HOWARD FM 1584 (1503-02-011)

Items: 54

County: HOWARD
Length: N/A
Highway: FM 1584
District: ABILENE
Control Number: 1503-02-011
DBE Goal: N/A
Project: STP 1802(505)HES
Guaranty: N/A
Time: 210 WORKING DAYS
Engineer's Estimate: $3,142,590.82
Date: 08/08/2018 (7 years ago)
Contract Number: N/A
Type: PAVEMENT WIDENING
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (6)
E
Engineer's Estimate
$3,142,590.82
$3,443,262.37
Over/Under Est: 9.57% $300,671.55
$3,551,765.24
Over/Under Est: 13.02% $409,174.42
Amt Left: 3.15% $108,502.87
Over/Under Est: 20.76% $652,328.89
Amt Left: 10.21% $351,657.34
Delta: -6.85% -$243,154.47
$3,804,710.66
Over/Under Est: 21.07% $662,119.84
Amt Left: 10.5% $361,448.29
Delta: -0.26% -$9,790.95
Over/Under Est: 26.44% $830,841.84
Amt Left: 15.4% $530,170.29
Delta: -4.43% -$168,722.00
$4,340,948.98
Over/Under Est: 38.13% $1,198,358.16
Amt Left: 26.07% $897,686.61
Delta: -9.25% -$367,516.32

