Bid Cobra

HOWARD US 87 (0068-08-067)

Items: 62

County: HOWARD
Length: N/A
Highway: US 87
District: ABILENE
Control Number: 0068-08-067
DBE Goal: N/A
Project: F 2021(846)
Guaranty: N/A
Time: 198 WORKING DAYS
Engineer's Estimate: $7,292,455.80
Date: 08/05/2021 (4 years ago)
Contract Number: N/A
Type: REHABILITATE EXISTING ROADWAY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Documents:
Bidders (6)
E
Engineer's Estimate
$7,292,455.80
1
$6,899,249.88
Over/Under Est: -5.39% -$393,205.92
$7,055,762.70
Over/Under Est: -3.25% -$236,693.10
Amt Left: 2.27% $156,512.82
Over/Under Est: -1.88% -$136,989.07
Amt Left: 3.71% $256,216.85
Delta: -1.41% -$99,704.03
$7,528,027.48
Over/Under Est: 3.23% $235,571.68
Amt Left: 9.11% $628,777.60
Delta: -5.21% -$372,560.75
$7,565,691.62
Over/Under Est: 3.75% $273,235.82
Amt Left: 9.66% $666,441.74
Delta: -0.50% -$37,664.14
$9,401,233.70
Over/Under Est: 28.92% $2,108,777.90
Amt Left: 36.26% $2,501,983.82
Delta: -24.26% -$1,835,542.08

