HOCKLEY US 385 (0227-06-026)

Items: 105

County: HOCKLEY
Length: N/A
Highway: US 385
District: LUBBOCK
Control Number: 0227-06-026
DBE Goal: N/A
Project: STP 1802(433)
Guaranty: N/A
Time: 0 X
Engineer's Estimate: $24,906,985.90
Date: 06/05/2018 (8 years ago)
Contract Number: N/A
Type: REHABILITATION
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (6)
E
Engineer's Estimate
$24,906,985.90
$27,611,673.86
Over/Under Est: 10.86% $2,704,687.96
Over/Under Est: 13.67% $3,405,949.38
Amt Left: 2.54% $701,261.42
$28,659,818.86
Over/Under Est: 15.07% $3,752,832.96
Amt Left: 3.8% $1,048,145.00
Delta: -1.23% -$346,883.58
Over/Under Est: 16% $3,985,389.04
Amt Left: 4.64% $1,280,701.08
Delta: -0.81% -$232,556.08
Over/Under Est: 22.67% $5,645,835.53
Amt Left: 10.65% $2,941,147.57
Delta: -5.75% -$1,660,446.49
$34,733,291.10
Over/Under Est: 39.45% $9,826,305.20
Amt Left: 25.79% $7,121,617.24
Delta: -13.68% -$4,180,469.67

Bid Items & Bid Tabulations

105 Total 0 of 105
HOCKLEY  |  US 385  |  LUBBOCK  |  0227-06-026  |  06/05/2018  |  $24,906,985.90  |  STP 1802(433)  |  REHAB  |  0 X
Item Code
Description
Unit
Quantity
Engineer's Estimate
A. L. HELMCAMP, INC.
ALLEN BUTLER CONSTRUCTION, INC.
DUININCK, INC.
JOHNSON BROS. CORPORATION, A SOUTHLAND COMPANY
KIEWIT INFRASTRUCTURE SOUTH CO.
RK HALL, LLC
REMOVING CONC (RIPRAP)
SY 85.000 $10.000 $33.000 $18.460 $13.500 $6.000 $82.550 $55.000
REMOVING CONC (DRIVEWAYS)
SY 580.000 $6.500 $30.000 $14.770 $17.500 $7.000 $55.000 $17.500
EXCAVATION (ROADWAY)
CY 801.910 $30.000 $19.000 $9.410 $19.000 $7.000 $40.190 $14.350
EXCAVATION (CHANNEL)
CY 3,003.000 $30.000 $7.000 $19.270 $26.500 $10.000 $20.400 $15.200
SUBGRADE WIDENING (DENS CONT)
SY 103,662.930 $6.500 $2.200 $2.820 $4.450 $11.000 $2.000 $14.800
EMBANKMENT (FINAL)(ORD COMP)(TY C)
CY 1,040.000 $5.000 $15.000 $13.770 $50.500 $8.000 $274.460 $21.000
BACKFILL (TY B)
STA 1,360.090 $250.000 $130.000 $114.140 $210.000 $100.000 $99.320 $137.500
BLADING
STA 1,360.090 $100.000 $130.000 $101.820 $115.000 $80.000 $30.000 $220.000
REWORK BS MTL (TY B) (6") (DENS CONT)
SY 4,350.000 $8.000 $7.000 $5.890 $7.200 $3.750 $8.210 $6.500
PRIME COAT (MC-30)
GAL 21,316.000 $5.000 $4.000 $3.890 $3.800 $2.750 $5.000 $4.550
EMULS ASPH (EROSN CONT)(CSS-1H)
GAL 83,052.090 $3.000 $3.000 $3.330 $3.100 $2.750 $3.340 $4.150
FOG SEAL (CSS-1H)
GAL 72,194.500 $3.000 $2.500 $3.440 $3.250 $3.250 $3.130 $4.350
D-GR HMA TY-B PG70-28
TON 26,106.540 $90.000 $107.000 $86.310 $94.000 $80.000 $115.000 $120.000
D-GR HMA TY-C SAC-B PG70-28
TON 46,264.430 $80.000 $107.000 $98.060 $94.000 $94.000 $115.000 $126.000
STONE-MTRX-ASPH SMA-D SAC-A PG70-28
TON 73,665.460 $110.000 $117.000 $135.190 $130.000 $135.000 $120.000 $143.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
SY 32,000.000 $25.000 $34.000 $33.640 $46.000 $47.000 $48.940 $48.000
CEM STABIL BKFL
CY 184.940 $200.000 $240.000 $92.730 $205.000 $140.000 $234.140 $227.220
RIPRAP (CONC)(4 IN)
CY 23.890 $400.000 $600.000 $462.410 $520.000 $400.000 $652.880 $568.050
CMP (GAL STL 18 IN)
LF 21.000 $80.000 $60.000 $88.640 $52.000 $50.000 $203.650 $56.800