Bid Items & Bid Tabulations

54 Total 0 of 54
HOWARD  |  FM 1584  |  ABILENE  |  1503-02-011  |  08/08/2018  |  $3,142,590.82  |  STP 1802(505)HES  |  PAVMT WIDENING  |  210 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
DELHUR INDUSTRIES, INC.
A. L. HELMCAMP, INC.
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
GILVIN-TERRILL, LTD.
NOBLES ROAD CONSTRUCTION, INC.
RK HALL, LLC
EXCAVATION (ROADWAY)
CY 739.000 $14.500 $18.000 $25.000 $10.860 $15.000 $7.150 $27.150
SUBGRADE WIDENING (DENS CONT)
STA 478.680 $424.000 $420.000 $50.000 $405.200 $700.000 $472.000 $708.450
BROADCAST SEED (PERM) (RURAL) (SANDY)
AC 28.000 $361.000 $598.560 $500.000 $829.100 $750.000 $435.000 $630.000
VEGETATIVE WATERING
MG 1,620.000 $59.300 $43.840 $23.000 $12.700 $20.000 $50.000 $44.500
PROOF ROLLING
HR 200.000 $64.300 $120.000 $65.000 $64.610 $85.000 $65.000 $107.980
FL BS (CMP IN PLC)(TYD GR1-2)(FNAL POS)
CY 28,192.000 $36.200 $44.330 $59.000 $56.570 $40.000 $57.200 $54.780
REWORK BS MTL (TY C) (6") (DENS CONT)
STA 233.000 $1,340.000 $360.000 $550.000 $1,061.920 $2,550.000 $1,205.000 $1,246.600
REWORK BS MTL (TY B) (6") (DENS CONT)
SY 3,173.000 $9.100 $3.600 $5.500 $4.320 $10.000 $14.000 $16.800
PRIME COAT (MC-30)
GAL 22,699.000 $4.550 $5.060 $4.000 $2.830 $3.500 $4.250 $5.050
ASPH (MULTI OPTION)
GAL 34,048.000 $3.850 $4.400 $3.600 $2.810 $3.000 $4.250 $4.090
AGGR(TY-D GR-3 SAC-B)
CY 721.000 $167.650 $132.020 $110.000 $127.350 $83.000 $95.000 $143.830
AGGR(TY-D GR-4 SAC-B)
CY 658.000 $63.200 $132.020 $110.000 $120.790 $83.000 $95.000 $104.510
ASPH (AC-20-5TR OR AC-20XP)
GAL 27,238.000 $3.050 $3.850 $4.000 $2.790 $4.000 $4.250 $3.680
FLOWABLE BACKFILL
CY 241.000 $289.000 $203.500 $350.000 $220.240 $300.000 $290.000 $262.500
GABION MATTRESSES (GALV)(12 IN)
SY 88.000 $167.600 $48.000 $110.000 $6.800 $250.000 $210.000 $140.950
CMP AR (GAL STL DES 3)
LF 2,043.000 $50.000 $56.900 $65.000 $29.910 $50.000 $75.000 $57.750
RC PIPE (CL IV)(30 IN)
LF 610.000 $135.250 $116.030 $125.000 $170.830 $150.000 $150.000 $183.750
SET (TY II) (30 IN) (RCP) (3: 1) (C)
EA 26.000 $1,650.000 $1,500.000 $2,500.000 $2,154.570 $2,000.000 $2,200.000 $2,625.000
SET (TY II) (DES 3) (CMP) (6: 1) (P)
EA 62.000 $1,180.000 $1,240.500 $1,000.000 $550.470 $2,000.000 $1,700.000 $2,100.000
REMOV STR (PIPE)
LF 314.000 $21.000 $18.000 $50.000 $21.670 $20.000 $10.000 $10.500
REMOV STR (BOX CULVERT)
LF 30.000 $37.400 $18.000 $200.000 $81.080 $150.000 $400.000 $105.000
MOBILIZATION
LS 1.000 $312,890.000 $374,500.000 $340,000.000 $632,820.110 $300,000.000 $322,000.000 $430,001.070
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 12.000 $5,000.000 $14,500.000 $10,000.000 $3,423.050 $12,500.000 $3,850.000 $13,595.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 70.000 $34.100 $41.840 $45.000 $40.140 $45.000 $44.000 $37.710
ROCK FILTER DAMS (REMOVE)
LF 70.000 $8.100 $17.590 $18.000 $17.040 $12.000 $17.000 $23.320
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 222.000 $20.000 $34.580 $10.000 $25.270 $20.000 $38.000 $29.100
CONSTRUCTION EXITS (REMOVE)
SY 222.000 $5.000 $11.010 $4.000 $18.120 $4.500 $11.000 $14.710
TEMP SEDMT CONT FENCE (INSTALL)
LF 2,465.000 $3.700 $5.040 $4.000 $3.900 $3.000 $3.850 $5.380
TEMP SEDMT CONT FENCE (REMOVE)
LF 2,465.000 $1.250 $2.880 $1.000 $1.420 $1.500 $1.000 $1.810
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 960.000 $5.100 $9.000 $5.000 $5.620 $5.000 $5.500 $4.890
BIODEG EROSN CONT LOGS (REMOVE)
LF 960.000 $0.500 $2.380 $1.000 $2.320 $1.000 $1.000 $1.110
DRIVEWAYS (SURF TREAT)
SY 2,786.000 $16.000 $27.600 $24.000 $27.250 $35.000 $30.000 $50.640
TURNOUTS (SURF TREAT)
SY 8.000 $25.000 $52.250 $600.000 $294.250 $35.000 $155.000 $416.080
MAILBOX INSTALL-S (TWW-POST) TY 4
EA 1.000 $500.000 $275.000 $400.000 $389.810 $600.000 $750.000 $262.500
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 24.000 $752.000 $949.500 $950.000 $912.280 $500.000 $825.000 $866.250
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 2.000 $964.000 $1,158.500 $1,150.000 $1,173.910 $650.000 $1,012.000 $1,065.750
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 2.000 $1,135.000 $1,301.500 $1,350.000 $1,316.910 $800.000 $1,210.000 $1,202.250
REMOVE SM RD SN SUP&AM
EA 24.000 $88.000 $110.000 $100.000 $169.780 $55.000 $165.000 $105.000
INSTL OM ASSM (OM-2Y)(WC)GND
EA 4.000 $79.000 $82.500 $100.000 $111.200 $75.000 $70.000 $78.750
REMOVE DELIN & OBJECT MARKER ASSMS
EA 4.000 $15.000 $13.200 $25.000 $41.900 $40.000 $22.000 $12.600
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 48,454.000 $0.300 $0.180 $0.380 $0.300 $0.270 $0.380 $0.280
WK ZN PAV MRK NON-REMOV (Y)4"(BRK)
LF 5,950.000 $0.250 $0.120 $0.380 $0.320 $0.270 $0.380 $0.280
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 6,629.000 $0.350 $0.120 $0.380 $0.310 $0.270 $0.380 $0.280
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 2,125.000 $0.200 $1.700 $0.600 $1.020 $1.000 $1.650 $1.440
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 120.000 $9.000 $4.130 $8.500 $31.760 $28.000 $17.600 $29.400
REFL PAV MRK TY II (Y) 24" (SLD)
LF 133.000 $10.000 $0.720 $6.000 $2.790 $1.750 $4.400 $1.840
REF PROF PAV MRK TY I(W)4"(SLD)(100MIL)
LF 48,454.000 $0.550 $0.640 $0.900 $0.830 $0.750 $0.820 $0.790
REF PROF PAV MRK TY I(Y)4"(BRK)(100MIL)
LF 5,950.000 $0.550 $0.640 $1.100 $0.840 $0.750 $0.820 $0.790
REF PROF PAV MRK TY I(Y)4"(SLD)(100MIL)
LF 6,764.000 $0.550 $0.640 $0.900 $0.840 $0.750 $0.820 $0.790
REFL PAV MRKR TY II-A-A
EA 384.000 $6.400 $5.500 $5.800 $4.700 $4.000 $3.300 $4.200
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $10,155.000 $18,975.000 $6,000.000 $4,978.700 $15,000.000 $15,000.000 $12,486.930
PREFORMED CENTERLINE RUMBLE STRIP
LF 745.000 $4.600 $17.710 $8.000 $22.150 $20.000 $4.000 $21.000
TMA (STATIONARY)
DAY 6.000 $600.000 $960.000 $1,000.000 $2,769.140 $2,850.000 $5,000.000 $131.150
TMA (MOBILE OPERATION)
DAY 2.000 $800.000 $3,000.000 $650.000 $2,807.410 $950.000 $5,000.000 $673.170
Totals: $3,142,590.820 $3,443,262.370 $3,551,765.240 $3,794,919.716 $3,804,710.660 $3,973,432.660 $4,340,948.986