HUDSPETH SH 20 (0002-04-034)

Items: 50

County: HUDSPETH
Length: N/A
Highway: SH 20
District: EL PASO
Control Number: 0002-04-034
DBE Goal: N/A
Project: STP 2023(472)HES
Guaranty: N/A
Time: 180 WORKING DAYS
Engineer's Estimate: $3,368,914.77
Date: 02/02/2023 (3 years ago)
Contract Number: N/A
Type: HAZARD ELIMINATION & SAFETY
Mail/Deliver Bids To: N/A
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$3,368,914.77
$3,183,455.40
Over/Under Est: -5.51% -$185,459.37
$3,203,707.85
Over/Under Est: -4.9% -$165,206.92
Amt Left: 0.64% $20,252.45
Over/Under Est: 8.16% $274,901.83
Amt Left: 14.46% $460,361.20
Delta: -13.74% -$440,108.75
Subcontractor Percentage Amount
PMI PAVEMENT MARKING, LLC 3.52% $112,500.00
PROFESSIONAL TRAFFIC CONTROL LLC 0.40% $12,784.09
Total: 3.92% $125,284.09

Bid Items & Bid Tabulations

50 Total 0 of 50
HUDSPETH  |  SH 20  |  EL PASO  |  0002-04-034  |  02/02/2023  |  $3,368,914.77  |  STP 2023(472)HES  |  HAZARD ELIM & SAFETY  |  180 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
LESNA CONSTRUCTION, INC.
DAN WILLIAMS COMPANY
INTERNATIONAL EAGLE ENTERPRISES, INC.
PREPARING ROW
STA 289.600 $350.000 $120.000 $190.000 $250.000
SUBGRADE WIDENING (DENS CONT)
SY 38,388.000 $4.500 $4.000 $5.000 $2.500
BACKFILL (TY A OR B)
STA 374.000 $185.000 $150.000 $275.000 $200.000
PROOF ROLLING
HR 10.900 $90.000 $100.000 $68.000 $32.000
FL BS (CMP IN PLACE)(TY A GR 1-2)(8")
SY 31,793.000 $20.000 $20.000 $17.000 $12.500
PRIME COAT (SS-1H)
GAL 5,079.000 $6.500 $7.500 $5.000 $8.000
ASPH (MULTI OPTION)
GAL 8,835.000 $7.000 $7.500 $5.000 $8.000
AGGR(TY-PB GR-4 SAC-B)
CY 227.000 $200.000 $110.000 $160.000 $300.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
SY 134.000 $62.000 $60.000 $120.000 $50.000
PLANE ASPH CONC PAV(0" TO 2")
SY 1,232.000 $5.000 $5.000 $4.000 $15.000
PLANE ASPH CONC PAV (0" TO 1/2" MICRO)
SY 115.000 $5.000 $15.000 $16.000 $200.000
DRILL SHAFT (18 IN)
LF 48.000 $300.000 $450.000 $200.000 $600.000
CL C CONC (RAIL FOUNDATION)
CY 15.500 $600.000 $600.000 $900.000 $1,500.000
RAIL (TY T221)
LF 20.000 $150.000 $200.000 $350.000 $200.000
RAIL (TY T221) (MOD)
LF 73.000 $250.000 $200.000 $225.000 $250.000
RETROFIT RAIL (TY T221)
LF 12.000 $150.000 $150.000 $600.000 $1,000.000
MOBILIZATION
LS 1.000 $178,985.120 $150,000.000 $208,000.000 $340,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 10.000 $10,000.000 $10,000.000 $15,000.000 $15,000.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 19,113.000 $4.000 $4.000 $2.000 $4.500
TEMP SEDMT CONT FENCE (REMOVE)
LF 19,113.000 $1.000 $1.000 $0.500 $1.000
RUMBLE STRIPS (CENTERLINE) ASPHALT
LF 29,808.000 $1.000 $0.350 $0.180 $1.750
MTL W-BEAM GD FEN (TIM POST)
LF 350.000 $32.500 $50.000 $30.000 $40.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $3,500.000 $3,500.000 $2,600.000 $2,500.000
REMOVE METAL BEAM GUARD FENCE
LF 225.000 $7.500 $4.000 $4.500 $5.000
REMOVE DOWNSTREAM ANCHOR TERMINAL
EA 2.000 $400.000 $450.000 $350.000 $500.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $4,000.000 $3,900.000 $3,200.000 $3,500.000
GUARDRAIL END TREATMENT (REMOVE)
EA 2.000 $500.000 $500.000 $350.000 $500.000
CRASH CUSH ATTEN (INSTL)(R)(N)(TL3)
EA 4.000 $10,000.000 $12,000.000 $28,000.000 $32,000.000
RELOCATE EXISTING MAILBOX
EA 15.000 $450.000 $200.000 $650.000 $800.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 9.000 $850.000 $750.000 $1,100.000 $1,000.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 3.000 $925.000 $750.000 $1,200.000 $1,100.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 1.000 $1,000.000 $850.000 $1,350.000 $1,000.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 1.000 $1,400.000 $850.000 $1,450.000 $1,000.000
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 12.000 $850.000 $500.000 $890.000 $800.000
REMOVE SM RD SN SUP&AM
EA 14.000 $135.000 $140.000 $100.000 $250.000
INSTL OM ASSM (OM-2Y)(WC)GND
EA 19.000 $75.000 $50.000 $90.000 $54.000
REMOVE DELIN & OBJECT MARKER ASSMS
EA 19.000 $25.000 $10.000 $40.000 $25.000
REFL PAV MRK TY I (W)12"(SLD)(090MIL)
LF 525.000 $3.750 $7.500 $6.500 $10.000
REF PROF PAV MRK TY I(W)6"(SLD)(090MIL)
LF 60,116.000 $0.700 $1.750 $1.500 $1.750
RE PM W/RET REQ TY I (W)6"(SLD)(090MIL)
LF 2,148.000 $0.650 $1.200 $1.120 $2.000
RE PM W/RET REQ TY I (Y)6"(BRK)(090MIL)
LF 7,363.000 $1.000 $1.300 $1.150 $2.000
RE PM W/RET REQ TY I (Y)6"(SLD)(090MIL)
LF 5,290.000 $0.750 $1.200 $1.100 $2.000
REFL PAV MRKR TY II-A-A
EA 442.000 $4.000 $6.250 $5.350 $10.000
ELIM EXT PV MRK & MRKS (RUMBLE STRIP)
LF 57,916.000 $1.000 $0.350 $0.300 $0.800
SP MIXES SP-D SAC-A PG70-22
TON 8,543.000 $145.000 $140.000 $135.000 $158.000
SP MIXES SP-D SAC-A PG70-22 (LEVEL-UP)
TON 286.000 $300.000 $200.000 $200.000 $200.000
TACK COAT
GAL 3,220.000 $7.000 $7.500 $5.000 $8.000
UNDERSEAL COURSE
GAL 20,615.000 $7.000 $7.500 $5.000 $8.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 180.000 $125.000 $140.000 $110.000 $100.000
TMA (STATIONARY)
DAY 168.000 $200.000 $125.000 $300.000 $150.000
Totals: $3,368,914.770 $3,183,455.400 $3,203,707.850 $3,643,816.600