Job Info for 0002-10-039

County: HUDSPETH Highway: IH 10 Date: 09/07/2023 (1 year ago) Engineer's Estimate: $18,263,528 Control Number: 0002-10-039
Project: F 2024(040) District: EL PASO Time: 160 WORKING DAYS Type: PREVENTIVE MAINTENANCE
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12
Plans: Plans | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $18,263,527.79
DAN WILLIAMS COMPANY   $18,357,209.18 1
0.51% | $93,681.39
LESNA CONSTRUCTION, INC.   $20,489,953.75 2
12.19% | $2,226,425.96
11.62% | $2,132,744.57
Subcontractor Percentage Amount
TRI STATE ELECTRIC, LTD. 5.85% $1,073,896.74
PMI PAVEMENT MARKING, LLC 2.17% $398,351.44
WEST TEXAS ROCK RESOURCES, LLC 0.11% $20,192.93
MAJOR MOTION LOGISTICS, LLC 0.06% $11,014.33
SOUTHEAST GRINDING AND GROOVING LLC 0.03% $5,507.16
Total: 8.22% $1,508,962.60

Bid Items

Items: 61, 0 filtered
HUDSPETH IH 10  |  EL PASO  |  0002-10-039  |  09/07/2023  |  $18,263,528  |  F 2024(040)  |  PREVENT MAINT  |  160 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate DAN WILLIAMS COMPANY LESNA CONSTRUCTION, INC.
100 6001 PREPARING ROW AC 0.600 $40,000.000 $12,000.000 $40,000.000
110 6003 EXCAVATION (SPECIAL) CY 3.500 $300.000 $1,275.000 $1,100.000
134 6004 BACKFILL (TY A OR B) STA 1,051.000 $251.810 $175.000 $200.000
314 6009 EMULS ASPH (EROSN CONT)(MULTI) GAL 2,594.000 $4.500 $7.500 $4.500
351 6002 FLEXIBLE PAVEMENT STRUCTURE REPAIR(6") SY 17,937.000 $53.060 $50.000 $55.000
354 6002 PLAN & TEXT ASPH CONC PAV(0" TO 2") SY 19,257.000 $5.810 $4.250 $1.750
354 6020 PLANE ASPH CONC PAV(0" TO 1") SY 6,253.000 $2.000 $4.750 $2.000
354 6188 PLANE ASPH CONC PAV(MICRO-MLLING)(1") SY 460,547.000 $0.900 $0.850 $0.750
356 6021 PAV JT UNDERSEAL (24") LF 480.000 $60.000 $55.000 $20.000
416 6005 DRILL SHAFT (42 IN) LF 147.000 $990.000 $1,000.000 $1,000.000
416 6006 DRILL SHAFT (48 IN) LF 30.000 $1,000.000 $1,175.000 $1,200.000
429 6006 CONC STR REPR(RAPID DECK REP(FULL DPT)) SF 576.000 $200.000 $262.000 $210.000
432 6001 RIPRAP (CONC)(4 IN) CY 12.000 $1,000.000 $1,050.000 $700.000
432 6045 RIPRAP (MOW STRIP)(4 IN) CY 13.000 $750.000 $850.000 $775.000
438 6002 CLEANING AND SEALING EXIST JOINTS(CL3) LF 1,732.000 $35.000 $30.500 $28.000
500 6001 MOBILIZATION LS 1.000 $1,422,112.220 $336,000.000 $800,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 8.000 $10,000.000 $7,500.000 $15,000.000
533 6003 RUMBLE STRIPS (SHOULDER) ASPHALT LF 212,721.000 $0.190 $0.120 $0.250
540 6002 MTL W-BEAM GD FEN (STEEL POST) LF 150.000 $95.000 $42.000 $120.000
540 6016 DOWNSTREAM ANCHOR TERMINAL SECTION EA 1.000 $6,500.000 $1,475.000 $5,000.000
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 1.000 $7,500.000 $3,200.000 $5,000.000
618 6023 CONDT (PVC) (SCH 40) (2") LF 2,295.000 $30.000 $32.000 $32.000
618 6024 CONDT (PVC) (SCH 40) (2") (BORE) LF 460.000 $38.000 $40.000 $40.000
620 6008 ELEC CONDR (NO.8) INSULATED LF 2,685.000 $2.600 $3.250 $3.500
620 6016 ELEC CONDR (NO.2) INSULATED LF 6,365.000 $4.000 $5.000 $5.000
