Show Job Controls
Bid Cobra

HILL FM0308 (6399-56-001)

Items: 14

County: HILL
Length: N/A
Highway: FM0308
District: WACO
Control Number: 6399-56-001
DBE Goal: N/A
Project: RMC - 639956001
Guaranty: N/A
Time: 365 CALENDAR DAYS
Engineer's Estimate: $836,030.16
Date: 05/04/2022 (4 years ago)
Contract Number: N/A
Type: BASE FAILURE PAVEMENT REPAIR
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Documents:
Bidders (4)
E
Engineer's Estimate
$836,030.16
$889,845.10
Over/Under Est: 6.44% $53,814.94
Over/Under Est: 9.75% $81,481.44
Amt Left: 3.11% $27,666.50
Over/Under Est: 26.88% $224,718.73
Amt Left: 19.21% $170,903.79
Delta: -15.61% -$143,237.29
Over/Under Est: 59.6% $498,300.29
Amt Left: 49.95% $444,485.35
Delta: -25.79% -$273,581.56

Bid Items & Bid Tabulations

14 Total 0 of 14
HILL  |  FM0308  |  WACO  |  6399-56-001  |  05/04/2022  |  $836,030.16  |  RMC - 639956001  |  BASE FAILURE PAVMT REPAIR  |  365 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
KNIFE RIVER CORPORATION - SOUTH
BIG CREEK CONSTRUCTION, LTD.
TEXAS MATERIALS GROUP, INC.
PEACHTREE CONSTRUCTION, LTD.
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
SY 14,346.000 $50.000 $59.750 $60.000 $72.400 $88.000
MOBILIZATION (CALLOUT)
EA 3.000 $20,642.720 $225.000 $250.000 $0.010 $5,000.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 840.000 $1.000 $1.000 $1.500 $1.000 $2.850
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 840.000 $1.000 $1.000 $1.500 $1.000 $2.850
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 100.000 $7.000 $11.000 $15.000 $10.000 $11.000
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 2,100.000 $1.000 $0.900 $0.850 $0.780 $2.100
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 8,400.000 $1.000 $0.800 $0.800 $0.700 $1.400
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 2,102.000 $1.000 $0.800 $0.800 $0.730 $2.100
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 8,400.000 $1.000 $0.800 $0.800 $0.710 $1.400
REFL PAV MRKR TY I-C
EA 200.000 $5.000 $4.750 $5.000 $4.250 $7.050
REFL PAV MRKR TY II-A-A
EA 105.000 $4.000 $11.000 $15.000 $10.000 $7.050
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 100.000 $80.000 $5.000 $100.000 $0.010 $65.000
TMA (STATIONARY)
DAY 100.000 $160.000 $5.000 $175.000 $0.010 $75.000
TMA (MOBILE OPERATION)
HR 100.000 $80.000 $91.000 $50.000 $25.000 $25.000
Totals: $836,030.160 $889,845.100 $917,511.600 $1,060,748.890 $1,334,330.450