IRION US 67 (0077-05-031)

Items: 114

County: IRION
Length: N/A
Highway: US 67
District: SAN ANGELO
Control Number: 0077-05-031
DBE Goal: 0.0%
Project: F 2B24(013)
Guaranty: N/A
Time: 448 WORKING DAYS
Engineer's Estimate: $57,311,002.26
Date: 08/02/2024 (1 year ago)
Contract Number: N/A
Type: PREVENTIVE MAINTENANCE
Mail/Deliver Bids To: N/A
KLINTON KUNTZ
THOMAS GATLIN
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$57,311,002.26
1
$52,231,940.64
Over/Under Est: -8.86% -$5,079,061.62
Over/Under Est: -7.88% -$4,517,687.40
Amt Left: 1.07% $561,374.22
$56,263,862.40
Over/Under Est: -1.83% -$1,047,139.86
Amt Left: 7.72% $4,031,921.76
Delta: -6.57% -$3,470,547.54
$61,520,070.05
Over/Under Est: 7.34% $4,209,067.79
Amt Left: 17.78% $9,288,129.41
Delta: -9.34% -$5,256,207.65
$69,927,828.14
Over/Under Est: 22.01% $12,616,825.88
Amt Left: 33.88% $17,695,887.50
Delta: -13.67% -$8,407,758.09
Subcontractor Percentage Amount
RELMCO, INC. 9.77% $5,121,843.13
W. S. CONSTRUCTION COMPANY 7.99% $4,188,692.59
RPV CONSTRUCTION, LLC 2.38% $1,247,695.66
TRP CONSTRUCTION GROUP, LLC 1.63% $854,514.26
DUSTROL, INC. 0.71% $372,211.73
DOUBLE A CONTRACTING, L.P. 0.27% $141,545.31
CONTRACTORS SERVICE, LTD. 0.21% $110,090.79
PROFESSIONAL TRAFFIC CONTROL LLC 0.15% $78,636.28
DK CONTRACTING, LLC 0.04% $20,969.68
J. H. ODEN CONTRACTING COMPANY 0.01% $5,242.42
Total: 23.16% $12,141,441.85

Bid Items & Bid Tabulations

114 Total 0 of 114
IRION  |  US 67  |  SAN ANGELO  |  0077-05-031  |  08/02/2024  |  $57,311,002.26  |  F 2B24(013)  |  PREVENT MAINT  |  448 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
RK HALL, LLC
KIEWIT INFRASTRUCTURE SOUTH CO.
FNF CONSTRUCTION, INC.
CK NEWBERRY, LLC
REECE ALBERT, INC.
REMOVING CONC (RIPRAP)
SY 38.000 $50.000 $443.320 $101.150 $45.000 $100.000 $133.640
REMOVING STAB BASE & ASPH PAV(14")
SY 35,886.000 $20.000 $14.400 $10.690 $10.000 $10.000 $12.770
EXCAVATION (ROADWAY)
CY 100.000 $20.000 $277.920 $123.130 $45.000 $100.000 $70.270
EMBANKMENT (FINAL)(ORD COMP)(TY B)
CY 699.000 $60.000 $197.910 $71.080 $100.000 $65.000 $104.970
BACKFILL (TY A OR B)
STA 2,181.000 $200.000 $214.730 $244.460 $165.000 $325.000 $239.190
FURNISHING AND PLACING TOPSOIL (3")
SY 24,180.000 $2.500 $10.830 $10.780 $4.100 $4.000 $1.820
BROADCAST SEED (PERM) (RURAL) (CLAY)
SY 24,180.000 $0.500 $0.330 $0.360 $0.300 $0.300 $0.390
FL BS (CMP IN PLACE)(TY A GR 1-2)(14")
SY 35,886.000 $40.000 $35.460 $27.010 $25.000 $50.000 $42.380
PRIME COAT (MC-30)
GAL 7,183.000 $6.500 $12.290 $6.110 $20.000 $10.000 $10.840
ASPH (AC-20-5TR)
GAL 636,933.000 $6.500 $5.110 $5.010 $3.500 $5.000 $5.780