624 6002 GROUND BOX TY A (122311)W/APRON EA 20.000 $1,700.000 $1,700.000 $1,700.000
628 6128 ELC SRV TY D 120/240 060(NS)GS(N)GC(O) EA 6.000 $8,675.000 $9,125.000 $9,200.000
628 6225 ELC SRV TY D 120/240 100(NS)GS(N)GC(O) EA 1.000 $10,035.000 $11,000.000 $11,000.000
644 6002 IN SM RD SN SUP&AM TY10BWG(1)SA(P-BM) EA 3.000 $1,000.000 $5,500.000 $6,000.000
644 6004 IN SM RD SN SUP&AM TY10BWG(1)SA(T) EA 65.000 $1,000.000 $1,345.000 $1,400.000
644 6067 IN SM RD SN SUP&AM (INST SIGN ONLY) EA 2.000 $326.000 $320.000 $320.000
644 6076 REMOVE SM RD SN SUP&AM EA 37.000 $180.000 $225.000 $230.000
650 6028 INS OH SN SUP(30 FT BAL TEE) EA 1.000 $56,500.000 $55,450.000 $56,000.000
662 6005 WK ZN PAV MRK NON-REMOV (W)6"(BRK) LF 26,686.000 $0.720 $0.320 $0.400
662 6008 WK ZN PAV MRK NON-REMOV (W)6"(SLD) LF 111,357.000 $0.550 $0.280 $0.330
662 6037 WK ZN PAV MRK NON-REMOV (Y)6"(SLD) LF 106,560.000 $0.600 $0.290 $0.340
662 6109 WK ZN PAV MRK SHT TERM (TAB)TY W EA 8,864.000 $2.000 $2.260 $2.000
666 6035 REFL PAV MRK TY I (W)8"(SLD)(090MIL) LF 240.000 $1.260 $3.170 $3.500
666 6074 REFL PAV MRK TY I (W)(NUMBER)(090MIL) EA 4.000 $280.000 $210.000 $220.000
666 6080 REFL PAV MRK TY I(W)(ENTR GORE)(090MIL) EA 7.000 $1,000.000 $950.000 $1,000.000
666 6083 REFL PAV MRK TY I(W)(EXIT GORE)(090MIL) EA 6.000 $745.000 $2,845.000 $3,000.000
666 6305 RE PM W/RET REQ TY I (W)6"(BRK)(090MIL) LF 26,686.000 $1.190 $1.240 $1.290
666 6308 RE PM W/RET REQ TY I (W)6"(SLD)(090MIL) LF 111,365.000 $1.190 $1.180 $1.250
666 6320 RE PM W/RET REQ TY I (Y)6"(SLD)(090MIL) LF 106,560.000 $1.190 $1.120 $1.170
672 6008 REFL PAV MRKR TY I-R EA 182.000 $15.810 $5.350 $5.500
672 6010 REFL PAV MRKR TY II-C-R EA 1,768.000 $4.820 $5.350 $5.500
3076 6034 D-GR HMA TY-C PG76-22 (LEVEL-UP) TON 6.000 $108.000 $1,050.000 $500.000
3080 6001 STONE-MTRX-ASPH SMA-C SAC-A PG76-22 TON 63,326.000 $141.140 $155.000 $175.000
3080 6029 TACK COAT GAL 69,082.000 $4.000 $5.500 $6.000
3082 6004 TBWC (MEMBRANE) GAL 102,696.000 $5.000 $5.100 $4.500
3082 6005 TBWC PG76-22 SAC-A TY C TON 23,340.000 $145.000 $160.000 $172.500
6001 6001 PORTABLE CHANGEABLE MESSAGE SIGN DAY 280.000 $100.000 $135.000 $150.000
6010 6011 CCTV FIELD EQUIP (DIGITAL) (INSTL ONLY) EA 7.000 $2,300.000 $2,900.000 $3,000.000
6028 6001 INSTALL DMS (POLE MTD CABINET) EA 1.000 $35,588.000 $38,500.000 $40,000.000
6064 6046 ITS POLE (55 FT)(90 MPH) EA 7.000 $25,500.000 $27,000.000 $27,000.000
6064 6084 ITS POLE MNT CAB (TY 2)(CONF 2) EA 7.000 $8,500.000 $8,600.000 $9,000.000
6185 6002 TMA (STATIONARY) DAY 240.000 $210.560 $185.000 $250.000
6185 6005 TMA (MOBILE OPERATION) DAY 80.000 $340.420 $315.000 $350.000
6377 6001 SYSTEM INTEGRATION LS 1.000 $60,000.000 $36,500.000 $37,000.000
6386 6001 INSTALLATION OF CELLULAR MODEM EA 8.000 $3,600.000 $2,900.000 $3,000.000
6489 6002 BACKLIT W/ PERIMETER LED RDSD SGN EA 16.000 $4,865.000 $8,000.000 $9,000.000
Totals: $18,263,527.79 $18,357,209.18 $20,489,953.75