HOCKLEY SH 114 (0130-04-035)

Items: 55

County: HOCKLEY
Length: N/A
Highway: SH 114
District: LUBBOCK
Control Number: 0130-04-035
DBE Goal: N/A
Project: STP 2022(894)HES
Guaranty: N/A
Time: 165 WORKING DAYS
Engineer's Estimate: $1,865,723.00
Date: 08/03/2022 (3 years ago)
Contract Number: N/A
Type: HAZARD ELIMINATION & SAFETY
Mail/Deliver Bids To: N/A
ALEJANDRO MENDOZA
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$1,865,723.00
$1,890,330.00
Over/Under Est: 1.32% $24,607.00
$2,738,082.88
Over/Under Est: 46.76% $872,359.88
Amt Left: 44.85% $847,752.88
$2,987,215.00
Over/Under Est: 60.11% $1,121,492.00
Amt Left: 58.03% $1,096,885.00
Delta: -9.10% -$249,132.12
Subcontractor Percentage Amount
VALLEY CONSTRUCTION, LLC 26.74% $485,985.95
ROCK HILL INDUSTRIAL LLC 1.85% $33,622.81
FC TRAFFIC CONTROL, INC. 1.03% $18,719.73
BARRICADES UNLIMITED 0.31% $5,634.09
Total: 29.93% $543,962.58

