County: HOWARD Highway: FM 2230 Date: 02/06/2020 (4 years ago) Engineer's Estimate: $6,187,879 Control Number: 2149-01-010
Project: C 2149-1-10 District: ABILENE Time: 216 WORKING DAYS Type: EXCAVATION, EMBANKMENT, FLEX BASE, STRUCTURES AND

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $6,187,879.07
TIERRA LEASE SERVICE, LLC   $5,693,174.52 1
-7.99% | -$494,704.55
RK HALL, LLC   $5,809,495.51 2
-6.11% | -$378,383.56
2.04% | $116,320.99
A. L. HELMCAMP, INC.   $5,986,647.22 3
-3.25% | -$201,231.85
5.15% | $293,472.70
3.05% | $177,151.71
GILVIN-TERRILL, LTD.   $6,069,518.16 4
-1.91% | -$118,360.91
6.61% | $376,343.64
1.38% | $82,870.94
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.   $6,285,462.17 5
1.58% | $97,583.10
10.4% | $592,287.65
3.56% | $215,944.01
FNH CONSTRUCTION, LLC   $8,090,749.05 6
30.75% | $1,902,869.98
42.11% | $2,397,574.53
28.72% | $1,805,286.88

Bid Items

Items: 54, 0 filtered
HOWARD FM 2230  |  ABILENE  |  2149-01-010  |  02/06/2020  |  $6,187,879  |  C 2149-1-10  |  EXCAVATION, EMBANKMENT, FLEX BASE, STRUCTS AND  |  216 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate TIERRA LEASE SERVICE, LLC RK HALL, LLC A. L. HELMCAMP, INC. GILVIN-TERRILL, LTD. SALINAS CONSTRUCTION TECHNOLOGIES, LTD. FNH CONSTRUCTION, LLC
100 6002 PREPARING ROW STA 353.000 $650.000 $200.000 $258.750 $500.000 $225.000 $726.550 $1,750.000
110 6001 EXCAVATION (ROADWAY) CY 36,487.000 $10.000 $9.500 $5.290 $11.000 $5.000 $17.960 $20.000
132 6005 EMBANKMENT (FINAL)(ORD COMP)(TY C) CY 15,554.000 $20.000 $12.500 $4.440 $9.000 $4.000 $0.210 $35.000
134 6002 BACKFILL (TY B) STA 353.000 $380.000 $200.000 $498.840 $550.000 $500.000 $523.640 $250.000
150 6002 BLADING HR 50.000 $200.000 $150.000 $172.970 $135.000 $125.000 $205.990 $150.000
164 6001 BROADCAST SEED (PERM) (RURAL) (SANDY) SY 277,011.000 $0.200 $0.150 $0.170 $0.110 $0.200 $0.170 $0.250
168 6001 VEGETATIVE WATERING MG 2,729.000 $31.570 $32.000 $41.130 $30.000 $20.000 $23.210 $35.000
247 6056 FL BS (CMP IN PLC)(TY D GR 4)(FNAL POS) CY 26,897.000 $70.000 $73.700 $52.360 $60.000 $48.000 $62.370 $52.000
251 6034 REWORK BS MTL (TY C) (8") (ORD COMP) SY 87,713.000 $1.890 $1.250 $2.820 $1.800 $2.500 $1.610 $4.000
275 6001 CEMENT TON 1,756.000 $200.000 $220.000 $248.070 $220.000 $200.000 $179.530 $210.000
275 6011 CEMENT TREAT(EXIST MATL)(8") SY 125,426.000 $4.000 $1.650 $3.110 $3.400 $2.500 $2.260 $5.000
310 6009 PRIME COAT (MC-30) GAL 22,991.000 $5.000 $4.750 $5.380 $3.600 $4.000 $5.840 $8.000
316 6001 ASPH (MULTI OPTION) GAL 51,077.000 $5.000 $3.750 $4.950 $3.400 $6.000 $4.740 $8.000
316 6017 ASPH (AC-20-5TR) GAL 39,974.000 $4.250 $3.750 $4.050 $3.400 $6.000 $5.120 $8.000
316 6222 AGGR(TY-PB GR-3 SAC-B) CY 1,058.000 $71.630 $145.000 $259.700 $165.000 $135.000 $212.400 $200.000
316 6224 AGGR(TY-PB GR-4 SAC-B) CY 966.000 $123.820 $135.000 $185.400 $155.000 $140.000 $182.880 $200.000
432 6003 RIPRAP (CONC)(6 IN) CY 153.000 $700.000 $700.000 $690.000 $640.000 $1,380.000 $565.450 $650.000
462 6001 CONC BOX CULV (3 FT X 2 FT) LF 74.000 $200.860 $500.000 $661.660 $360.000 $800.000 $393.060 $500.000
462 6003 CONC BOX CULV (4 FT X 2 FT) LF 148.000 $188.430 $550.000 $1,059.140 $380.000 $1,000.000 $336.180 $600.000
462 6004 CONC BOX CULV (4 FT X 3 FT) LF 74.000 $224.480 $575.000 $822.660 $480.000 $1,100.000 $459.560 $700.000
467 6106 SET (TY I)(S=3 FT)(HW=3FT)(4:1)(C) EA 4.000 $7,222.210 $9,500.000 $9,631.250 $17,000.000 $10,000.000 $10,024.860 $9,000.000
467 6139 SET (TY I)(S= 4 FT)(HW= 3 FT)(4:1) (C) EA 8.000 $8,400.000 $10,000.000 $6,670.000 $10,000.000 $12,000.000 $10,689.860 $9,500.000
