HUDSPETH FM 192 (0957-01-019)
Items: 51
County: HUDSPETH
Length: N/A
Highway: FM 192
District: EL PASO
Control Number: 0957-01-019
DBE Goal: N/A
Project: BR 2B20(113)
Guaranty: N/A
Time: 100 WORKING DAYS
Engineer's Estimate: $582,867.48
Date: 08/05/2020 (5 years ago)
Contract Number: N/A
Type: INSTALLATION OF BOX CULVERT AND ROADWAY APPROACHES
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (7)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$582,867.48 | |||
| $423,112.00 |
-27.41%
-$159,755.48
|
|||
| $472,707.35 |
-18.9%
-$110,160.13
|
11.72%
$49,595.35
|
||
| $512,909.00 |
-12%
-$69,958.48
|
21.22%
$89,797.00
|
-8.50%
-$40,201.65
|
|
| $572,830.64 |
-1.72%
-$10,036.84
|
35.39%
$149,718.64
|
-11.68%
-$59,921.64
|
|
| $579,732.95 |
-0.54%
-$3,134.53
|
37.02%
$156,620.95
|
-1.20%
-$6,902.31
|
|
| $587,166.20 |
0.74%
$4,298.72
|
38.77%
$164,054.20
|
-1.28%
-$7,433.25
|
|
| $627,947.10 |
7.73%
$45,079.62
|
48.41%
$204,835.10
|
-6.95%
-$40,780.90
|
E
Engineer's Estimate
$582,867.48
1
$423,112.00
Over/Under Est:
-27.41%
-$159,755.48
$472,707.35
Over/Under Est:
-18.9%
-$110,160.13
Amt Left:
11.72%
$49,595.35
$512,909.00
Over/Under Est:
-12%
-$69,958.48
Amt Left:
21.22%
$89,797.00
Delta:
-8.50%
-$40,201.65
$572,830.64
Over/Under Est:
-1.72%
-$10,036.84
Amt Left:
35.39%
$149,718.64
Delta:
-11.68%
-$59,921.64
$579,732.95
Over/Under Est:
-0.54%
-$3,134.53
Amt Left:
37.02%
$156,620.95
Delta:
-1.20%
-$6,902.31
$587,166.20
Over/Under Est:
0.74%
$4,298.72
Amt Left:
38.77%
$164,054.20
Delta:
-1.28%
-$7,433.25
$627,947.10
Over/Under Est:
7.73%
$45,079.62
Amt Left:
48.41%
$204,835.10
Delta:
-6.95%
-$40,780.90
Bid Items & Bid Tabulations
51
Total
0 of 51