CMP (GAL STL 24 IN)
LF 531.000 $90.000 $72.000 $68.680 $62.000 $75.000 $110.660 $68.170
CMP (GAL STL 30 IN)
LF 120.000 $110.000 $85.000 $124.720 $72.500 $85.000 $136.700 $79.530
CMP (GAL STL 36 IN)
LF 117.000 $120.000 $96.000 $106.380 $83.000 $100.000 $138.450 $90.890
CMP AR (GAL STL DES 4)
LF 48.000 $110.000 $110.000 $141.420 $93.500 $120.000 $142.350 $102.250
RC PIPE (CL III)(24 IN)
LF 80.000 $100.000 $150.000 $121.020 $130.000 $80.000 $155.830 $142.010
RC PIPE (CL III)(30 IN)
LF 48.000 $110.000 $205.000 $177.190 $175.000 $110.000 $280.460 $193.140
SET (TY II) (18 IN) (CMP) (4: 1) (C)
EA 1.000 $800.000 $1,200.000 $914.890 $1,000.000 $1,500.000 $1,772.220 $1,136.100
SET (TY II) (18 IN) (CMP) (6: 1) (C)
EA 1.000 $900.000 $1,300.000 $1,061.190 $1,100.000 $2,000.000 $1,876.020 $1,249.710
SET (TY II) (24 IN) (CMP) (4: 1) (C)
EA 2.000 $1,200.000 $1,450.000 $953.090 $1,200.000 $2,000.000 $2,405.860 $1,363.320
SET (TY II) (24 IN) (CMP) (6: 1) (C)
EA 38.000 $1,200.000 $1,500.000 $1,779.370 $1,300.000 $2,200.000 $3,038.030 $1,420.120
SET (TY II) (24 IN) (RCP) (6: 1) (C)
EA 7.000 $1,300.000 $1,560.000 $1,771.730 $1,300.000 $2,500.000 $2,531.440 $1,476.930
SET (TY II) (30 IN) (CMP) (4: 1) (C)
EA 2.000 $1,350.000 $2,400.000 $1,024.150 $2,100.000 $3,200.000 $2,867.080 $2,272.200
SET (TY II) (30 IN) (CMP) (6: 1) (C)
EA 12.000 $1,800.000 $2,600.000 $2,179.880 $2,300.000 $3,200.000 $3,390.600 $2,499.420
SET (TY II) (30 IN) (RCP) (4: 1) (C)
EA 6.000 $1,800.000 $3,000.000 $2,051.380 $2,600.000 $3,000.000 $2,697.860 $2,840.250
SET (TY II) (36 IN) (CMP) (4: 1) (C)
EA 6.000 $3,000.000 $3,000.000 $1,528.140 $2,600.000 $3,000.000 $3,447.320 $2,840.250
SET (TY II) (36 IN) (CMP) (6: 1) (C)
EA 3.000 $3,300.000 $3,800.000 $2,564.770 $3,300.000 $3,500.000 $5,622.590 $3,635.520
SET (TY II) (DES 4) (CMP) (6: 1) (P)
EA 4.000 $2,600.000 $4,200.000 $2,143.820 $3,600.000 $3,500.000 $3,208.440 $3,976.350
CLEAN EXIST CULVERTS
EA 26.000 $1,800.000 $2,100.000 $1,692.960 $2,600.000 $2,000.000 $2,593.980 $1,605.000
MOBILIZATION
LS 1.000 $1,757,000.000 $2,000,000.000 $1,527,641.790 $1,285,000.000 $1,500,000.000 $2,459,602.000 $2,165,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 17.000 $8,000.000 $14,000.000 $9,635.110 $22,000.000 $12,000.000 $30,000.000 $10,000.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 624.000 $30.000 $20.000 $20.750 $38.500 $25.000 $40.210 $39.890
CONSTRUCTION EXITS (REMOVE)
SY 624.000 $10.000 $2.000 $8.160 $11.500 $4.000 $11.870 $11.770
TEMP SEDMT CONT FENCE (INSTALL)
LF 18,850.000 $3.000 $3.000 $2.510 $3.100 $3.500 $3.200 $3.180
TEMP SEDMT CONT FENCE (REMOVE)
LF 18,850.000 $1.000 $1.000 $1.050 $1.050 $1.200 $1.080 $1.070
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 12,880.000 $3.000 $4.000 $3.190 $5.000 $5.000 $5.180 $5.140
BIODEG EROSN CONT LOGS (REMOVE)
LF 12,880.000 $1.000 $1.000 $0.940 $1.150 $1.250 $1.200 $1.190
INTERSECTIONS (ACP)
SY 4,333.000 $35.000 $33.000 $31.880 $59.500 $30.000 $45.610 $85.000
INTERSECTIONS (SURF TREAT)
SY 2,828.000 $20.000 $20.000 $18.230 $36.000 $12.000 $25.210 $85.000
DRIVEWAYS (CONC)