Bid Items & Bid Tabulations

55 Total 0 of 55
HOCKLEY  |  SH 114  |  LUBBOCK  |  0130-04-035  |  08/03/2022  |  $1,865,723.00  |  STP 2022(894)HES  |  HAZARD ELIM & SAFETY  |  165 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
DIGG COMMERCIAL, LLC
GILVIN-TERRILL, LTD.
EARTH BUILDERS, L.P.
PREPARING ROW(TREE)(5" TO 12" DIA)
EA 5.000 $350.000 $1,369.000 $2,000.000 $2,000.000
REMOVING CONC (RIPRAP)
SY 26.000 $50.000 $450.000 $100.000 $20.000
EXCAVATION (SPECIAL)
CY 50.000 $50.000 $87.000 $50.000 $100.000
CEM STABIL BKFL
CY 135.000 $250.000 $550.000 $1,400.000 $400.000
TRENCH EXCAVATION PROTECTION
LF 180.000 $10.000 $1.000 $20.000 $50.000
TEMPORARY SPL SHORING (COFFERDAM)
SF 260.000 $100.000 $1.000 $90.000 $20.000
CONC STR REPAIR (STANDARD)
SF 150.000 $200.000 $1.000 $250.000 $200.000
RIPRAP (CONC) (CL A )
CY 17.600 $1,000.000 $1,800.000 $1,500.000 $1,000.000
CMP (GAL STL 24 IN)
LF 46.000 $300.000 $151.000 $400.000 $500.000
CMP AR (GAL STL DES 3)
LF 14.000 $300.000 $200.000 $400.000 $500.000
CMP AR (GAL STL DES 4)
LF 153.500 $300.000 $162.000 $600.000 $500.000
CMP AR (GAL STL DES 5)
LF 19.000 $300.000 $250.000 $500.000 $600.000
CMP AR (GAL STL DES 6)
LF 16.000 $350.000 $300.000 $550.000 $800.000
CMP AR (GAL STL DES 7)
LF 6.000 $400.000 $400.000 $600.000 $1,200.000
CONC BOX CULV (6 FT X 5 FT)
LF 12.000 $850.000 $1,649.000 $6,000.000 $5,000.000
CONC BOX CULV (8 FT X 4 FT)
LF 3.000 $1,000.000 $3,460.000 $7,000.000 $7,500.000
RC PIPE (CL III)(24 IN)
LF 144.000 $300.000 $146.000 $450.020 $400.000
RC PIPE (CL III)(30 IN)
LF 76.000 $300.000 $220.000 $500.000 $450.000
RC PIPE (CL III)(36 IN)
LF 6.000 $340.000 $380.000 $500.000 $500.000
RC PIPE (ARCH)(CL III)(DES 3)
LF 12.000 $310.000 $400.000 $550.000 $1,200.000
SET (PIPE RUNNER ASSEMBLY)
EA 37.000 $8,500.000 $4,500.000 $9,250.000 $15,000.000
SET (TY I)(S= 6 FT)(HW= 5 FT)(3:1) (C)
EA 6.000 $8,000.000 $15,000.000 $20,000.000 $25,000.000
SET (TY I)(S= 8 FT)(HW= 4 FT)(4:1) (C)
EA 1.000 $11,500.000 $22,000.000 $20,000.000 $30,000.000
SET (TY II) (24 IN) (CMP) (6: 1) (P)
EA 6.000 $3,500.000 $5,200.000 $5,000.000 $5,000.000
SET (TY II) (24 IN) (RCP) (6: 1) (C)
EA 20.000 $3,000.000 $5,500.000 $6,000.000 $6,000.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 2.000 $3,000.000 $5,900.000 $6,000.000 $6,000.000
SET (TY II) (30 IN) (RCP) (4: 1) (C)
EA 8.000 $3,000.000 $6,500.000 $6,300.000 $7,000.000
SET (TY II) (30 IN) (RCP) (6: 1) (C)
EA 2.000 $3,000.000 $6,880.000 $7,000.000 $7,000.000
SET (TY II) (30 IN) (RCP) (6: 1) (P)
EA 2.000 $3,000.000 $7,000.000 $7,000.000 $7,000.000
SET (TY II) (36 IN) (RCP) (3: 1) (C)
EA 2.000 $4,000.000 $7,350.000 $7,500.000 $8,000.000
SET (TY II) (DES 3) (CMP) (6: 1) (C)
EA 4.000 $3,000.000 $6,500.000 $5,400.000 $9,000.000
SET (TY II) (DES 3) (RCP) (6: 1) (P)
EA 2.000 $6,400.000 $7,000.000 $5,400.000 $9,000.000
SET (TY II) (DES 4) (CMP) (4: 1) (C)
EA 1.000 $5,300.000 $8,000.000 $5,600.000 $10,000.000
SET (TY II) (DES 4) (CMP) (6: 1) (C)
EA 30.000 $6,000.000 $8,680.000 $6,000.000 $10,000.000
SET (TY II) (DES 4) (CMP) (6: 1) (P)
EA 3.000 $5,400.000 $9,000.000 $5,600.000 $10,000.000
SET (TY II) (DES 5) (CMP) (4: 1) (C)
EA 4.000 $6,600.000 $10,000.000 $6,000.000 $10,000.000
SET (TY II) (DES 6) (CMP) (6: 1) (P)
EA 4.000 $7,600.000 $11,000.000 $7,000.000 $12,000.000
SET (TY II) (DES 7) (CMP) (6: 1) (P)
EA 2.000 $8,000.000 $12,000.000 $8,800.000 $15,000.000
CLEAN EXIST CULVERTS
EA 71.000 $2,500.000 $2,500.000 $3,000.000 $3,500.000
REMOV STR (BOX CULVERT)
LF 11.400 $320.000 $500.000 $1,000.000 $200.000
REMOV STR (PIPE)
EA 1.000 $500.000 $4,000.000 $3,500.000 $2,500.000
MOBILIZATION
LS 1.000 $170,000.000 $200,000.000 $270,000.000 $300,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 5.000 $5,000.000 $4,000.000 $16,940.000 $10,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $5,000.000 $4,000.000 $16,940.000 $10,000.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 2,150.000 $10.000 $5.000 $6.000 $6.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,075.000 $1.000 $1.000 $2.500 $1.000
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 4,190.000 $10.000 $6.000 $12.000 $10.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 2,095.000 $1.000 $1.000 $2.500 $1.000
DRIVEWAYS (ACP)
SY 8.000 $75.000 $2,000.000 $400.000 $500.000
REMOVE DELIN & OBJECT MARKER ASSMS
EA 157.000 $25.000 $50.000 $15.000 $10.000
INSTL OM ASSM (OM-2Z)(WFLX)GND(BI)
EA 157.000 $150.000 $100.000 $90.000 $25.000
LITTER REMOVAL
CYC 2.000 $2,500.000 $5,000.000 $2,500.000 $2,500.000
DITCH CLEANING AND RESHAPING (FOOT)
LF 9,940.000 $18.000 $1.000 $10.000 $20.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 660.000 $75.000 $65.000 $95.000 $50.000
TMA (STATIONARY)
DAY 330.000 $150.000 $295.000 $350.000 $150.000
Totals: $1,865,723.000 $1,890,330.000 $2,738,082.880 $2,987,215.000