AGGR(TY-PB GR-3 SAC-B)
CY 11,618.000 $200.000 $207.120 $147.340 $215.000 $150.000 $243.320
LRA PAV TY-I GR-D
TON 6.000 $300.000 $3,129.290 $1,542.900 $2,000.000 $2,500.000 $1,240.890
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
SY 38,379.000 $80.000 $50.400 $68.000 $80.000 $110.000 $115.390
PLANE ASPH CONC PAV(0" TO 2")
SY 16,617.000 $2.000 $14.980 $3.850 $2.750 $4.000 $7.000
PLANE ASPH CONC PAV (2")
SY 39,441.000 $2.500 $3.580 $2.850 $3.000 $3.000 $5.180
CEM STABIL BKFL
CY 670.000 $475.000 $323.390 $500.000 $300.000 $300.000 $312.870
FLOWABLE BACKFILL
CY 7.000 $200.000 $330.000 $1,000.000 $400.000 $1,500.000 $312.890
TRENCH EXCAVATION PROTECTION
LF 1,240.000 $12.000 $22.000 $28.540 $268.000 $25.000 $84.410
TEMPORARY SPL SHORING
SF 3,861.000 $70.000 $30.290 $200.000 $50.000 $25.000 $26.110
DRILL SHAFT (36 IN)
LF 665.000 $400.000 $550.000 $487.080 $1,000.000 $500.000 $466.630
CL C CONC (ABUT)
CY 53.000 $2,200.000 $1,617.000 $2,576.320 $3,000.000 $4,000.000 $2,422.870
CL C CONC (CAP)
CY 54.000 $2,200.000 $2,102.100 $2,703.930 $5,000.000 $5,000.000 $3,110.430
CL C CONC (COLUMN)
CY 26.000 $2,200.000 $1,832.600 $2,744.920 $4,750.000 $5,500.000 $2,864.260
CL C CONC (RAIL FOUNDATION)
CY 26.300 $1,350.000 $1,940.400 $5,466.920 $2,000.000 $2,500.000 $1,614.630
CL C CONC (RAC-R)
CY 15.000 $2,500.000 $1,617.000 $5,447.480 $2,250.000 $3,500.000 $1,808.390
REINF CONC SLAB
SF 10,350.000 $45.000 $33.000 $57.070 $75.000 $45.000 $60.840
APPROACH SLAB
CY 76.000 $2,200.000 $993.300 $1,361.020 $2,000.000 $1,000.000 $1,364.820
PRESTR CONC GIRDER (TX28)
LF 1,338.000 $300.000 $302.500 $289.150 $450.000 $400.000 $294.390
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 44.000 $185.000 $275.000 $468.970 $475.000 $325.000 $346.880
RIPRAP (CONC)(5 IN)
CY 60.000 $750.000 $660.000 $10,105.510 $775.000 $1,000.000 $768.560
RIPRAP (STONE PROTECTION)(18 IN)
CY 76.000 $300.000 $236.500 $700.000 $500.000 $400.000 $727.020
RIPRAP (MOW STRIP)(4 IN)
CY 895.000 $550.000 $643.500 $883.160 $860.000 $1,000.000 $852.520
CLEANING AND SEALING EXIST JOINTS(CL3)
LF 1,628.000 $150.000 $34.620 $61.230 $55.000 $50.000 $40.650
RAIL (TY SSTR)
LF 2,685.900 $150.000 $203.500 $256.780 $200.000 $225.000 $209.260
RAIL (TY T222)
LF 65.000 $180.000 $220.000 $190.300 $350.000 $400.000 $361.680
RETROFIT RAIL (TY T222)
LF 587.000 $325.000 $165.000 $300.010 $325.000 $275.000 $503.760
SEALED EXPANSION JOINT (4 IN) (SEJ - B)
LF 92.000 $300.000 $330.000 $293.920 $220.000 $300.000 $407.820
CONC BOX CULV (6 FT X 5 FT)
LF 2,032.000 $1,000.000 $715.000 $636.480 $750.000 $650.000 $677.860
