HOPKINS TI (0901-28-105)

Items: 41

County: HOPKINS
Length: N/A
Highway: TI
District: PARIS
Control Number: 0901-28-105
DBE Goal: 350.0%
Project: BR 2B23(130)
Guaranty: N/A
Time: 64 WORKING DAYS
Engineer's Estimate: $481,824.00
Date: 08/01/2024 (1 year ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
JESSE HERRERA
DUSTIN LYDAY
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$481,824.00
$562,558.51
Over/Under Est: 16.76% $80,734.51
Over/Under Est: 28.65% $138,055.41
Amt Left: 10.19% $57,320.90
Over/Under Est: 30.62% $147,539.00
Amt Left: 11.88% $66,804.49
Delta: -1.53% -$9,483.59
$694,428.75
Over/Under Est: 44.12% $212,604.75
Amt Left: 23.44% $131,870.24
Delta: -10.34% -$65,065.75
Over/Under Est: 81.8% $394,139.00
Amt Left: 55.71% $313,404.49
Delta: -26.14% -$181,534.25
Subcontractor Percentage Amount
PEACHTREE CONSTRUCTION, LTD. 9.05% $52,170.68
MORRIS COUNTY CONTRACTORS, L.L.C. 6.75% $38,911.84
HODGES AND SON CONSTRUCTION COMPANY, INC. 6.15% $35,453.01
DUSTROL, INC. 1.40% $8,070.60
WOLFE CONSTRUCTION GROUP, INCORPORATED 1.03% $5,937.66
DIAMOND ELITE BARRICADES, LLC 0.62% $3,574.12
TORO BRAVO CONSTRUCTION, LLC 0.00% $0.00
Total: 25.00% $144,117.91

