Job Info for 0002-05-045

County: HUDSPETH Highway: IH 10 Date: 07/12/2017 (7 years ago) Engineer's Estimate: $677,614 Control Number: 0002-05-045
Project: NH 1702(307) District: EL PASO Time: 140 WORKING DAYS Type: CHANNEL IMPROVEMENTS

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $677,614.00
LESNA CONSTRUCTION, INC.   $603,661.00 1
-10.91% | -$73,953.00
DAN WILLIAMS COMPANY   $606,825.00 2
-10.45% | -$70,789.00
0.52% | $3,164.00
KEGLEY, INC.   $659,759.66 3
-2.63% | -$17,854.34
9.29% | $56,098.66
8.72% | $52,934.66
DEL MAR CONTRACTING, INC.   $683,560.00 4
0.88% | $5,946.00
13.24% | $79,899.00
3.61% | $23,800.34
DCI CONTRACTING, INC.   $821,456.50 5
21.23% | $143,842.50
36.08% | $217,795.50
20.17% | $137,896.50
STRUCTURAL ASSURANCE, LLC   $836,769.20 6
23.49% | $159,155.20
38.62% | $233,108.20
1.86% | $15,312.70
SJ&J CONSTRUCTION, LLC   $967,096.00 7
42.72% | $289,482.00
60.21% | $363,435.00
15.57% | $130,326.80
GILVIN-TERRILL, LTD.   $995,640.00 8
46.93% | $318,026.00
64.93% | $391,979.00
2.95% | $28,544.00
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.   $1,337,209.37 9
97.34% | $659,595.37
121.52% | $733,548.37
34.31% | $341,569.37

Bid Items

Items: 16, 0 filtered
HUDSPETH IH 10  |  EL PASO  |  0002-05-045  |  07/12/2017  |  $677,614  |  NH 1702(307)  |  CHANNEL IMPRVS  |  140 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate LESNA CONSTRUCTION, INC. DAN WILLIAMS COMPANY KEGLEY, INC. DEL MAR CONTRACTING, INC. DCI CONTRACTING, INC. STRUCTURAL ASSURANCE, LLC SJ&J CONSTRUCTION, LLC GILVIN-TERRILL, LTD. SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
100 6001 PREPARING ROW AC 1.100 $16,830.000 $9,500.000 $25,000.000 $2,875.000 $12,000.000 $13,723.660 $5,162.000 $1,200.000 $10,000.000 $20,047.260
110 6002 EXCAVATION (CHANNEL) CY 687.000 $15.000 $9.000 $25.000 $25.300 $43.000 $29.340 $21.000 $15.000 $25.000 $52.740
132 6003 EMBANKMENT (FINAL)(ORD COMP)(TY B) CY 75.000 $18.000 $11.000 $25.000 $17.250 $33.000 $90.680 $77.000 $39.000 $50.000 $72.830
156 6001 BULLDOZER WORK HR 40.000 $95.000 $50.000 $160.000 $92.000 $165.000 $119.000 $148.000 $100.000 $200.000 $274.370
432 6002 RIPRAP (CONC)(5 IN) CY 186.000 $460.000 $350.000 $600.000 $557.750 $740.000 $814.750 $663.000 $650.000 $1,000.000 $916.220
432 6033 RIPRAP (STONE PROTECTION)(18 IN) CY 51.000 $195.000 $95.000 $150.000 $132.250 $126.000 $165.370 $173.000 $180.000 $500.000 $509.010
459 6007 GABION MATTRESSES (GALV)(12 IN) SY 3,708.000 $68.000 $80.000 $65.000 $86.250 $78.000 $79.130 $75.000 $95.000 $100.000 $113.030
459 6009 GABIONS (3' X 3')(GALV) CY 698.000 $185.000 $185.000 $160.000 $212.750 $162.000 $246.870 $270.000 $340.000 $260.000 $362.080
500 6001 MOBILIZATION LS 1.000 $75,232.000 $35,000.000 $50,000.000 $31,275.510 $34,000.000 $100,640.000 $160,000.000 $200,000.000 $95,000.000 $353,488.850
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 8.000 $10,000.000 $5,000.000 $1,000.000 $1,150.000 $4,000.000 $3,230.000 $2,300.000 $2,000.000 $6,000.000 $1,359.550
506 6003 ROCK FILTER DAMS (INSTALL) (TY 3) LF 190.000 $32.000 $44.000 $80.000 $51.750 $62.000 $51.580 $95.000 $30.000 $145.000 $88.030
506 6011 ROCK FILTER DAMS (REMOVE) LF 190.000 $10.000 $6.000 $15.000 $6.900 $12.000 $15.780 $12.000 $18.000 $20.000 $10.990
506 6020 CONSTRUCTION EXITS (INSTALL) (TY 1) SY 111.000 $17.000 $22.000 $35.000 $20.700 $28.000 $49.020 $49.000 $18.000 $60.000 $51.700
506 6024 CONSTRUCTION EXITS (REMOVE) SY 111.000 $8.000 $6.000 $10.000 $5.750 $10.000 $24.510 $9.000 $8.000 $35.000 $24.900
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 220.000 $3.000 $3.000 $3.000 $2.300 $3.000 $5.440 $4.000 $3.000 $20.000 $8.130
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 220.000 $1.000 $1.000 $1.000 $1.730 $2.000 $1.360 $1.000 $1.000 $12.000 $3.610
Totals: $677,614.00 $603,661.00 $606,825.00 $659,759.66 $683,560.00 $821,456.51 $836,769.20 $967,096.00 $995,640.00 $1,337,209.38