County: HOPKINS Highway: IH 30 Date: 06/05/2019 (5 years ago) Engineer's Estimate: $3,988,122 Control Number: 0009-09-106
Project: STP 1902(034)HES District: PARIS Time: 182 WORKING DAYS Type: SAFETY IMPROVEMENT PROJECTS

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $3,988,122.00
DBI SERVICES, LLC   $3,952,539.25 1
-0.89% | -$35,582.75
STATELINE CONSTRUCTION, LLC   $4,023,088.00 2
0.88% | $34,966.00
1.78% | $70,548.75
3LW CIVIL LLC   $4,055,676.75 3
1.69% | $67,554.75
2.61% | $103,137.50
0.81% | $32,588.75
EAST TEXAS BRIDGE, INC.   $4,180,162.50 4
4.82% | $192,040.50
5.76% | $227,623.25
3.07% | $124,485.75
VANN/ELLI, INC.   $4,676,763.75 5
17.27% | $688,641.75
18.32% | $724,224.50
11.88% | $496,601.25
SJ&J CONSTRUCTION, LLC   $4,730,023.00 6
18.6% | $741,901.00
19.67% | $777,483.75
1.14% | $53,259.25

Bid Items

Items: 27, 0 filtered
HOPKINS IH 30  |  PARIS  |  0009-09-106  |  06/05/2019  |  $3,988,122  |  STP 1902(034)HES  |  SAFETY IMPRV PROJECTS  |  182 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate DBI SERVICES, LLC STATELINE CONSTRUCTION, LLC 3LW CIVIL LLC EAST TEXAS BRIDGE, INC. VANN/ELLI, INC. SJ&J CONSTRUCTION, LLC
104 6054 REMOVING CONCRETE(MOW STRIP) LF 53.000 $10.000 $40.000 $100.000 $13.000 $20.000 $30.000 $45.000
132 6019 EMBANKMENT (VEHICLE)(ORD COMP)(TY B) CY 42.000 $20.000 $50.000 $50.000 $41.000 $40.000 $50.000 $19.000
162 6002 BLOCK SODDING SY 200.000 $5.250 $20.000 $9.000 $8.000 $10.000 $15.000 $6.000
168 6001 VEGETATIVE WATERING MG 2.000 $10.000 $200.000 $100.000 $50.000 $100.000 $2,000.000 $20.000
169 6003 SOIL RETENTION BLANKETS (CL 1) (TY C) SY 17,125.000 $1.500 $1.000 $1.100 $0.750 $1.100 $1.750 $3.000
432 6045 RIPRAP (MOW STRIP)(4 IN) CY 3,434.000 $400.000 $350.000 $422.000 $435.000 $420.000 $450.000 $550.000
500 6001 MOBILIZATION LS 1.000 $266,145.000 $440,000.000 $380,000.000 $350,000.000 $300,000.000 $450,000.000 $120,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 12.000 $5,500.000 $4,000.000 $11,295.000 $8,000.000 $10,000.000 $5,000.000 $5,000.000
506 6040 BIODEG EROSN CONT LOGS (INSTL) (8") LF 800.000 $3.000 $8.000 $4.000 $7.000 $10.000 $7.000 $4.000
506 6043 BIODEG EROSN CONT LOGS (REMOVE) LF 800.000 $0.850 $2.000 $2.000 $2.000 $3.000 $1.500 $1.000
540 6002 MTL W-BEAM GD FEN (STEEL POST) LF 41,175.000 $22.500 $19.750 $19.500 $20.000 $21.500 $25.560 $28.000
540 6006 MTL BEAM GD FEN TRANS (THRIE-BEAM) EA 130.000 $1,750.000 $2,250.000 $1,760.000 $1,700.000 $1,750.000 $2,400.000 $1,850.000
540 6008 MTL BEAM GD FEN TRANS (T101) EA 48.000 $1,100.000 $1,700.000 $1,110.000 $1,000.000 $1,200.000 $1,100.000 $1,750.000
540 6016 DOWNSTREAM ANCHOR TERMINAL SECTION EA 53.000 $1,200.000 $1,100.000 $920.000 $1,216.000 $1,000.000 $1,020.000 $1,100.000
542 6001 REMOVE METAL BEAM GUARD FENCE LF 24,750.000 $3.000 $1.000 $2.000 $1.000 $2.250 $3.000 $3.500
542 6002 REMOVE TERMINAL ANCHOR SECTION EA 174.000 $250.000 $100.000 $200.000 $150.000 $220.000 $200.000 $300.000
542 6004 RM MTL BM GD FENCE TRANS (THRIE-BEAM) EA 111.000 $400.000 $300.000 $200.000 $250.000 $220.000 $150.000 $300.000
542 6005 RM MTL BM GD FEN TRANS (T101) EA 17.000 $200.000 $300.000 $150.000 $230.000 $175.000 $100.000 $300.000
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 242.000 $2,300.000 $2,750.000 $2,400.000 $2,600.000 $2,600.000 $2,640.000 $2,635.000
544 6003 GUARDRAIL END TREATMENT (REMOVE) EA 22.000 $400.000 $150.000 $200.000 $300.000 $220.000 $200.000 $600.000
545 6005 CRASH CUSH ATTEN (REMOVE) EA 36.000 $800.000 $150.000 $1,100.000 $1,100.000 $1,200.000 $1,500.000 $1,000.000
545 6007 CRASH CUSH ATTEN (INSTL)(L)(N)(TL3) EA 3.000 $24,000.000 $30,900.000 $23,950.000 $30,000.000 $27,500.000 $30,000.000 $24,500.000
658 6061 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2 EA 268.000 $14.000 $18.000 $17.000 $12.000 $20.000 $16.000 $30.000
658 6062 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) EA 388.000 $40.000 $22.000 $19.000 $12.000 $20.000 $16.000 $30.000
658 6064 INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2 EA 196.000 $10.000 $18.000 $17.000 $12.000 $20.000 $16.000 $25.000
6001 6002 PORTABLE CHANGEABLE MESSAGE SIGN EA 6.000 $9,000.000 $4,000.000 $6,500.000 $7,500.000 $20,000.000 $15,000.000 $12,000.000
6185 6002 TMA (STATIONARY) DAY 211.000 $350.000 $450.000 $150.000 $150.000 $200.000 $400.000 $150.000
Totals: $3,988,122.00 $3,952,539.25 $4,023,088.00 $4,055,676.75 $4,180,162.50 $4,676,763.75 $4,730,023.00