Bid Items & Bid Tabulations

41 Total 0 of 41
HOPKINS  |  TI  |  PARIS  |  0901-28-105  |  08/01/2024  |  $481,824.00  |  BR 2B23(130)  |  BRIDGE REPL  |  64 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
THK CONSTRUCTION LLC
TALBERT COMPANIES LLC
EAST TEXAS BRIDGE, INC.
SKYLINE BRIDGE LLC
HODGES AND SON CONSTRUCTION COMPANY, INC.
PREPARING ROW
STA 3.500 $2,500.000 $2,500.000 $5,475.000 $6,000.000 $4,500.000 $7,500.000
REMOVING CONC (RIPRAP)
SY 285.000 $50.000 $15.000 $43.800 $25.000 $30.000 $15.000
EXCAVATION (ROADWAY)
CY 20.000 $20.000 $20.000 $24.310 $35.000 $250.000 $80.000
EXCAVATION (CHANNEL)
CY 160.000 $25.000 $20.000 $35.770 $35.000 $25.000 $60.000
EMBANKMENT (FINAL)(ORD COMP)(TY B)
CY 65.000 $30.000 $20.000 $37.070 $50.000 $150.000 $80.000
BROADCAST SEED (TEMP) (WARM)
SY 890.000 $0.400 $0.010 $1.100 $1.100 $1.250 $5.000
BROADCAST SEED (TEMP) (COOL)
SY 890.000 $0.400 $0.010 $1.100 $1.100 $1.250 $5.000
CELL FBR MLCH SEED(PERM)(RURAL)(CLAY)
SY 1,780.000 $1.000 $3.300 $3.290 $2.000 $2.500 $4.000
VEGETATIVE WATERING
MG 12.000 $20.000 $20.000 $80.760 $50.000 $1.000 $1.000
REWORK BS MTL (TY B) (8") (ORD COMP)
SY 584.000 $10.000 $40.000 $19.710 $35.000 $25.000 $35.000
CEM STABIL BKFL
CY 45.000 $250.000 $366.000 $279.660 $350.000 $350.000 $300.000
FLOWABLE BACKFILL
CY 10.000 $500.000 $300.000 $635.020 $400.000 $275.000 $300.000
DRILL SHAFT (24 IN)
LF 165.000 $200.000 $270.300 $209.370 $285.000 $650.000 $200.000
CL C CONC (ABUT)
CY 20.400 $1,250.000 $1,100.000 $1,459.930 $1,500.000 $1,250.000 $2,200.000
REINF CONC SLAB
SF 1,170.000 $30.000 $35.000 $26.280 $30.000 $40.000 $50.000
PRESTR CONC SLAB BEAM (5SB15)
LF 222.500 $290.000 $319.000 $234.860 $395.000 $385.000 $440.000
RIPRAP (CONC)(CL B)(RR8&RR9)
CY 40.000 $525.000 $1,050.000 $766.500 $875.000 $700.000 $800.000
RIPRAP (MOW STRIP)(4 IN)
CY 18.000 $525.000 $650.000 $766.500 $750.000 $750.000 $700.000
RAIL (TY T223)
LF 114.000 $200.000 $200.000 $195.270 $185.000 $150.000 $150.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 1.000 $20,000.000 $5,000.000 $19,710.000 $25,000.000 $15,000.000 $30,000.000
REMOV STR (SMALL FENCE)
LF 93.000 $8.000 $10.000 $10.950 $10.000 $15.000 $10.000
MOBILIZATION
LS 1.000 $43,802.000 $50,000.000 $87,000.000 $50,000.000 $65,000.000 $75,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000 $2,500.000 $968.830 $4,927.500 $4,000.000 $4,000.000 $16,000.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 70.000 $35.000 $45.000 $54.320 $50.000 $40.000 $1.000
ROCK FILTER DAMS (REMOVE)
LF 70.000 $10.000 $10.000 $12.490 $20.000 $10.000 $1.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 78.000 $25.000 $1.000 $26.940 $45.000 $10.000 $1.000
CONSTRUCTION EXITS (REMOVE)
SY 78.000 $12.000 $1.000 $9.960 $25.000 $1.000 $1.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 575.000 $4.000 $4.400 $7.670 $5.250 $3.750 $1.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 575.000 $1.000 $1.100 $2.740 $1.250 $1.500 $1.000
CONSTRUCTING DETOURS
SY 521.000 $100.000 $141.200 $136.880 $135.000 $130.000 $400.000
MTL W-BEAM GD FEN (STEEL POST)
LF 422.500 $35.000 $33.000 $33.230 $33.000 $34.000 $26.000
MTL BEAM GD FEN TRANS (TL2)
EA 4.000 $1,400.000 $1,402.500 $1,527.530 $1,500.000 $1,750.000 $1,500.000
MTL W - BEAM GD FEN (LOW FILL CULVERT)
LF 40.000 $100.000 $110.000 $152.210 $115.000 $120.000 $60.000
REMOVE METAL BEAM GUARD FENCE
LF 237.500 $5.000 $2.500 $4.110 $3.000 $5.000 $2.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $3,100.000 $3,410.000 $3,531.380 $3,500.000 $3,500.000 $3,500.000
GUARDRAIL END TREATMENT (MOVE & RESET)
EA 4.000 $1,500.000 $1,100.000 $2,031.230 $1,200.000 $1,500.000 $3,000.000
RELOCATE SM RD SN SUP&AM TY TWT
EA 1.000 $600.000 $1,000.000 $732.560 $1,000.000 $500.000 $600.000
REMOVE SM RD SN SUP&AM
EA 4.000 $80.000 $250.000 $136.880 $125.000 $200.000 $50.000
REMOVE DELIN & OBJECT MARKER ASSMS
EA 9.000 $25.000 $10.000 $49.280 $20.000 $25.000 $50.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 8.000 $50.000 $27.500 $27.380 $35.000 $50.000 $50.000
D-GR HMA TY-C SAC-A PG64-22(EXEMPT)
TON 176.000 $200.000 $311.190 $355.880 $300.000 $375.000 $300.000
Totals: $481,824.000 $562,558.510 $619,879.422 $629,363.000 $694,428.750 $875,963.000