467 6144 SET (TY I)(S= 4 FT)(HW= 4 FT)(4:1) (C) EA 4.000 $6,800.000 $11,000.000 $10,263.750 $11,000.000 $10,000.000 $11,354.860 $13,000.000
496 6006 REMOV STR (HEADWALL) EA 2.000 $249.270 $2,000.000 $1,150.000 $1,200.000 $9,000.000 $2,475.570 $3,000.000
496 6007 REMOV STR (PIPE) LF 500.000 $16.650 $20.000 $17.250 $47.000 $60.000 $17.290 $30.000
500 6001 MOBILIZATION LS 1.000 $550,000.000 $565,000.000 $473,700.700 $580,000.000 $600,000.000 $756,786.190 $800,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 12.000 $18,000.000 $3,350.000 $15,547.240 $20,000.000 $50,000.000 $4,734.640 $8,500.000
506 6002 ROCK FILTER DAMS (INSTALL) (TY 2) LF 220.000 $30.210 $30.000 $51.750 $42.000 $60.000 $50.520 $30.000
506 6011 ROCK FILTER DAMS (REMOVE) LF 220.000 $11.710 $10.000 $11.500 $11.000 $20.000 $11.510 $15.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 400.000 $3.070 $5.000 $4.600 $7.400 $10.000 $4.680 $4.000
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 400.000 $1.180 $2.000 $1.150 $1.000 $5.000 $1.380 $2.000
506 6041 BIODEG EROSN CONT LOGS (INSTL) (12") LF 864.000 $5.020 $6.000 $6.900 $7.400 $10.000 $6.730 $18.000
506 6043 BIODEG EROSN CONT LOGS (REMOVE) LF 864.000 $1.160 $2.000 $1.150 $1.000 $5.000 $1.230 $9.000
530 6006 DRIVEWAYS (SURF TREAT) SY 4,552.000 $23.840 $27.000 $41.850 $35.000 $34.320 $44.970 $36.000
644 6001 IN SM RD SN SUP&AM TY10BWG(1)SA(P) EA 25.000 $493.070 $650.000 $848.700 $775.000 $500.000 $865.980 $650.000
644 6004 IN SM RD SN SUP&AM TY10BWG(1)SA(T) EA 19.000 $670.410 $700.000 $984.400 $900.000 $600.000 $946.820 $650.000
644 6007 IN SM RD SN SUP&AM TY10BWG(1)SA(U) EA 1.000 $1,200.600 $850.000 $1,124.700 $1,000.000 $1,100.000 $1,083.730 $650.000
644 6030 IN SM RD SN SUP&AM TYS80(1)SA(T) EA 1.000 $764.370 $825.000 $1,334.000 $1,200.000 $1,200.000 $1,221.230 $650.000
644 6076 REMOVE SM RD SN SUP&AM EA 37.000 $67.650 $100.000 $152.750 $80.000 $50.000 $122.140 $150.000
658 6047 INSTL OM ASSM (OM-2Y)(WC)GND EA 30.000 $66.270 $50.000 $103.500 $95.000 $60.000 $148.730 $100.000
662 6004 WK ZN PAV MRK NON-REMOV (W)4"(SLD) LF 35,276.000 $0.280 $0.330 $0.250 $0.230 $0.220 $0.250 $0.500
662 6034 WK ZN PAV MRK NON-REMOV (Y)4"(SLD) LF 70,552.000 $0.320 $0.330 $0.250 $0.230 $0.220 $0.250 $0.500
662 6109 WK ZN PAV MRK SHT TERM (TAB)TY W EA 882.000 $1.630 $1.000 $7.210 $1.500 $1.500 $1.500 $5.000
666 6170 REFL PAV MRK TY II (W) 4" (SLD) LF 67,573.000 $0.100 $0.330 $0.160 $0.150 $0.140 $0.160 $0.500
666 6182 REFL PAV MRK TY II (W) 24" (SLD) LF 127.000 $3.500 $8.000 $0.930 $0.850 $0.810 $1.780 $2.000
666 6205 REFL PAV MRK TY II (Y) 4" (BRK) LF 8,429.000 $0.110 $0.330 $0.160 $0.150 $0.140 $0.170 $0.500
666 6207 REFL PAV MRK TY II (Y) 4" (SLD) LF 7,579.000 $0.100 $0.330 $0.160 $0.150 $0.140 $0.170 $0.500
666 6303 RE PM W/RET REQ TY I (W)4"(SLD)(100MIL) LF 67,573.000 $0.310 $0.850 $0.520 $0.470 $0.450 $0.500 $0.800
666 6312 RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL) LF 8,429.000 $0.310 $0.850 $0.520 $0.470 $0.450 $0.510 $0.800
666 6315 RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL) LF 7,579.000 $0.320 $0.850 $0.520 $0.470 $0.450 $0.510 $0.800
672 6009 REFL PAV MRKR TY II-A-A EA 516.000 $2.620 $4.000 $3.740 $3.500 $3.250 $3.790 $6.000
6001 6002 PORTABLE CHANGEABLE MESSAGE SIGN EA 2.000 $14,971.440 $18,000.000 $18,329.040 $25,000.000 $17,500.000 $23,816.160 $16,500.000
6185 6002 TMA (STATIONARY) DAY 117.000 $250.000 $350.000 $414.800 $350.000 $582.000 $312.100 $400.000
6185 6005 TMA (MOBILE OPERATION) DAY 38.000 $250.000 $350.000 $536.170 $100.000 $950.000 $503.970 $650.000
Totals: $6,187,879.07 $5,693,174.52 $5,809,495.51 $5,986,647.22 $6,069,518.16 $6,285,462.17 $8,090,749.05