.000 $36.000 $40.000 $38.000 $42.330
ROCK FILTER DAMS (REMOVE)
LF 320.000 $20.000 $12.000 $14.000 $13.000 $15.130
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 1,092.000 $20.880 $30.000 $5.000 $20.000 $41.420
CONSTRUCTION EXITS (REMOVE)
SY 1,092.000 $6.900 $15.000 $1.500 $5.000 $12.960
TEMP SEDMT CONT FENCE (INSTALL)
LF 20,521.000 $1.870 $3.890 $9.000 $4.000 $3.900
TEMP SEDMT CONT FENCE (REMOVE)
LF 20,521.000 $0.550 $1.000 $1.100 $1.000 $0.880
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 350.000 $1.870 $8.000 $10.000 $8.500 $6.040
BIODEG EROSN CONT LOGS (REMOVE)
LF 350.000 $0.450 $1.000 $3.000 $1.100 $1.350
CONSTRUCTING DETOURS
SY 4,886.000 $75.000 $51.590 $75.000 $125.000 $100.000
ONE-WAY TRAF CONT (PORT TRAF SIG)
MO 12.000 $5,000.000 $2,000.000 $4,000.000 $6,500.000 $7,500.000
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
LF 840.000 $70.000 $75.400 $90.000 $90.000 $110.000
PORT CTB (FUR & INST)(LOW PROF)(TY 1)
LF 2,080.000 $40.000 $30.510 $85.000 $90.000 $42.000
PORT CTB (FUR & INST)(LOW PROF)(TY 2)
LF 440.000 $52.000 $36.920 $79.000 $90.000 $42.000
PORT CTB (MOVE)(SGL SLP)(TY 1)
LF 5,880.000 $10.000 $14.240 $22.500 $25.000 $18.000
PORT CTB (MOVE)(LOW PROF)(TY 1)
LF 5,080.000 $8.000 $8.510 $15.000 $25.000 $16.000
PORT CTB (MOVE)(LOW PROF)(TY 2)
LF 760.000 $15.000 $5.820 $15.000 $25.000 $16.000
PORT CTB (STKPL)(SGL SLP)(TY 1)
LF 840.000 $9.000 $14.240 $28.000 $15.000 $20.000
PORT CTB (REMOVE)(LOW PROF)(TY 1)
LF 2,080.000 $9.000 $12.520 $14.000 $20.000 $24.000
PORT CTB (REMOVE)(LOW PROF)(TY 2)
LF 440.000 $12.000 $3.420 $14.000 $20.000 $24.000
CONC CURB (TY F2)
LF 50.000 $119.000 $271.220 $525.000 $85.000 $290.000
CONC CURB (TY F3)
LF 408.000 $155.000 $159.370 $600.000 $110.000 $390.000
CONC CURB & GUTTER (VALLEY GUTTER)
LF 208.000 $40.000 $70.000 $100.000 $160.000 $115.000
TURNOUTS (ACP)
SY 123.000 $70.000 $47.170 $115.000 $160.000 $125.000
DRIVEWAYS (ACP)(TYPE 1)
SY 1,558.000 $40.000 $16.200 $85.000 $90.000 $100.000
DRIVEWAYS (CONC)(TYPE 1)
SY 1,007.000 $110.000 $158.400 $150.000 $116.000 $156.000
DRIVEWAYS (ACP) (TYPE 2)
SY 2,093.000 $35.000 $16.200 $40.000 $120.000 $75.000
INTERSECTIONS (ACP) (TYPE 1)
SY 735.000 $50.000 $16.180 $77.000 $120.000 $275.000
INTERSECTIONS (ACP) (TYPE 2)
SY 1,081.000 $30.000 $16.150 $40.000 $120.000 $75.000
DRIVEWAYS (CONC)(TYPE 2)
SY 1,558.000 $100.000 $141.790 $158.000 $127.000 $166.000
CONC SIDEWALKS (4")
SY 2,346.000 $75.000 $98.610 $120.000 $95.000 $135.000
CURB RAMPS (TY 10)
EA 18.000 $2,500.000 $4,558.750 $2,800.000 $2,700.000 $3,500.000
RUMBLE STRIPS (SHOULDER) ASPHALT
LF 95,345.000 $0.220 $0.100 $0.150 $0.200 $0.330
RUMBLE STRIPS (CENTERLINE) ASPHALT
LF 47,673.000 $0.200 $0.100 $0.150 $0.200 $0.330
MTL W-BEAM GD FEN (TIM POST)
LF 5,388.000 $25.000 $21.000 $26.500 $22.000 $26.000
MTL W-BEAM GD FEN (STEEL POST)
LF 89.000 $90.000 $84.000 $77.000 $90.000 $119.500
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 5.000 $2,835.000 $1,575.000 $1,870.000 $1,700.000 $1,840.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 2.000 $1,035.510 $1,290.000 $1,430.000 $1,400.000 $1,575.000
