Show Job Controls
Bid Cobra

HUDSPETH IH 10 (2121-06-057)

Items: 28

County: HUDSPETH
Length: 0.0000 MILES
Highway: IH 10
District: EL PASO
Control Number: 2121-06-057
DBE Goal: 0.0%
Project: C 2121-6-57
Guaranty: $15,000.00
Time: 80 WORKING DAYS
Engineer's Estimate: $751,533.84
Date: 09/05/2024 (1 year ago)
Contract Number: 9243035
Type: INFRASTRUCTURE IMPROVEMENTS
Project ID: A00203781
Project Description: INTELLIGENT TRANSPORTATION SYSTEM WORK
Mail/Deliver Bids To: N/A
RENE ROMERO
ARMANDO RAMIREZ2
ALDO MADRID
MONICA RUIZ
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (1)
E
Engineer's Estimate
$751,533.84
$752,716.50
Over/Under Est: 0.16% $1,182.66
Subcontractor Percentage Amount
SYNERGY PROJECT CONTRACTORS, INC. 5.91% $44,485.55
Total: 5.91% $44,485.55

Bid Items & Bid Tabulations

28 Total 0 of 28
HUDSPETH  |  IH 10  |  EL PASO  |  2121-06-057  |  09/05/2024  |  $751,533.84  |  C 2121-6-57  |  INFRASTRUCT IMPRVS  |  80 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
TRI STATE ELECTRIC, LTD.
PREPARING ROW
AC 0.540 $51,200.000 $3,000.000
EXCAV (SPECIAL)
CY 1.250 $2,500.000 $2,300.000
DRILL SHAFT (42 IN)
LF 63.000 $1,000.000 $900.000
DRILL SHAFT (48 IN)
LF 60.000 $1,200.000 $1,250.000
RIPRAP (CONC)(4 IN)
CY 7.500 $950.000 $600.000
RIPRAP (MOW STRIP)(4 IN)
CY 11.000 $1,000.000 $550.000
MOBILIZATION
LS 1.000 $50,000.000 $55,800.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000 $14,800.000 $15,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 20.000 $650.000 $300.000
TMA (STATIONARY)
DAY 20.000 $500.000 $275.000
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 30.000 $10.000 $25.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 30.000 $4.000 $12.000
MTL W-BEAM GD FEN (STEEL POST)
LF 150.000 $105.000 $62.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 1.000 $6,500.000 $6,000.000
GUARDRAIL END TREATMENT (INSTALL)
EA 1.000 $7,500.000 $5,500.000
CONDT (PVC) (SCH 40) (2")
LF 250.000 $38.000 $50.000
ELEC CONDR (NO.10) INSULATED
LF 165.000 $3.000 $2.500
ELEC CONDR (NO.8) INSULATED
LF 950.000 $4.000 $4.000
GROUND BOX TY A (122311)W/APRON
EA 10.000 $1,600.000 $2,500.000
ELC SRV TY D 120/240 100(NS)GS(N)GC(O)
EA 5.000 $11,000.000 $11,000.000
INS OH SN SUP(30 FT BAL TEE)
EA 2.000 $59,000.000 $68,000.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF1
EA 5.000 $37.000 $25.000
INSTALL DMS (POLE MTD CABINET)
EA 2.000 $26,333.330 $32,512.000
SYSTEM INTEGRATION
LS 1.000 $34,833.330 $40,000.000
ITS POLE (55 FT)(90 MPH)
EA 3.000 $25,964.860 $28,300.000
ITS POLE MNT CAB (TY 2)(CONF 2)
EA 3.000 $7,350.000 $6,000.000
INSTALLATION OF CELLULAR MODEM
EA 5.000 $1,668.570 $2,000.000
CCTV FIELD EQUIP (DIGITAL) (INSTL ONLY)
EA 3.000 $2,166.140 $2,000.000
Totals: $751,533.840 $752,716.500