CONC BOX CULV (7 FT X 7 FT)
LF 448.000 $1,200.000 $1,006.500 $833.440 $1,500.000 $875.000 $873.730
CONC BOX CULV (8 FT X 8 FT)
LF 1,092.000 $1,500.000 $1,133.000 $1,450.930 $1,750.000 $1,000.000 $978.690
CONC BOX CULV (10 FT X 10 FT)
LF 500.000 $1,800.000 $1,754.500 $1,364.430 $2,000.000 $1,500.000 $1,624.110
WINGWALL (FW - 0) (HW=11 FT)
EA 1.000 $57,172.860 $45,313.950 $55,893.440 $65,000.000 $50,000.000 $27,771.630
WINGWALL (FW - 0) (HW=13 FT)
EA 1.000 $69,132.000 $70,213.500 $79,847.770 $80,000.000 $75,000.000 $32,034.270
WINGWALL (PW - 1) (HW=10 FT)
EA 1.000 $50,000.000 $68,744.500 $81,178.560 $75,000.000 $75,000.000 $53,605.710
WINGWALL (PW - 1) (HW=11 FT)
EA 1.000 $60,000.000 $81,424.750 $103,802.100 $85,000.000 $85,000.000 $61,355.950
WINGWALL (PW - 1) (HW=12 FT)
EA 4.000 $60,000.000 $89,284.910 $113,783.070 $82,500.000 $85,000.000 $74,272.990
WINGWALL (PW - 1) (HW=13 FT)
EA 1.000 $100,000.000 $99,821.480 $96,482.720 $130,000.000 $95,000.000 $75,564.690
WINGWALL (PW - 1) (HW=8 FT)
EA 4.000 $50,000.000 $59,812.500 $54,562.640 $45,000.000 $65,000.000 $34,488.500
WINGWALL (PW - 1) (HW=9 FT)
EA 5.000 $30,000.000 $61,407.500 $65,209.010 $50,000.000 $65,000.000 $39,009.460
CLEAN EXIST CULVERTS
EA 12.000 $2,169.000 $2,750.000 $35,369.280 $7,500.000 $5,000.000 $2,097.410
REMOV STR (BOX CULVERT)
EA 9.000 $15,000.000 $61,554.540 $46,524.100 $20,000.000 $15,000.000 $92,020.200
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
EA 1.000 $90,000.000 $220,000.000 $165,695.080 $150,000.000 $250,000.000 $150,101.570
MOBILIZATION
LS 1.000 $4,000,000.000 $3,264,413.810 $5,255,155.100 $5,626,500.000 $6,100,000.000 $6,368,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 25.000 $7,500.000 $26,081.700 $60,000.000 $70,000.000 $35,000.000 $6,646.780
ROCK FILTER DAMS (INSTALL) (TY 3)
LF 1,095.000 $100.000 $62.850 $96.790 $105.000 $100.000 $103.340
ROCK FILTER DAMS (REMOVE)
LF 1,095.000 $20.000 $37.770 $24.200 $20.000 $25.000 $25.830
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 1,244.000 $0.010 $9.700 $8.710 $15.000 $10.000 $9.300
BIODEG EROSN CONT LOGS (REMOVE)
LF 1,244.000 $0.010 $2.730 $1.210 $1.000 $2.000 $1.290
ONE-WAY TRAF CONT (PORT TRAF SIG)
MO 61.000 $6,400.000 $5,940.000 $15,671.430 $4,500.000 $3,500.000 $4,554.870
PTB(FRN&INSTL)(SSCB OR CSB)(TY1)OR(STL)
LF 1,990.000 $50.000 $33.000 $95.850 $60.000 $125.000 $101.330
PTB(MOVE)(SSCB OR CSB)(TY1)OR(STL)
LF 2,270.000 $20.000 $11.000 $37.550 $10.000 $65.000 $75.310
PTB(REMOVE)(SSCB OR CSB)(TY1)OR(STL)
LF 1,980.000 $30.000 $27.500 $24.160 $22.000 $50.000 $44.740
PERM CTB (SGL SLOPE) (TY 1) (42 )
