PREPARING ROW
|
AC
|
0.600
|
$40,000.000
|
$12,000.000
|
$40,000.000
|
|
|
EXCAVATION (SPECIAL)
|
CY
|
3.500
|
$300.000
|
$1,275.000
|
$1,100.000
|
|
|
BACKFILL (TY A OR B)
|
STA
|
1,051.000
|
$251.810
|
$175.000
|
$200.000
|
|
|
EMULS ASPH (EROSN CONT)(MULTI)
|
GAL
|
2,594.000
|
$4.500
|
$7.500
|
$4.500
|
|
|
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
|
SY
|
17,937.000
|
$53.060
|
$50.000
|
$55.000
|
|
|
PLAN & TEXT ASPH CONC PAV(0" TO 2")
|
SY
|
19,257.000
|
$5.810
|
$4.250
|
$1.750
|
|
|
PLANE ASPH CONC PAV(0" TO 1")
|
SY
|
6,253.000
|
$2.000
|
$4.750
|
$2.000
|
|
|
PLANE ASPH CONC PAV(MICRO-MLLING)(1")
|
SY
|
460,547.000
|
$0.900
|
$0.850
|
$0.750
|
|
|
PAV JT UNDERSEAL (24")
|
LF
|
480.000
|
$60.000
|
$55.000
|
$20.000
|
|
|
DRILL SHAFT (42 IN)
|
LF
|
147.000
|
$990.000
|
$1,000.000
|
$1,000.000
|
|
|
DRILL SHAFT (48 IN)
|
LF
|
30.000
|
$1,000.000
|
$1,175.000
|
$1,200.000
|
|
|
CONC STR REPR(RAPID DECK REP(FULL DPT))
|
SF
|
576.000
|
$200.000
|
$262.000
|
$210.000
|
|
|
RIPRAP (CONC)(4 IN)
|
CY
|
12.000
|
$1,000.000
|
$1,050.000
|
$700.000
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
13.000
|
$750.000
|
$850.000
|
$775.000
|
|
|
CLEANING AND SEALING EXIST JOINTS(CL3)
|
LF
|
1,732.000
|
$35.000
|
$30.500
|
$28.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$1,422,112.220
|
$336,000.000
|
$800,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
8.000
|
$10,000.000
|
$7,500.000
|
$15,000.000
|
|
|
RUMBLE STRIPS (SHOULDER) ASPHALT
|
LF
|
212,721.000
|
$0.190
|
$0.120
|
$0.250
|
|
|
MTL W-BEAM GD FEN (STEEL POST)
|
LF
|
150.000
|
$95.000
|
$42.000
|
$120.000
|
|
|
DOWNSTREAM ANCHOR TERMINAL SECTION
|
EA
|
1.000
|
$6,500.000
|
$1,475.000
|
$5,000.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
1.000
|
$7,500.000
|
$3,200.000
|
$5,000.000
|
|
|
CONDT (PVC) (SCH 40) (2")
|
LF
|
2,295.000
|
$30.000
|
$32.000
|
$32.000
|
|
|
CONDT (PVC) (SCH 40) (2") (BORE)
|
LF
|
460.000
|
$38.000
|
$40.000
|
$40.000
|
|
|
ELEC CONDR (NO.8) INSULATED
|
LF
|
2,685.000
|
$2.600
|
$3.250
|
$3.500
|
|
|
ELEC CONDR (NO.2) INSULATED
|
LF
|
6,365.000
|
$4.000
|
$5.000
|
$5.000
|
|
|
GROUND BOX TY A (122311)W/APRON
|
EA
|
20.000
|
$1,700.000
|
$1,700.000
|
$1,700.000
|
|
|
ELC SRV TY D 120/240 060(NS)GS(N)GC(O)
|
EA
|
6.000
|
$8,675.000
|
$9,125.000
|
$9,200.000
|
|
|
ELC SRV TY D 120/240 100(NS)GS(N)GC(O)
|
EA
|
1.000
|
$10,035.000
|
$11,000.000
|
$11,000.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P-BM)
|
EA
|
3.000
|
$1,000.000
|
$5,500.000
|
$6,000.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
|
EA
|
65.000
|
$1,000.000
|
$1,345.000
|
$1,400.000
|
|
|
IN SM RD SN SUP&AM (INST SIGN ONLY)
|
EA
|
2.000
|
$326.000
|
$320.000
