HOUSTON FM 2781 (2813-01-008)
Items: 77
County: HOUSTON
Length: N/A
Highway: FM 2781
District: LUFKIN
Control Number: 2813-01-008
DBE Goal: N/A
Project: STP 2019(095)
Guaranty: N/A
Time: 159 WORKING DAYS
Engineer's Estimate: $4,275,842.60
Date: 10/03/2018 (7 years ago)
Contract Number: N/A
Type: REHAB AND WIDEN EXISTING PAVMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (8)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$4,275,842.60 | |||
| $4,041,100.84 |
-5.49%
-$234,741.76
|
|||
| $4,325,022.17 |
1.15%
$49,179.57
|
7.03%
$283,921.33
|
||
| $4,332,433.32 |
1.32%
$56,590.72
|
7.21%
$291,332.48
|
-0.17%
-$7,411.15
|
|
| $4,539,928.07 |
6.18%
$264,085.47
|
12.34%
$498,827.23
|
-4.79%
-$207,494.75
|
|
| $4,570,326.71 |
6.89%
$294,484.11
|
13.1%
$529,225.87
|
-0.67%
-$30,398.64
|
|
| $4,903,550.22 |
14.68%
$627,707.62
|
21.34%
$862,449.38
|
-7.29%
-$333,223.51
|
|
| $5,637,299.38 |
31.84%
$1,361,456.78
|
39.5%
$1,596,198.54
|
-14.96%
-$733,749.16
|
|
| $5,870,362.02 |
37.29%
$1,594,519.42
|
45.27%
$1,829,261.18
|
-4.13%
-$233,062.64
|
E
Engineer's Estimate
$4,275,842.60
1
Awarded
$4,041,100.84
Over/Under Est:
-5.49%
-$234,741.76
$4,325,022.17
Over/Under Est:
1.15%
$49,179.57
Amt Left:
7.03%
$283,921.33
$4,332,433.32
Over/Under Est:
1.32%
$56,590.72
Amt Left:
7.21%
$291,332.48
Delta:
-0.17%
-$7,411.15
$4,539,928.07
Over/Under Est:
6.18%
$264,085.47
Amt Left:
12.34%
$498,827.23
Delta:
-4.79%
-$207,494.75
$4,570,326.71
Over/Under Est:
6.89%
$294,484.11
Amt Left:
13.1%
$529,225.87
Delta:
-0.67%
-$30,398.64
$4,903,550.22
Over/Under Est:
14.68%
$627,707.62
Amt Left:
21.34%
$862,449.38
Delta:
-7.29%
-$333,223.51
$5,637,299.38
Over/Under Est:
31.84%
$1,361,456.78
Amt Left:
39.5%
$1,596,198.54
Delta:
-14.96%
-$733,749.16
$5,870,362.02
Over/Under Est:
37.29%
$1,594,519.42
Amt Left:
45.27%
$1,829,261.18
Delta:
-4.13%
-$233,062.64