Bid Items & Bid Tabulations

62 Total 0 of 62
HOWARD  |  US 87  |  ABILENE  |  0068-08-067  |  08/05/2021  |  $7,292,455.80  |  F 2021(846)  |  REHAB EXIST ROADWAY  |  198 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
RK HALL, LLC
REECE ALBERT, INC.
DELHUR INDUSTRIES, INC.
A. L. HELMCAMP, INC.
FNF CONSTRUCTION, INC.
CK NEWBERRY, LLC
REMOVING STAB BASE AND ASPH PAV (2")
SY 372.000 $2.250 $6.850 $8.780 $12.000 $8.750 $12.500 $15.000
EXCAVATION (ROADWAY)
CY 6.000 $15.000 $59.410 $24.740 $120.000 $200.000 $180.000 $100.000
BACKFILL (TY B)
STA 413.200 $300.000 $207.990 $221.470 $240.000 $90.000 $105.000 $225.000
BROADCAST SEED (PERM) (RURAL) (SANDY)
SY 33,898.000 $0.170 $0.120 $0.120 $0.280 $0.120 $0.200 $0.300
DRILL SEEDING (TEMP) (WARM)
SY 16,949.000 $0.070 $0.140 $0.140 $0.330 $0.140 $0.200 $0.350
DRILL SEEDING (TEMP) (COOL)
SY 16,949.000 $0.070 $0.150 $0.150 $0.330 $0.150 $0.200 $0.350
VEGETATIVE WATERING
MG 570.600 $9.500 $54.990 $59.460 $37.800 $10.000 $35.000 $20.000
CEMENT
TON 1,733.000 $179.000 $202.100 $235.280 $184.800 $220.000 $210.000 $250.000
CEMENT TREAT (EXIST MATL)(12")
SY 96,313.000 $2.500 $2.220 $3.860 $2.560 $2.350 $2.000 $2.000
PRIME COAT (MC-30)
GAL 19,263.000 $4.500 $4.830 $4.340 $4.790 $4.000 $4.500 $5.000
STONE-MTRX-ASPH SMA-D SAC-A PG76-22
TON 20,426.000 $130.000 $139.490 $138.100 $139.910 $162.000 $140.000 $145.000
TACK COAT
GAL 18,569.000 $3.000 $3.880 $2.350 $4.180 $3.000 $4.500 $5.000
PLANE ASPH CONC PAV (2")
SY 91,740.000 $1.670 $1.060 $1.150 $1.100 $1.750 $1.500 $1.000
RIPRAP (CONC)(5 IN)
CY 29.000 $650.000 $865.700 $502.980 $550.000 $525.000 $450.000 $700.000
RIPRAP (MOW STRIP)(4 IN)
CY 810.000 $650.000 $422.850 $412.480 $418.000 $394.000 $425.000 $600.000
GABION MATTRESSES (GALV)(12 IN)
SY 34.000 $75.000 $386.730 $382.940 $60.000 $105.000 $145.000 $250.000
SET (PIPE RUNNER ASSEMBLY)
EA 4.000 $2,220.000 $9,739.400 $24.980 $3,228.500 $2,625.000 $500.000 $12,000.000
SET (REPLACE PIPE RUNNER ASSEMBLY)
EA 1.000 $2,220.000 $6,475.700 $7,258.450 $9,278.500 $8,400.000 $5,000.000 $8,000.000
SET (TY I)(S= 5 FT)(HW= 3 FT)(4:1) (C)
EA 12.000 $9,000.000 $4,290.000 $4,333.170 $7,628.500 $6,825.000 $8,000.000 $7,000.000
SET (TY I)(S= 7 FT)(HW= 3 FT)(4:1) (C)
EA 6.000 $9,500.000 $6,807.900 $6,716.020 $10,928.500 $9,975.000 $80,000.000 $10,000.000
CLEAN EXIST CULVERTS
EA 14.000 $1,600.000 $7,510.210 $2,919.180 $1,440.000 $2,100.000 $800.000 $2,500.000
REMOV STR (WINGWALL)
EA 4.000 $990.000 $4,265.800 $1,984.830 $1,800.000 $1,575.000 $3,000.000 $1,500.000
MOBILIZATION
LS 1.000 $662,950.530 $304,202.480 $313,338.670 $607,000.000 $525,000.000 $750,000.000 $1,250,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 10.000 $9,500.000 $12,014.780 $3,208.280 $12,047.000 $7,500.000 $22,500.000 $25,000.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 800.000 $5.250 $6.100 $3.960 $9.600 $3.900 $6.000 $10.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 800.000 $1.350 $1.880 $1.070 $2.400 $1.000 $1.000 $2.000
CONSTRUCTING DETOURS
SY 3,503.000 $60.000 $97.340 $124.750 $67.410 $48.000 $40.000 $150.000
INTERSECTIONS (ACP)
SY 604.000 $60.000 $49.920 $44.370 $28.900 $56.000 $33.000 $50.000
DRIVEWAYS (ACP)
SY 1,550.000 $60.000 $40.120 $43.470 $28.900 $47.000 $52.000 $50.000
RUMBLE STRIPS (SHOULDER)
LF 68,666.000 $0.250 $0.220 $0.140 $0.110 $0.160 $0.120 $0.500
MTL W-BEAM GD FEN (TIM POST)
LF 275.000 $22.000 $31.080 $31.010 $31.900 $32.500 $28.000 $35.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 2.000 $1,200.000 $1,760.000 $1,871.500 $2,832.500 $1,550.000 $1,900.000 $2,500.000
MTL W - BEAM GD FEN (LOW FILL CULVERT)
LF 50.000 $105.000 $55.000 $208.540 $214.500 $89.000 $205.000 $300.000
REMOVE METAL BEAM GUARD FENCE
LF 325.000 $2.000 $3.300 $1.660 $1.710 $10.000 $2.000 $2.000
REMOVE TERMINAL ANCHOR SECTION
EA 2.000 $200.000 $330.000 $374.300 $385.000 $525.000 $450.000 $500.000
CABLE BARRIER SYSTEM (TL-4)
LF 20,505.000 $8.500 $14.800 $14.380 $15.330 $13.000 $13.750 $18.000
CABLE BARRIER TERMINAL SECTION (TL-4)
EA 26.000 $2,250.000 $2,090.000 $2,031.910 $2,090.000 $2,350.000 $2,500.000 $6,000.000
GUARDRAIL END TREATMENT (INSTALL)
EA 2.000 $2,600.000 $3,657.500 $3,208.280 $3,300.000 $3,300.000 $3,250.000 $3,500.000
GUARDRAIL END TREATMENT (REMOVE)
EA 2.000 $325.000 $330.000 $219.230 $225.500 $525.000 $300.000 $250.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 55.000 $550.000 $660.000 $641.660 $660.000 $630.000 $700.000 $800.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P-BM)
EA 27.000 $700.000 $1,045.000 $1,015.950 $1,045.000 $998.000 $800.000 $1,000.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 5.000 $850.000 $990.000 $962.480 $990.000 $945.000 $900.000 $1,000.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 6.000 $1,200.000 $770.000 $748.600 $770.000 $735.000 $1,000.000 $1,200.000
IN SM RD SN SUP&AM TY10BWG(2)SA(P-EXAL)
EA 1.000 $1,300.000 $1,320.000 $1,283.310 $1,320.000 $1,260.000 $1,300.000 $2,000.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 3.000 $990.000 $1,100.000 $1,069.430 $1,100.000 $1,050.000 $1,000.000 $1,500.000
REMOVE SM RD SN SUP&AM
EA 38.000 $100.000 $91.840 $106.940 $110.000 $105.000 $125.000 $200.000
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 436.000 $0.250 $0.240 $0.240 $0.240 $0.230 $2.000 $1.000
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 41,350.000 $0.250 $0.240 $0.240 $0.240 $0.230 $0.300 $0.500
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 2,478.000 $0.550 $2.200 $2.140 $2.200 $2.100 $2.000 $3.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 2,541.000 $1.500 $3.190 $1.910 $2.200 $0.580 $2.500 $2.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 4,340.000 $0.750 $0.970 $0.940 $0.970 $0.920 $0.950 $2.000
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 10,553.000 $0.400 $0.500 $0.480 $0.500 $0.470 $0.500 $1.000
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 42,981.000 $0.400 $0.480 $0.470 $0.480 $0.460 $0.500 $1.000
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 41,455.000 $0.400 $0.480 $0.470 $0.480 $0.460 $0.500 $1.000
PREFAB PAV MRK TY B (W)(24")(SLD)
LF 12.000 $31.000 $27.500 $26.740 $27.500 $26.250 $55.000 $30.000
PREFAB PAV MRK TY C (W) (36")(YLD TRI)
EA 176.000 $31.000 $38.500 $37.430 $38.500 $36.750 $50.000 $50.000
REFL PAV MRKR TY II-C-R
EA 747.000 $3.250 $3.580 $3.480 $3.580 $3.410 $4.750 $4.000
ELIM EXT PAV MRK & MRKS (4")
LF 1,450.000 $1.000 $2.200 $2.140 $2.200 $2.100 $3.000 $3.000
SP MIXES SP-C PG64-22
TON 10,091.000 $130.000 $95.680 $105.130 $101.670 $124.000 $93.500 $150.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $10,000.000 $10,406.020 $12,983.350 $19,250.000 $15,000.000 $6,000.000 $25,000.000
TMA (STATIONARY)
DAY 228.000 $250.000 $133.440 $189.760 $288.000 $100.000 $180.000 $350.000
TMA (MOBILE OPERATION)
DAY 22.000 $200.000 $304.350 $618.060 $360.000 $1,000.000 $635.000 $400.000
Totals: $7,292,455.800 $6,899,249.892 $7,055,762.710 $7,155,466.730 $7,528,027.480 $7,565,691.620 $9,401,233.700