SY 1,139.000 $80.000 $110.000 $79.130 $93.500 $80.000 $76.420 $102.250
DRIVEWAYS (SURF TREAT)
SY 777.000 $20.000 $24.000 $44.460 $45.000 $10.000 $22.210 $20.000
TURNOUTS (ACP)
SY 1,156.900 $35.000 $35.000 $63.650 $145.000 $50.000 $39.520 $85.000
RUMBLE STRIPS (SHOULDER) ASPHALT
LF 271,270.000 $0.140 $0.130 $0.100 $0.090 $0.100 $0.090 $0.100
RUMBLE STRIPS (CENTERLINE) ASPHALT
LF 135,610.000 $0.200 $0.160 $0.120 $0.160 $0.100 $0.090 $0.100
REMOVE METAL BEAM GUARD FENCE
LF 175.000 $5.000 $10.000 $13.630 $3.100 $7.000 $2.830 $10.700
GUARDRAIL END TREATMENT (REMOVE)
EA 4.000 $500.000 $550.000 $596.150 $310.000 $350.000 $348.150 $1,070.000
MAILBOX INSTALL-S (TWG-POST) TY 2
EA 56.000 $300.000 $230.000 $298.360 $220.000 $275.000 $226.520 $187.250
MAILBOX INSTALL-D (TWG-POST) TY 2
EA 12.000 $320.000 $250.000 $319.330 $240.000 $275.000 $248.100 $240.750
MAILBOX INSTALL-M (TWG-POST) TY 2
EA 3.000 $360.000 $450.000 $492.160 $410.000 $400.000 $426.080 $374.500
ELEC CONDR (NO.12) INSULATED
LF 250.000 $3.500 $4.000 $3.140 $3.100 $3.750 $3.940 $3.560
ELEC CONDR (NO.6) BARE
LF 160.000 $1.500 $4.300 $3.660 $3.650 $4.250 $4.210 $4.150
ALUMINUM SIGNS (TY A)
SF 54.630 $20.000 $40.000 $29.240 $36.500 $20.000 $21.250 $26.750
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 116.000 $600.000 $500.000 $476.320 $470.000 $525.000 $490.800 $856.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P-BM)
EA 49.000 $740.000 $570.000 $549.600 $545.000 $600.000 $566.310 $936.250
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 34.000 $610.000 $570.000 $539.130 $535.000 $600.000 $555.520 $936.250
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 1.000 $800.000 $640.000 $607.180 $600.000 $675.000 $625.630 $1,016.500
IN SM RD SN SUP&AM TYS80(1)SA(P-BM)
EA 1.000 $900.000 $1,000.000 $947.400 $940.000 $1,000.000 $976.210 $1,337.500
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 3.000 $700.000 $730.000 $690.930 $685.000 $775.000 $711.930 $1,070.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 12.000 $850.000 $850.000 $806.080 $800.000 $900.000 $830.580 $1,230.500
IN SM RD SN SUP&AM TYS80(1)SA(U-BM)
EA 17.000 $950.000 $720.000 $680.460 $675.000 $700.000 $701.140 $1,284.000
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 1.000 $300.000 $420.000 $392.570 $390.000 $450.000 $404.510 $802.500
REMOVE SM RD SN SUP&AM
EA 164.000 $100.000 $80.000 $73.280 $72.500 $80.000 $75.510 $123.050
INSTL OM ASSM (OM-2Z)(FLX)GND(BI)
EA 52.000 $60.000 $90.000 $83.750 $83.000 $90.000 $86.290 $145.520
WK ZN PAV MRK NON-REMOV (W)4"(BRK)
LF 24,216.000 $0.200 $0.140 $0.140 $0.080 $0.090 $0.090 $0.140
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 813,138.000 $0.200 $0.140 $0.140 $0.080 $0.090 $0.090 $0.140
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 991,136.000 $0.200 $0.140 $0.140 $0.080 $0.090 $0.090 $0.140
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 18,977.000 $0.500 $0.600 $1.000 $1.050 $1.000 $1.120 $1.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 10,184.000 $0.500 $0.600 $0.990 $1.050 $1.000 $1.120 $1.000
REFL PAV MRK TY I (W)4"(DOT)(100MIL)