LF 216.000 $150.000 $110.000 $282.180 $275.000 $250.000 $381.050
RUMBLE STRIPS (SHOULDER)
LF 405,181.000 $0.150 $0.070 $0.080 $0.100 $0.250 $0.200
RUMBLE STRIPS (CENTERLINE)
LF 207,468.000 $0.150 $0.070 $0.080 $0.100 $0.250 $0.200
MTL W-BEAM GD FEN (STEEL POST)
LF 16,200.000 $33.830 $30.250 $37.500 $35.500 $40.000 $35.520
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 88.000 $2,500.000 $3,376.620 $3,447.970 $3,255.000 $5,000.000 $3,745.940
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 1.000 $1,500.000 $2,200.000 $1,754.230 $1,655.000 $2,000.000 $2,583.400
MTL W - BEAM GD FEN (LOW FILL CULVERT)
LF 619.000 $85.000 $99.000 $108.880 $105.000 $125.000 $116.250
MTL BM GD FEN (LONG SPAN SYSTEM)
EA 11.000 $1,250.000 $1,375.000 $1,663.500 $1,570.000 $2,000.000 $1,614.630
REMOVE METAL BEAM GUARD FENCE
LF 23,330.000 $2.250 $1.930 $2.720 $3.000 $2.500 $2.260
GUARDRAIL END TREATMENT (INSTALL)
EA 136.000 $2,950.000 $3,300.000 $3,720.180 $3,510.000 $4,000.000 $3,875.110
CRASH CUSH ATTEN (MOVE & RESET)
EA 18.000 $1,000.000 $880.000 $6,183.760 $1,000.000 $4,000.000 $3,438.740
CRASH CUSH ATTEN (REMOVE)
EA 8.000 $1,500.000 $770.000 $4,420.660 $1,500.000 $2,000.000 $2,813.430
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 8.000 $5,000.000 $8,250.000 $23,573.240 $27,750.000 $10,000.000 $9,867.470
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 2.000 $600.000 $1,471.800 $731.940 $915.000 $800.000 $1,728.300
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 3.000 $880.000 $1,927.200 $979.950 $1,140.000 $1,000.000 $2,263.070
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 2.000 $1,200.000 $2,602.600 $1,385.240 $1,540.000 $1,500.000 $3,056.170
IN SM RD SN SUP&AM TYS80(1)SA(U-BM)
EA 2.000 $1,350.000 $2,769.800 $1,469.920 $1,655.000 $1,500.000 $3,252.510
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 51.000 $100.000 $38.500 $26.620 $34.250 $35.000 $45.210
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 34.000 $35.000 $38.500 $32.660 $57.000 $50.000 $45.210
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 185.000 $40.000 $38.500 $32.660 $57.000 $50.000 $45.210
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 13,362.000 $0.010 $4.780 $2.420 $1.250 $2.000 $1.990
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 22,236.000 $0.010 $3.140 $2.420 $1.250 $2.000 $2.020
REFL PAV MRK TY I (W)6"(DOT)(090MIL)
LF 6,564.000 $1.000 $1.100 $1.210 $1.300 $1.000 $1.290
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
LF 8,469.000 $1.000 $1.100 $1.210 $1.300 $1.000 $1.290
REFL PAV MRK TY I (W)24"(SLD)(090MIL)
