HUDSPETH IH 10 (0002-07-054)

Items: 49

County: HUDSPETH
Length: N/A
Highway: IH 10
District: EL PASO
Control Number: 0002-07-054
DBE Goal: N/A
Project: C 2-7-54
Guaranty: N/A
Time: 240 WORKING DAYS
Engineer's Estimate: $2,707,251.36
Date: 07/08/2020 (5 years ago)
Contract Number: N/A
Type: INSTALLATION OF QUEUE DETECTION SYSTEM
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (1)
E
Engineer's Estimate
$2,707,251.36
$2,841,820.20
Over/Under Est: 4.97% $134,568.84

Bid Items & Bid Tabulations

49 Total 0 of 49
HUDSPETH  |  IH 10  |  EL PASO  |  0002-07-054  |  07/08/2020  |  $2,707,251.36  |  C 2-7-54  |  INSTL OF QUEUE DETECTION SYSTEM  |  240 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
TRI STATE ELECTRIC, LTD.
EXCAVATION (SPECIAL)
CY 11.500 $61.150 $550.000
FLOWABLE BACKFILL
CY 30.000 $250.000 $450.000
DRILL SHAFT (30 IN)
LF 175.000 $225.000 $450.000
DRILL SHAFT (42 IN)
LF 125.000 $240.000 $525.000
DRILL SHAFT (48 IN)
LF 84.000 $365.000 $575.000
RIPRAP (CONC)(4 IN)
CY 18.750 $348.780 $500.000
RIPRAP (MOW STRIP)(4 IN)
CY 89.000 $335.480 $500.000
MOBILIZATION
LS 1.000 $150,000.000 $86,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 12.000 $10,000.000 $5,200.000
MTL W-BEAM GD FEN (STEEL POST)
LF 1,025.000 $25.140 $36.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 6.000 $1,055.000 $2,500.000
GUARDRAIL END TREATMENT (INSTALL)
EA 6.000 $2,992.000 $4,800.000
CONDT (PVC) (SCH 40) (2")
LF 8,069.000 $11.000 $12.500
CONDT (PVC) (SCH 40) (2") (BORE)
LF 644.000 $24.240 $45.000
CONDT (PVC) (SCH 40) (3")
LF 25,131.000 $16.250 $16.500
CONDT (PVC) (SCH 40) (3") (BORE)
LF 1,996.000 $33.500 $35.000
ELEC CONDR (NO.14) INSULATED
LF 31,470.000 $0.800 $1.000
ELEC CONDR (NO.8) INSULATED
LF 11,103.000 $1.600 $1.950
ELEC CONDR (NO.6) INSULATED
LF 16,706.000 $1.600 $2.250
ELEC CONDR (NO.4) INSULATED
LF 5,256.000 $1.650 $3.000
GROUND BOX TY A (122311)W/APRON
EA 32.000 $1,564.710 $1,250.000
GROUND BOX TY 1 (364860)W/APRON
EA 26.000 $1,800.000 $3,850.000
GROUND BOX TY 2 (366048)W/APRON
EA 15.000 $4,218.500 $6,500.000
ELC SRV TY D 120/240 100(NS)GS(N)GC(O)
EA 6.000 $7,470.000 $6,800.000
INS OH SN SUP(30 FT BAL TEE)
EA 3.000 $26,700.000 $31,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 20.000 $106.150 $125.000
ITS SYSTEM SUPPORT EQUIPMENT
LS 1.000 $15,000.000 $25,000.000
FIBER OPTIC CBL (SNGLE-MODE)(12 FIBER)
LF 1,213.000 $5.000 $12.000
FIBER OPTIC CBL (SNGLE-MODE)(72 FIBER)
LF 30,257.000 $8.000 $5.050
FIBER OPTIC PATCH PANEL (12 POSITION)
EA 15.000 $3,000.000 $2,600.000
FIBER OPTIC PATCH PANEL (72 POSITION)
EA 1.000 $4,500.000 $4,500.000
FO SPLICE ENCLOSURE (TYPE 1)
EA 15.000 $2,013.370 $3,500.000
ITS GRND MNT CAB (TY 4) (CONF 1)
EA 1.000 $15,700.000 $11,500.000
ITS GRND MNT CAB (TY 6) (CONF 2)
EA 1.000 $15,000.000 $12,000.000
CCTV FIELD EQUIP (DIGITAL) (INSTL ONLY)
EA 5.000 $1,353.780 $450.000
ITS POLE (30 FT)(90 MPH)
EA 7.000 $8,720.000 $7,800.000
ITS POLE (55 FT)(90 MPH)
EA 5.000 $21,000.000 $9,800.000
ITS POLE MNT CAB (TY 2)(CONF 2)
EA 12.000 $6,133.050 $4,500.000
ITS POLE MNT CAB (TY 3)(CONF 2)
EA 3.000 $7,200.000 $6,500.000
INSTALLATION OF VE
EA 1.000 $600.000 $2,500.000
INSTALLATION OF VD
EA 1.000 $600.000 $2,500.000
INSTALLATION OF FES (FIELD CABINET)
EA 16.000 $600.000 $1,250.000
INSTALLATION OF FES (HUB CABINET)
EA 3.000 $600.000 $2,500.000
TMA (STATIONARY)
DAY 207.000 $209.130 $350.000
ITS RVSD (DC ONLY) (INSTALL ONLY)
EA 11.000 $600.000 $450.000
COLOR DMS (POLE MNT CABINET)
EA 3.000 $172,000.000 $160,500.000
INSTALLATION OF CELLULAR MODEM
EA 2.000 $1,200.000 $9,500.000
CENTRAL PROCESSING UNIT
EA 1.000 $25,000.000 $105,000.000
6001 SYSTEM INTEGRATION
LS 1.000 $50,000.000 $45,000.000
Totals: $2,707,251.360 $2,841,820.200