REMOVE METAL BEAM GUARD FENCE
LF 5,416.000 $3.000 $2.000 $2.200 $2.200 $3.000
REMOVE TERMINAL ANCHOR SECTION
EA 6.000 $158.000 $200.000 $275.000 $220.000 $250.000
REMOVE DOWNSTREAM ANCHOR TERMINAL
EA 22.000 $150.000 $200.000 $275.000 $220.000 $200.000
GUARDRAIL END TREATMENT (INSTALL)
EA 24.000 $3,100.000 $2,775.000 $3,250.000 $2,900.000 $2,835.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 24.000 $1,200.000 $961.180 $3,750.000 $1,000.000 $1,800.000
CRASH CUSH ATTEN (REMOVE)
EA 4.000 $1,000.000 $706.820 $3,000.000 $900.000 $1,300.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 4.000 $10,000.000 $7,361.180 $12,500.000 $10,000.000 $9,500.000
MAILBOX INSTALL-S (TWW-POST) TY 4
EA 11.000 $260.000 $370.000 $305.000 $290.000 $275.000
MAILBOX INSTALL-D (TWW-POST) TY 4
EA 2.000 $270.000 $399.000 $350.000 $330.000 $315.000
CONDT (PVC) (SCH 40) (2")
LF 163.000 $20.000 $48.000 $55.000 $50.000 $48.000
ELEC CONDR (NO.6) BARE
LF 100.000 $6.000 $6.000 $7.000 $6.500 $6.000
TRAY CABLE (4 CONDR) (12 AWG)
LF 40.000 $5.000 $10.000 $11.000 $11.000 $10.000
REMOVE ELECTRICAL SERVICES
EA 2.000 $500.000 $2,800.000 $3,100.000 $3,000.000 $2,800.000
ELC SRV TY T 120/240 000(NS)GS(N)SP(O)
EA 2.000 $7,500.000 $12,500.000 $18,500.000 $13,000.000 $12,500.000
ALUMINUM SIGNS (TY A)
SF 216.000 $30.000 $33.000 $40.000 $45.000 $75.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 36.000 $552.000 $905.000 $800.000 $740.000 $700.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 56.000 $750.000 $1,050.000 $925.000 $870.000 $825.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 4.000 $1,100.000 $1,110.000 $1,100.000 $970.000 $920.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 14.000 $990.000 $1,131.000 $1,100.000 $1,100.000 $990.000
REMOVE SM RD SN SUP&AM
EA 89.000 $95.000 $159.000 $110.000 $110.000 $100.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 274.000 $21.000 $24.000 $27.000 $25.000 $45.000
INSTL OM ASSM (OM-2Z)(WFLX)GND
EA 21.000 $52.000 $107.000 $110.000 $110.000 $100.000
WK ZN PAV MRK NON-REMOV (W)4"(BRK)
LF 4,760.000 $0.700 $0.430 $0.500 $0.430 $0.430
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 134,218.000 $0.350 $0.250 $0.300 $0.350 $0.250
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 50.000 $6.500 $8.000 $9.000 $8.300 $8.000
WK ZN PAV MRK NON-REMOV (Y)4"(BRK)
LF 8,305.000 $0.400 $0.430 $0.500 $0.430 $0.430
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 44,372.000 $0.400 $0.250 $0.300 $0.350 $0.250
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 14,110.000 $1.000 $0.970 $1.100 $0.850 $0.970
WK ZN PAV MRK REMOV (W)8"(SLD)
LF 110.000 $2.100 $2.000 $2.200 $5.250 $2.000
WK ZN PAV MRK REMOV (W)24"(SLD)
LF 80.000 $14.000 $10.000 $11.000 $7.350 $10.000
WK ZN PAV MRK REMOV (W)(ARROW)
EA 4.000 $90.000 $167.000 $185.000 $337.050 $167.000
WK ZN PAV MRK REMOV (W)(WORD)
EA 4.000 $90.000 $193.000 $215.000 $496.650 $193.000
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 11,987.000 $1.000 $0.970 $1.100 $0.860 $0.970
