HUDSPETH IH 10 (0002-05-050)

Items: 33

County: HUDSPETH
Length: N/A
Highway: IH 10
District: EL PASO
Control Number: 0002-05-050
DBE Goal: N/A
Project: C 2-5-50
Guaranty: N/A
Time: 238 WORKING DAYS
Engineer's Estimate: $2,203,953.53
Date: 05/08/2020 (6 years ago)
Contract Number: N/A
Type: REPLACE SUBSTANDARD METAL BEAM GUARD FENCE
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (7)
E
Engineer's Estimate
$2,203,953.53
$1,883,865.28
Over/Under Est: -14.52% -$320,088.25
$1,901,606.50
Over/Under Est: -13.72% -$302,347.03
Amt Left: 0.94% $17,741.22
Over/Under Est: -11.47% -$252,690.53
Amt Left: 3.58% $67,397.72
Delta: -2.61% -$49,656.50
Over/Under Est: -11.27% -$248,481.53
Amt Left: 3.8% $71,606.72
Delta: -0.22% -$4,209.00
$2,118,291.40
Over/Under Est: -3.89% -$85,662.13
Amt Left: 12.44% $234,426.12
Delta: -8.33% -$162,819.40
Over/Under Est: -2.69% -$59,395.23
Amt Left: 13.84% $260,693.02
Delta: -1.24% -$26,266.90
$3,288,884.78
Over/Under Est: 49.23% $1,084,931.25
Amt Left: 74.58% $1,405,019.50
Delta: -53.36% -$1,144,326.48