LF 468.000 $10.500 $13.200 $14.520 $15.300 $12.000 $15.500
REFL PAV MRK TY I (Y)24"(SLD)(090MIL)
LF 140.000 $8.000 $16.500 $18.150 $19.150 $15.000 $19.380
REFL PAV MRK TY II (W) 6" (BRK)
LF 44,450.000 $0.170 $0.220 $0.240 $0.300 $0.200 $0.260
REFL PAV MRK TY II (W) 6" (DOT)
LF 6,564.000 $1.000 $0.500 $0.540 $0.600 $0.450 $0.580
REFL PAV MRK TY II (W) 6" (SLD)
LF 432,192.000 $0.170 $0.200 $0.220 $0.250 $0.180 $0.230
REFL PAV MRK TY II (W) 8" (SLD)
LF 8,469.000 $0.350 $0.400 $0.440 $0.500 $0.360 $0.470
REFL PAV MRK TY II (W) 24" (SLD)
LF 468.000 $3.500 $5.500 $6.050 $6.500 $5.000 $6.460
REFL PAV MRK TY II (Y) 6" (BRK)
LF 7,870.000 $0.170 $0.280 $0.300 $0.350 $0.250 $0.320
REFL PAV MRK TY II (Y) 6" (SLD)
LF 395,860.000 $0.170 $0.200 $0.220 $0.250 $0.180 $0.230
REFL PAV MRK TY II (Y) 24" (SLD)
LF 140.000 $5.000 $5.500 $6.050 $6.500 $5.000 $6.460
PAVEMENT SEALER (ARROW)
EA 64.000 $20.000 $33.000 $36.290 $38.000 $30.000 $38.750
PAVEMENT SEALER (WORD)
EA 32.000 $20.000 $66.000 $72.590 $76.500 $60.000 $77.500
RE PM W/RET REQ TY I (W)6"(BRK)(090MIL)
LF 44,450.000 $0.750 $0.720 $0.790 $0.650 $0.650 $0.840
RE PM W/RET REQ TY I (W)6"(SLD)(090MIL)
LF 432,192.000 $0.650 $0.720 $0.790 $0.650 $0.650 $0.840
RE PM W/RET REQ TY I (Y)6"(BRK)(090MIL)
LF 7,870.000 $0.750 $0.720 $0.790 $0.650 $0.650 $0.840
RE PM W/RET REQ TY I (Y)6"(SLD)(090MIL)
LF 395,860.000 $0.650 $0.720 $0.790 $0.650 $0.650 $0.840
PREFAB PAV MRK TY C (W) (ARROW)
EA 32.000 $250.000 $247.500 $272.210 $250.000 $225.000 $290.630
PREFAB PAV MRK TY C (W) (LNDP ARROW)
EA 32.000 $450.000 $522.500 $574.660 $550.000 $475.000 $613.560
PREFAB PAV MRK TY C (W) (WORD)
EA 32.000 $350.000 $357.500 $393.190 $400.000 $325.000 $419.800
REFL PAV MRKR TY I-C
EA 2,664.000 $4.000 $5.500 $6.050 $5.000 $5.000 $6.460
REFL PAV MRKR TY II-A-A
EA 8,238.000 $4.000 $5.500 $6.050 $5.000 $5.000 $6.460
FULL - WIDTH MOWING
CYC 4.000 $10,000.000 $27,078.530 $1.000 $57,500.000 $10,000.000 $11,367.000
LITTER REMOVAL
CYC 4.000 $10,000.000 $24,328.960 $17,211.540 $52,500.000 $10,000.000 $17,930.310
SP MIXES SP-C SAC-A PG70-22
TON 147,790.000 $180.000 $160.000 $123.480 $150.000 $185.000 $235.380
TACK COAT
GAL 76,431.000 $6.000 $6.340 $3.890 $5.500 $6.000 $2.880
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 896.000 $108.000 $78.640 $135.200 $50.000 $125.000 $72.740
TMA (STATIONARY)
DAY 1,044.000 $325.000 $386.070 $588.170 $275.000 $400.000 $316.200
TMA (MOBILE OPERATION)
DAY 158.000 $325.000 $554.260 $1,102.960 $650.000 $100.000 $948.440
Totals: $57,311,002.260 $52,231,940.640 $52,793,314.868 $56,263,862.400 $61,520,070.050 $69,927,828.153