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 10,217.000 $1.800 $1.000 $1.500 $0.570 $2.000
WK ZN PAV MRK SHT TERM (TAB)TY Y
EA 10,962.000 $1.800 $1.000 $1.500 $0.570 $2.000
REFL PAV MRK TY I (W)4"(DOT)(100MIL)
LF 2,660.000 $2.040 $1.270 $1.500 $1.790 $1.270
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 2,989.000 $1.900 $0.990 $1.100 $1.100 $0.990
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 6,300.000 $1.500 $0.570 $0.650 $0.530 $0.570
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 89,956.000 $0.550 $0.450 $0.500 $0.530 $0.450
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 840.000 $0.500 $0.570 $0.650 $1.050 $0.570
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 96,840.000 $0.600 $0.450 $0.500 $0.530 $0.450
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 560.000 $15.000 $13.490 $15.000 $16.540 $13.490
PREFAB PAV MRK TY C (W) (ARROW)
EA 23.000 $260.000 $239.000 $265.000 $294.000 $239.000
PREFAB PAV MRK TY C (W) (LNDP ARROW)
EA 12.000 $510.000 $475.000 $525.000 $616.350 $475.000
PREFAB PAV MRK TY C (W) (WORD)
EA 13.000 $300.000 $300.000 $330.000 $389.550 $300.000
PREFAB PAV MRK TY C (Y) (24") (SLD)
LF 1,238.000 $20.000 $13.490 $15.000 $17.060 $13.490
REFL PAV MRKR TY I-C
EA 516.000 $3.000 $4.670 $5.250 $4.730 $4.670
REFL PAV MRKR TY II-A-A
EA 1,452.000 $3.000 $4.670 $5.250 $4.730 $4.670
ELIM EXT PAV MRK & MRKS (4")
LF 32,501.000 $0.450 $0.440 $0.500 $0.530 $0.440
REMOVING TRAFFIC SIGNALS
EA 2.000 $3,718.000 $3,000.000 $3,500.000 $3,150.000 $3,000.000
TEMP TRAF SIGNALS
EA 1.000 $15,000.000 $4,000.000 $66,000.000 $26,250.000 $57,000.000
VEH SIG SEC (12")LED(YEL)
EA 8.000 $376.000 $1,100.000 $1,250.000 $1,155.000 $1,100.000
VEH SIG SEC (12")LED(RED)
EA 4.000 $376.000 $1,100.000 $1,250.000 $1,155.000 $1,100.000
BACK PLATE (12")(1 SEC)(VENTED)ALUM
EA 4.000 $190.000 $450.000 $500.000 $472.500 $450.000
TRF SIG CBL (TY A)(12 AWG)(4 CONDR)
LF 130.000 $5.000 $5.000 $5.500 $5.250 $5.000
TRF SIG CBL (TY A)(14 AWG)(7 CONDR)
LF 311.000 $4.000 $5.000 $5.500 $5.250 $5.000
INSTALL RDSD FLASH BEACON ASSEMBLY
EA 2.000 $9,000.000 $15,000.000 $16,500.000 $15,750.000 $15,000.000
REMOVE RDSD FLASH BEACON ASSEMBLY
EA 2.000 $500.000 $1,500.000 $1,650.000 $1,575.000 $1,500.000
INSTL RDSD FLSH BCN ASSM (SOLAR PWRD)
EA 6.000 $10,500.000 $18,500.000 $20,500.000 $19,425.000 $18,500.000
D-GR HMA TY-B PG64-22
TON 40,957.000 $92.000 $101.500 $99.000 $127.070 $139.650
D-GR HMA TY-B PG64-22 (LEVEL-UP)
TON 601.000 $92.000 $292.140 $220.000 $139.980 $230.000
SP MIXES SP-C SAC-A PG70-28
TON 28,978.000 $125.000 $130.500 $148.000 $161.670 $184.000
TACK COAT
GAL 48,205.000 $5.000 $0.140 $0.010 $4.600 $3.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 275.000 $110.000 $52.360 $100.000 $145.000 $100.000
TMA (STATIONARY)
DAY 199.000 $175.000 $408.460 $150.000 $300.000 $310.000
TMA (MOBILE OPERATION)
HR 384.000 $75.000 $82.190 $200.000 $75.000 $115.000
DRIVEWAY ASSISTANCE DEVICE(DAD) SYSTEM
MO 7.000 $15,000.000 $3,450.000 $11,000.000 $1,000.000 $8,000.000
Totals: $23,212,119.188 $29,571,986.476 $30,761,702.670 $34,566,334.050 $39,064,555.130