Bid Items & Bid Tabulations

33 Total 0 of 33
HUDSPETH  |  IH 10  |  EL PASO  |  0002-05-050  |  05/08/2020  |  $2,203,953.53  |  C 2-5-50  |  REPLACE SUBSTANDARD METAL BEAM GUARD...  |  238 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
SYNERGY PROJECT CONTRACTORS, INC.
MIJELUM, L.L.C.
INTERNATIONAL EAGLE ENTERPRISES, INC.
DEL MAR CONTRACTING, INC.
DAN WILLIAMS COMPANY
APACHE BARRICADE & SIGN
3LW CIVIL LLC
REMOVING CONC (RIPRAP)
SY 325.000 $14.000 $9.440 $20.000 $32.000 $28.000 $35.000 $65.150 $70.000
EXCAVATION (ROADWAY)
CY 18.000 $12.080 $9.440 $80.000 $180.000 $175.000 $175.000 $418.850 $30.000
EMBANKMENT (FINAL)(ORD COMP)(TY B)
CY 80.000 $30.000 $7.080 $80.000 $100.000 $120.000 $125.000 $130.570 $75.000
BLADING
HR 5.000 $142.450 $118.000 $500.000 $60.000 $230.000 $110.000 $180.550 $174.620
CL C CONC (MISC)
CY 10.000 $1,200.000 $1,239.000 $2,000.000 $800.000 $940.000 $2,000.000 $1,679.000 $3,000.000
RIPRAP (CONC)(4 IN)
CY 10.000 $504.940 $472.000 $1,200.000 $800.000 $875.000 $2,000.000 $575.000 $900.000
RIPRAP (MOW STRIP)(4 IN)
CY 816.000 $431.490 $354.000 $700.000 $450.000 $715.000 $675.000 $675.000 $750.000
RAIL (TY T552)
LF 55.000 $400.000 $118.000 $160.000 $130.000 $240.000 $200.000 $363.980 $200.000
RETROFIT RAIL (TY T551)
LF 6.000 $181.820 $118.000 $400.000 $600.000 $180.000 $1,200.000 $310.000 $500.000
MOBILIZATION
LS 1.000 $175,000.000 $118,000.000 $50,000.000 $195,000.000 $96,000.000 $200,000.000 $150,000.000 $300,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 12.000 $17,200.000 $11,800.000 $1,000.000 $10,000.000 $4,800.000 $10,000.000 $18,000.000 $25,000.000
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 749.000 $10.000 $9.440 $6.000 $4.000 $4.000 $12.000 $10.000 $10.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 749.000 $1.500 $3.540 $2.500 $1.000 $3.000 $2.600 $5.000 $4.000
PORT CTB (DES SOURCE)(F-SHAPE)(TY 1)
LF 1,525.000 $8.930 $21.240 $25.000 $16.000 $13.000 $15.000 $30.000 $70.000
PORT CTB (STKPL)(F-SHAPE)(TY 1)
LF 1,525.000 $9.440 $17.700 $15.000 $15.000 $13.000 $15.000 $30.000 $45.000
MTL W-BEAM GD FEN (STEEL POST)
LF 19,835.000 $26.000 $27.140 $26.000 $27.000 $31.000 $27.000 $23.000 $45.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 54.000 $2,494.120 $2,452.040 $2,100.000 $2,700.000 $1,900.000 $2,500.000 $2,400.000 $2,100.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 31.000 $1,127.200 $1,643.740 $1,600.000 $3,250.000 $1,600.000 $1,400.000 $1,500.000 $1,400.000
REMOVE METAL BEAM GUARD FENCE
LF 19,736.000 $2.500 $3.540 $5.000 $3.000 $3.000 $3.500 $3.750 $4.000
REMOVE TERMINAL ANCHOR SECTION
EA 31.000 $473.680 $354.000 $300.000 $290.000 $450.000 $350.000 $500.000 $350.000
GUARDRAIL END TREATMENT (INSTALL)
EA 41.000 $2,846.490 $3,030.240 $2,800.000 $3,100.000 $2,600.000 $3,600.000 $3,300.000 $3,500.000
GUARDRAIL END TREATMENT (REMOVE)
EA 41.000 $610.000 $413.000 $300.000 $400.000 $450.000 $350.000 $500.000 $350.000
CRASH CUSH ATTEN (REMOVE)
EA 4.000 $1,700.000 $531.000 $900.000 $900.000 $2,000.000 $600.000 $1,500.000 $1,700.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 4.000 $25,000.000 $10,030.000 $15,000.000 $22,000.000 $5,500.000 $9,000.000 $14,000.000 $12,000.000
INSTL DEL ASSM (D-SW)SZ 2(WC)GND
EA 15.000 $58.800 $82.600 $150.000 $60.000 $25.000 $75.000 $150.000 $125.880
INSTL DEL ASSM (D-SW)SZ (BRF)GF1 (BR)
EA 590.000 $35.000 $23.600 $60.000 $15.000 $19.000 $30.000 $25.000 $25.500
INSTL DEL ASSM (D-SY)SZ 2(WC)GND
EA 21.000 $52.370 $47.200 $100.000 $80.000 $13.000 $75.000 $119.000 $48.000
INSTL DEL ASSM (D-SY)SZ (BRF)GF1 (BR)
EA 282.000 $35.000 $24.780 $80.000 $80.000 $19.000 $30.000 $25.000 $31.000
INSTL OM ASSM (OM-3L)(TWT)GND
EA 15.000 $257.000 $247.800 $600.000 $80.000 $25.000 $200.000 $372.000 $266.450
INSTL OM ASSM (OM-3R)(TWT)GND
EA 17.000 $205.160 $236.000 $600.000 $80.000 $25.000 $200.000 $352.000 $220.690
REMOVE DELIN & OBJECT MARKER ASSMS
EA 80.000 $39.050 $35.400 $100.000 $2.000 $12.000 $50.000 $50.000 $39.500
PORTABLE CHANGEABLE MESSAGE SIGN
EA 24.000 $12,353.910 $8,260.000 $1,000.000 $90.000 $2,100.000 $650.000 $50.000 $15,000.000
TMA (STATIONARY)
DAY 167.000 $290.250 $118.000 $300.000 $270.000 $320.000 $350.000 $345.000 $350.000
Totals: $2,203,953.530 $1,883,865.280 $1,901,606.500 $1,951,263.000 $1,955,472.000 $2,118,291.400 $2,144,558.300 $3,288,884.780