County: HOWARD Highway: IH0020 Date: 10/06/2023 (1 year ago) Engineer's Estimate: $1,757,057 Control Number: 6451-89-001
Project: RMC - 645189001 District: ABILENE Time: 365 CALENDAR DAYS Type: METAL BEAM GUARD FENCE REPAIR
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11
Plans: Plans | Revision | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $1,757,056.55
AUSTIN BARRICADE COMPANY, L.L.C.   $1,384,501.00 1
-21.2% | -$372,555.55
DIGG COMMERCIAL, LLC   $1,479,706.00 2
-15.78% | -$277,350.55
6.88% | $95,205.00
HJC FARMS, INC.   $1,665,084.67 3
-5.23% | -$91,971.88
20.27% | $280,583.67
12.53% | $185,378.67

Bid Items

Items: 32, 0 filtered
HOWARD IH0020  |  ABILENE  |  6451-89-001  |  10/06/2023  |  $1,757,057  |  RMC - 645189001  |  METAL BEAM GUARD FENCE REPAIR  |  365 CALENDAR DAYS
Item code Description Unit Quantity Engineer's Estimate AUSTIN BARRICADE COMPANY, L.L.C. DIGG COMMERCIAL, LLC HJC FARMS, INC.
500 6033 MOBILIZATION (CALLOUT) EA 35.000 $1,000.000 $1.000 $1.000 $250.000
500 6034 MOBILIZATION (EMERGENCY) EA 100.000 $500.000 $1.000 $1.000 $1,000.000
540 6016 DOWNSTREAM ANCHOR TERMINAL SECTION EA 10.000 $1,700.000 $800.000 $1.000 $226.000
540 6037 MTL BM GD FEN TRANS (ANCHOR PLATE) EA 5.000 $800.000 $250.000 $1.000 $200.000
540 6039 MTL BM GD FEN TRANS (31"-28")(25') EA 6.000 $350.000 $880.000 $1.000 $185.000
542 6002 REMOVE TERMINAL ANCHOR SECTION EA 22.000 $350.000 $1.000 $1.000 $25.000
658 6061 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2 EA 111.000 $40.000 $19.000 $1.000 $24.000
658 6064 INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2 EA 8.000 $33.000 $90.000 $1.000 $24.000
770 6001 REPAIR RAIL ELEMENT (W - BEAM) LF 11,900.000 $30.000 $20.000 $1.000 $23.500
770 6002 REPAIR RAIL ELEMENT (THRIE - BEAM) LF 82.000 $25.000 $48.000 $1.000 $17.000
770 6003 REP RAIL ELMNT(THRIE-BM TRANS TO W -BM) LF 50.000 $20.000 $48.000 $1.000 $33.000
770 6004 REPAIR RAIL ELEMENT (CURVED RAIL) LF 875.000 $25.000 $38.000 $1.000 $27.000
770 6010 REM / REPL TIMBER/STL POST W/O CONC FND EA 827.000 $50.000 $35.000 $1.000 $22.000
770 6011 REM / REPL TIMBER / STL POST W/CONC FND EA 466.000 $100.000 $35.000 $1.000 $60.000
770 6016 REPAIR STEEL POST WITH BASE PLATE EA 10.000 $100.000 $180.000 $1.000 $150.000
770 6018 INSTALL BLOCKOUT (TYPE SPECIFIED) EA 873.000 $20.000 $10.000 $1.000 $13.000
770 6021 REPLACE SINGLE GDRAIL TERMINAL RAIL LF 350.000 $40.000 $50.000 $1.000 $48.250
770 6022 REPLACE SINGLE GDRAIL TERMINAL POST EA 33.000 $100.000 $104.000 $1.000 $310.000
770 6027 REMOVE GDRAIL END TRT / REPL WITH SGT EA 95.000 $4,000.000 $3,325.000 $1.000 $3,550.000
770 6028 REPL SINGLE GDRAIL TERM IMPACT HEAD EA 9.000 $1,000.000 $1,244.000 $500.000 $650.000
770 6029 REM & RESET SGT IMPACT HEAD EA 7.000 $350.000 $302.000 $500.000 $200.000
770 6060 REMOVE AND REPLACE DAT EA 3.000 $1,400.000 $4,500.000 $1.000 $1,226.000
771 6002 REPLACE POSTS (TL-4) EA 2,258.000 $230.000 $185.000 $1.000 $275.000
771 6004 CABLE SPLICE / TURNBUCKLE (TL-4) EA 36.000 $165.000 $150.000 $1.000 $1.000
771 6006 REPAIR CONCRETE FOUNDATION (TL-4) EA 1.000 $150.000 $500.000 $1,500.000 $50.000
771 6008 REPR OR REPLC CABLE BARR TERM SEC(TL-4) EA 61.000 $1,200.000 $500.000 $1.000 $2,000.000
771 6010 REPLACE CABLE (TL-4) LF 5,017.000 $5.000 $1.000 $1.000 $0.010
771 6011 CHECK / RE-TENSION CABLE EA 4.000 $175.000 $3,525.000 $1,500.000 $200.000
774 6007 REPAIR (TRACC) LF 9.000 $34.000 $100.000 $300.000 $1.000
774 6052 REPAIR (FASTRACC) LF 46.000 $1,000.000 $100.000 $200.000 $1.000
778 6002 CONCRETE RAIL REPAIR (MISC) LF 35.000 $223.330 $150.000 $1.000 $500.000
6185 6002 TMA (STATIONARY) DAY 186.000 $305.000 $1,000.000 $7,683.000 $250.000
Totals: $1,757,056.55 $1,384,501.00 $1,479,706.00 $1,665,084.67