|
$320.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
37.000
|
$180.000
|
$225.000
|
$230.000
|
|
|
INS OH SN SUP(30 FT BAL TEE)
|
EA
|
1.000
|
$56,500.000
|
$55,450.000
|
$56,000.000
|
|
|
WK ZN PAV MRK NON-REMOV (W)6"(BRK)
|
LF
|
26,686.000
|
$0.720
|
$0.320
|
$0.400
|
|
|
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
|
LF
|
111,357.000
|
$0.550
|
$0.280
|
$0.330
|
|
|
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
|
LF
|
106,560.000
|
$0.600
|
$0.290
|
$0.340
|
|
WK ZN PAV MRK SHT TERM (TAB)TY W
|
EA
|
8,864.000
|
$2.000
|
$2.260
|
$2.000
|
|
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
|
LF
|
240.000
|
$1.260
|
$3.170
|
$3.500
|
|
REFL PAV MRK TY I (W)(NUMBER)(090MIL)
|
EA
|
4.000
|
$280.000
|
$210.000
|
$220.000
|
|
REFL PAV MRK TY I(W)(ENTR GORE)(090MIL)
|
EA
|
7.000
|
$1,000.000
|
$950.000
|
$1,000.000
|
|
REFL PAV MRK TY I(W)(EXIT GORE)(090MIL)
|
EA
|
6.000
|
$745.000
|
$2,845.000
|
$3,000.000
|
|
RE PM W/RET REQ TY I (W)6"(BRK)(090MIL)
|
LF
|
26,686.000
|
$1.190
|
$1.240
|
$1.290
|
|
RE PM W/RET REQ TY I (W)6"(SLD)(090MIL)
|
LF
|
111,365.000
|
$1.190
|
$1.180
|
$1.250
|
|
RE PM W/RET REQ TY I (Y)6"(SLD)(090MIL)
|
LF
|
106,560.000
|
$1.190
|
$1.120
|
$1.170
|
|
REFL PAV MRKR TY I-R
|
EA
|
182.000
|
$15.810
|
$5.350
|
$5.500
|
|
REFL PAV MRKR TY II-C-R
|
EA
|
1,768.000
|
$4.820
|
$5.350
|
$5.500
|
|
|
D-GR HMA TY-C PG76-22 (LEVEL-UP)
|
TON
|
6.000
|
$108.000
|
$1,050.000
|
$500.000
|
|
|
STONE-MTRX-ASPH SMA-C SAC-A PG76-22
|
TON
|
63,326.000
|
$141.140
|
$155.000
|
$175.000
|
|
|
TACK COAT
|
GAL
|
69,082.000
|
$4.000
|
$5.500
|
$6.000
|
|
|
TBWC (MEMBRANE)
|
GAL
|
102,696.000
|
$5.000
|
$5.100
|
$4.500
|
|
|
TBWC PG76-22 SAC-A TY C
|
TON
|
23,340.000
|
$145.000
|
$160.000
|
$172.500
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
DAY
|
280.000
|
$100.000
|
$135.000
|
$150.000
|
|
|
CCTV FIELD EQUIP (DIGITAL) (INSTL ONLY)
|
EA
|
7.000
|
$2,300.000
|
$2,900.000
|
$3,000.000
|
|
|
INSTALL DMS (POLE MTD CABINET)
|
EA
|
1.000
|
$35,588.000
|
$38,500.000
|
$40,000.000
|
|
|
ITS POLE (55 FT)(90 MPH)
|
EA
|
7.000
|
$25,500.000
|
$27,000.000
|
$27,000.000
|
|
|
ITS POLE MNT CAB (TY 2)(CONF 2)
|
EA
|
7.000
|
$8,500.000
|
$8,600.000
|
$9,000.000
|
|
|
TMA (STATIONARY)
|
DAY
|
240.000
|
$210.560
|
$185.000
|
$250.000
|
|
|
TMA (MOBILE OPERATION)
|
DAY
|
80.000
|
$340.420
|
$315.000
|
$350.000
|
|
|
SYSTEM INTEGRATION
|
LS
|
1.000
|
$60,000.000
|
$36,500.000
|
$37,000.000
|
|
|
INSTALLATION OF CELLULAR MODEM
|
EA
|
8.000
|
$3,600.000
|
$2,900.000
|
$3,000.000
|
|
|
BACKLIT W/ PERIMETER LED RDSD SGN
|
EA
|
16.000
|
$4,865.000
|
$8,000.000
|
$9,000.000
|
|
Totals: |
$18,263,527.790
|
$18,357,209.180
|
$20,489,953.750
|