LF 3,733.000 $1.000 $0.390 $0.370 $0.360 $0.500 $0.380 $0.370
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 269,190.000 $0.250 $0.390 $0.370 $0.360 $0.500 $0.380 $0.370
RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)
LF 18,836.000 $0.600 $0.580 $0.550 $0.570 $0.650 $0.590 $0.570
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 12,783.000 $0.500 $0.390 $0.370 $0.360 $0.450 $0.380 $0.370
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 200,234.000 $0.250 $0.390 $0.370 $0.360 $0.450 $0.380 $0.370
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 314.000 $15.000 $18.700 $17.800 $18.500 $20.000 $19.040 $18.190
PREFAB PAV MRK TY C (W) (ARROW)
EA 20.000 $200.000 $825.000 $785.140 $190.000 $200.000 $196.590 $802.500
PREFAB PAV MRK TY C (W) (RR XING)
EA 1.000 $300.000 $1,171.500 $1,114.910 $545.000 $600.000 $566.680 $1,139.550
REFL PAV MRKR TY I-C
EA 1,009.000 $3.000 $3.300 $3.140 $2.650 $3.000 $2.750 $3.210
REFL PAV MRKR TY II-A-A
EA 2,936.000 $3.000 $3.300 $3.140 $2.650 $3.000 $2.750 $3.210
ELIM EXT PAV MRK & MRKS (4")
LF 744,307.000 $0.600 $0.400 $0.540 $0.450 $0.350 $0.320 $0.750
ELIM EXT PAV MRK & MRKS (24")
LF 314.000 $3.000 $4.000 $3.250 $2.050 $16.000 $14.940 $24.000
ELIM EXT PAV MRK & MRKS (RR XING)
EA 1.000 $120.000 $750.000 $816.640 $310.000 $280.000 $253.490 $5,000.000
PAV SURF PREP FOR MRK (24")
LF 314.000 $1.000 $3.300 $3.140 $6.150 $7.000 $6.420 $3.210
PAV SURF PREP FOR MRK (ARROW)
EA 20.000 $10.000 $27.500 $26.170 $38.000 $45.000 $39.640 $26.750
PAV SURF PREP FOR MRK (RR XING)
EA 1.000 $30.000 $82.500 $78.520 $115.000 $130.000 $119.730 $80.250
VEH SIG SEC (12")LED(YEL ARW)
EA 4.000 $300.000 $340.000 $287.890 $285.000 $350.000 $776.650 $326.340
VEH SIG SEC (12")LED(RED ARW)
EA 4.000 $300.000 $340.000 $287.890 $285.000 $350.000 $776.650 $326.340
INSTALL RDSD FLASH BEACON ASSEMBLY
EA 4.000 $6,000.000 $7,300.000 $6,281.160 $7,000.000 $7,500.000 $8,936.860 $7,120.110
FULL - WIDTH MOWING
CYC 4.000 $3,000.000 $4,200.000 $3,583.050 $15,000.000 $1,800.000 $1,561.370 $30,000.000
LITTER REMOVAL
CYC 4.000 $2,000.000 $3,700.000 $2,536.130 $5,200.000 $1,800.000 $1,071.420 $15,000.000
TREE REMOVAL (24" - 30" DIA)
EA 11.000 $1,800.000 $1,200.000 $1,179.730 $1,300.000 $1,500.000 $1,160.660 $1,131.140
DITCH CLEANING AND RESHAPING (FOOT)
LF 124,300.000 $5.000 $4.000 $9.340 $9.650 $5.000 $8.950 $5.500
NO. OF WORKING DAYS
$/D 4,000.000 $259.000 $240.000 $262.000 $259.000 $350.000 $226.000 $325.000
REINFORCED FAB FOR ASPH PVMNT OVERLAYS
SY 507,396.890 $4.000 $5.500 $4.950 $4.750 $6.000 $5.360 $5.350
ASPH FOR REINF FAB (AC-20-5TR)
GAL 101,479.370 $2.500 $3.600 $5.070 $4.050 $2.500 $4.310 $5.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $12,000.000 $6,500.000 $9,421.730 $10,500.000 $13,000.000 $22,853.970 $25,000.000
TMA (STATIONARY)
EA 4.000 $8,000.000 $10,000.000 $36,640.080 $26,000.000 $13,000.000 $18,972.220 $35,000.000
TMA (MOBILE OPERATION)
DAY 30.000 $250.000 $400.000 $1,095.790 $780.000 $75.000 $435.770 $825.000
Totals: $24,906,985.900 $27,611,673.873 $28,312,935.351 $28,659,818.904 $28,892,374.958 $30,552,821.473 $34,733,291.141