HOWARD US 87 (0068-07-052)
Items: 30
County: HOWARD
Length: N/A
Highway: US 87
District: ABILENE
Control Number: 0068-07-052
DBE Goal: N/A
Project: F 2021(845)
Guaranty: N/A
Time: 64 WORKING DAYS
Engineer's Estimate: $3,131,429.43
Date: 08/04/2021 (4 years ago)
Contract Number: N/A
Type: HIGHWAY IMPROVEMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (6)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$3,131,429.43 | |||
| $2,550,798.00 |
-18.54%
-$580,631.43
|
|||
| $2,608,629.24 |
-16.7%
-$522,800.19
|
2.27%
$57,831.24
|
||
| $3,107,995.18 |
-0.75%
-$23,434.25
|
21.84%
$557,197.18
|
-19.14%
-$499,365.94
|
|
| $3,327,206.00 |
6.25%
$195,776.57
|
30.44%
$776,408.00
|
-7.05%
-$219,210.82
|
|
| $3,540,010.15 |
13.05%
$408,580.72
|
38.78%
$989,212.15
|
-6.40%
-$212,804.15
|
|
| $3,561,176.00 |
13.72%
$429,746.57
|
39.61%
$1,010,378.00
|
-0.60%
-$21,165.85
|
E
Engineer's Estimate
$3,131,429.43
1
Awarded
$2,550,798.00
Over/Under Est:
-18.54%
-$580,631.43
$2,608,629.24
Over/Under Est:
-16.7%
-$522,800.19
Amt Left:
2.27%
$57,831.24
$3,107,995.18
Over/Under Est:
-0.75%
-$23,434.25
Amt Left:
21.84%
$557,197.18
Delta:
-19.14%
-$499,365.94
$3,327,206.00
Over/Under Est:
6.25%
$195,776.57
Amt Left:
30.44%
$776,408.00
Delta:
-7.05%
-$219,210.82
$3,540,010.15
Over/Under Est:
13.05%
$408,580.72
Amt Left:
38.78%
$989,212.15
Delta:
-6.40%
-$212,804.15
$3,561,176.00
Over/Under Est:
13.72%
$429,746.57
Amt Left:
39.61%
$1,010,378.00
Delta:
-0.60%
-$21,165.85
Bid Items & Bid Tabulations
30
Total
0 of 30