Job Info for 7107-08-004

County: IRION Highway: RL SO Date: 06/07/2017 (7 years ago) Engineer's Estimate: $9,515,331 Control Number: 7107-08-004
Project: NH 1702(336) District: SAN ANGELO Time: 199 WORKING DAYS Type: RAILROAD REHABILITATION

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $9,515,331.00
BALFOUR BEATTY INFRASTRUCTURE, INC.   $5,357,270.94 1
-43.7% | -$4,158,060.06
RAILWORKS TRACK SYSTEMS, INC.   $6,517,720.00 2
-31.5% | -$2,997,611.00
21.66% | $1,160,449.06
TRAC-WORK, INC.   $7,243,847.78 3
-23.87% | -$2,271,483.22
35.22% | $1,886,576.84
11.14% | $726,127.78

Bid Items

Items: 15, 0 filtered
IRION RL SO  |  SAN ANGELO  |  7107-08-004  |  06/07/2017  |  $9,515,331  |  NH 1702(336)  |  RAILROAD REHAB  |  199 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate BALFOUR BEATTY INFRASTRUCTURE, INC. RAILWORKS TRACK SYSTEMS, INC. TRAC-WORK, INC.
400 6008 CUT & RESTORE ASPH PAVING SY 212.440 $400.000 $113.970 $225.000 $161.110
400 6012 CUT AND RESTORE PAV (FLEX BASE) SY 525.300 $400.000 $73.820 $120.000 $188.090
500 6001 MOBILIZATION LS 1.000 $150,000.000 $365,577.940 $225,000.000 $280,441.810
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 10.000 $5,500.000 $8,389.290 $1,200.000 $4,999.700
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 1,310.000 $40.000 $7.640 $20.000 $29.490
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 1,310.000 $25.000 $2.800 $13.000 $25.220
4076 6001 TIE REMOVE AND REPLACE EA 38,800.000 $155.000 $92.090 $100.000 $116.500
4076 6002 OPEN DECK BRIDGE TIE REMOVE AND REPLACE EA 783.000 $225.000 $317.790 $300.000 $309.760
4076 6003 BALLAST DELIVERY AND REGULATING TON 10,600.000 $115.000 $60.050 $95.000 $62.650
4076 6004 BALLASTED TRACK SURFACING AND ALIGNMENT MI 53.000 $8,250.000 $2,076.450 $6,015.000 $10,982.400
4076 6005 RAIL REPLACEMENT LF 1,112.000 $80.000 $48.720 $80.000 $70.860
4076 6006 WELDS EA 68.000 $1,200.000 $666.640 $1,000.000 $967.650
4076 6007 CONCRETE VEHICULAR GRADE CROSSING LF 224.000 $1,800.000 $342.250 $1,000.000 $1,021.940
4076 6008 TIMBER VEHICULAR GRADE CROSSING LF 286.000 $1,450.000 $201.530 $900.000 $957.290
4076 6009 TIMBER CURBS EA 136.000 $700.000 $211.920 $350.000 $386.130
Totals: $9,515,331.00 $5,357,270.95 $6,517,720.00 $7,243,847.78