Show Job Controls
Bid Cobra

HOWARD VA (0908-12-031)

Items: 50

County: HOWARD
Length: N/A
Highway: VA
District: ABILENE
Control Number: 0908-12-031
DBE Goal: N/A
Project: STP 2B20(264)FRS
Guaranty: N/A
Time: 56 WORKING DAYS
Engineer's Estimate: $549,000.95
Date: 10/01/2020 (5 years ago)
Contract Number: N/A
Type: RXR CROSSING & INTERSECTION IMPROVEMENTS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (3)
E
Engineer's Estimate
$549,000.95
1
$715,429.39
Over/Under Est: 30.31% $166,428.44
Over/Under Est: 44.5% $244,309.65
Amt Left: 10.89% $77,881.21
Over/Under Est: 56.08% $307,860.55
Amt Left: 19.77% $141,432.11
Delta: -8.01% -$63,550.90

Bid Items & Bid Tabulations

50 Total 0 of 50
HOWARD  |  VA  |  ABILENE  |  0908-12-031  |  10/01/2020  |  $549,000.95  |  STP 2B20(264)FRS  |  RXR CROSSING & INTERS IMPRVS  |  56 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
RK HALL, LLC
TIERRA LEASE SERVICE, LLC
FNH CONSTRUCTION, LLC
PREPARING ROW
STA 9.200 $1,000.000 $579.580 $450.000 $6,500.000
EXCAVATION (ROADWAY)
CY 15.000 $9.000 $127.480 $60.000 $30.000
EXCAVATION (CHANNEL)
CY 5.000 $20.000 $77.180 $60.000 $50.000
EMBANKMENT (FINAL)(DENS CONT)(TY A)
CY 509.000 $20.000 $52.430 $60.000 $35.000
FURNISHING AND PLACING TOPSOIL (4")
SY 4,082.000 $3.000 $2.670 $5.000 $6.000
BROADCAST SEED (PERM) (RURAL) (CLAY)
SY 4,082.000 $0.600 $0.560 $0.500 $1.000
VEGETATIVE WATERING
MG 34.300 $28.000 $55.980 $32.000 $50.000
SOIL RETENTION BLANKETS (CL 1) (TY A)
SY 4,082.000 $1.000 $1.200 $2.250 $6.500
ASPH (MULTI OPTION)
GAL 2,501.000 $7.650 $5.190 $5.000 $10.000
AGGR(TY-B GR-4 SAC-B)
CY 45.000 $136.000 $305.050 $285.000 $350.000
PLANE ASPH CONC PAV (2")
SY 702.000 $1.900 $25.410 $15.000 $20.000
STRUCT EXCAV (PIPE)
CY 155.000 $8.000 $30.250 $32.000 $30.000
TRENCH EXCAVATION PROTECTION
LF 173.000 $2.000 $49.430 $5.000 $10.000
RC PIPE (CL V)(30 IN)
LF 202.000 $200.000 $226.860 $175.000 $125.000
SET (TY II) (30 IN) (RCP) (6: 1) (C)
EA 2.000 $2,800.000 $4,192.220 $4,300.000 $4,000.000
SET (TY II) (30 IN) (RCP) (6: 1) (P)
EA 2.000 $2,800.000 $4,192.220 $4,300.000 $4,000.000
REMOV STR (PIPE)
LF 108.000 $20.000 $39.920 $45.000 $30.000
MOBILIZATION
LS 1.000 $55,000.000 $70,000.000 $95,000.000 $85,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000 $9,000.000 $6,608.790 $3,250.000 $8,500.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 111.000 $30.000 $26.640 $20.000 $45.000
CONSTRUCTION EXITS (REMOVE)
SY 111.000 $10.000 $16.960 $10.000 $20.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 580.000 $3.000 $6.920 $4.000 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 580.000 $1.000 $2.070 $2.000 $2.000
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 175.000 $5.000 $9.950 $6.000 $18.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 175.000 $1.500 $2.380 $2.000 $9.000
CONC CURB (TY II)
LF 61.000 $20.000 $283.580 $160.000 $50.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 2.000 $700.000 $1,032.000 $1,100.000 $850.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 13.000 $800.000 $1,140.000 $1,100.000 $850.000
REMOVE SM RD SN SUP&AM
EA 12.000 $300.000 $80.530 $125.000 $250.000
WK ZN PAV MRK REMOV (TRAF BTN) TY W
LF 1,996.000 $1.000 $3.600 $1.500 $5.000
WK ZN PAV MRK REMOV (TRAF BTN) TY Y
LF 2,143.000 $1.000 $3.600 $1.500 $5.000
WK ZN PAV MRK REMOV (W)24"(SLD)
LF 11.000 $10.000 $60.000 $5.500 $10.000
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 4,151.000 $1.000 $1.200 $1.000 $1.000
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 4,260.000 $1.000 $1.200 $1.000 $1.000
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 150.000 $11.000 $24.000 $13.000 $15.000
PREFAB PAV MRK TY C (W) (RR XING)
EA 1.000 $500.000 $962.400 $700.000 $1,000.000
PREFAB PAV MRK TY C (W) (36")(YLD TRI)
EA 3.000 $30.000 $120.000 $45.000 $150.000
REFL PAV MRKR TY II-A-A
EA 104.000 $3.000 $12.000 $5.000 $5.000
ELIM EXT PAV MRK & MRKS (4")
LF 3,376.000 $1.000 $3.600 $2.250 $1.500
ELIM EXT PAV MRK & MRKS (24")
LF 36.000 $3.000 $21.600 $5.500 $1.500
PAV SURF PREP FOR MRK (4")
LF 2,896.000 $1.000 $1.200 $0.500 $0.500
PAV SURF PREP FOR MRK (24")
LF 25.000 $1.000 $1.200 $1.500 $1.500
PAV SURF PREP FOR MRK (RR XING)
EA 1.000 $20.000 $120.000 $100.000 $250.000
PAV SURF PREP FOR MRK (36")(YLD TRI)
EA 3.000 $5.000 $24.000 $75.000 $250.000
SP MIXES SP-B PG64-22
TON 1,886.000 $120.000 $131.690 $170.000 $165.000
SP MIXES SP-D PG64-22 (LEVEL-UP)
TON 83.000 $110.000 $220.850 $335.000 $185.000
SP MIXES SP-D SAC-B PG76-22
TON 306.000 $110.000 $142.820 $225.000 $165.000
TACK COAT
GAL 776.000 $7.650 $11.750 $5.500 $10.000
TMA (STATIONARY)
DAY 90.000 $150.000 $212.780 $325.000 $350.000
TMA (MOBILE OPERATION)
DAY 10.000 $200.000 $550.070 $325.000 $550.000
Totals: $549,000.950 $715,429.400 $793,310.600 $856,861.500