HILL FM 934 (1831-01-019)

Items: 93

County: HILL
Length: N/A
Highway: FM 934
District: WACO
Control Number: 1831-01-019
DBE Goal: N/A
Project: STP 2017(599)
Guaranty: N/A
Time: 170 WORKING DAYS
Engineer's Estimate: $2,335,603.70
Date: 02/03/2017 (9 years ago)
Contract Number: N/A
Type: WDN, GR, BS, SURF, ADD SHLDRS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (6)
E
Engineer's Estimate
$2,335,603.70
$2,487,232.28
Over/Under Est: 6.49% $151,628.58
Over/Under Est: 10.92% $255,144.73
Amt Left: 4.16% $103,516.15
Over/Under Est: 14.89% $347,858.26
Amt Left: 7.89% $196,229.68
Delta: -3.58% -$92,713.53
Over/Under Est: 22.56% $526,991.96
Amt Left: 15.09% $375,363.38
Delta: -6.68% -$179,133.70
Over/Under Est: 50.76% $1,185,490.53
Amt Left: 41.57% $1,033,861.95
Delta: -23.00% -$658,498.57
$4,366,902.40
Over/Under Est: 86.97% $2,031,298.70
Amt Left: 75.57% $1,879,670.12
Delta: -24.02% -$845,808.17

Bid Items & Bid Tabulations

93 Total 0 of 93
HILL  |  FM 934  |  WACO  |  1831-01-019  |  02/03/2017  |  $2,335,603.70  |  STP 2017(599)  |  WDN, GR, BS, SURF, ADD SHLDRS  |  170 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
BIG CREEK CONSTRUCTION, LTD.
KNIFE RIVER CORPORATION - SOUTH
BRETT CONSTRUCTION COMPANY
FRITCHER CONSTRUCTION SERVICES
OLDCASTLE MATERIALS TEXAS, INC.
FNH CONSTRUCTION, LLC
PREPARING ROW
STA 5.000 $2,000.000 $5,000.000 $1,500.000 $13,000.000 $2,500.000 $26,500.000 $10,000.000
REMOVING CONC (RIPRAP)
SY 88.000 $15.000 $15.000 $34.000 $20.000 $26.250 $33.150 $20.000
EXCAVATION (ROADWAY)
CY 2,469.000 $8.000 $15.000 $17.000 $15.000 $8.000 $20.000 $20.000
EXCAVATION (CHANNEL)
CY 32.000 $20.000 $100.000 $11.000 $30.000 $8.000 $10.050 $20.000
EMBANKMENT (FINAL)(DENS CONT)(TY B)
CY 9,374.000 $8.000 $15.000 $17.000 $13.000 $16.000 $20.000 $25.000
FURNISHING AND PLACING TOPSOIL (3")
SY 85,662.000 $0.750 $0.500 $0.100 $1.250 $1.650 $0.720 $2.250
BROADCAST SEED (PERM) (RURAL) (CLAY)
SY 8,568.000 $0.250 $0.250 $0.160 $0.450 $0.260 $0.160 $0.500
BROADCAST SEED (TEMP) (WARM)
SY 4,284.000 $0.250 $0.490 $0.130 $0.530 $0.260 $0.130 $0.500
BROADCAST SEED (TEMP) (COOL)
SY 4,284.000 $0.250 $0.490 $0.130 $0.530 $0.260 $0.130 $0.500
DRILL SEEDING (PERM) (RURAL) (CLAY)
SY 77,094.000 $0.100 $0.120 $0.160 $0.250 $0.110 $0.160 $0.500
DRILL SEEDING (TEMP) (WARM)
SY 38,547.000 $0.100 $0.140 $0.130 $0.250 $0.080 $0.130 $0.500
DRILL SEEDING (TEMP) (COOL)
SY 38,547.000 $0.100 $0.140 $0.130 $0.250 $0.080 $0.130 $0.500
VEGETATIVE WATERING
MG 1,390.000 $14.000 $5.000 $5.000 $8.000 $20.000 $13.200 $50.000
SOIL RETENTION BLANKETS (CL 1) (TY B)
SY 1,024.000 $2.000 $2.500 $2.000 $2.000 $1.310 $1.350 $6.500
PROOF ROLLING
HR 22.000 $100.000 $110.000 $50.000 $60.000 $75.000 $95.000 $150.000
FL BS (CMP IN PLC)(TY D GR 4)(FNAL POS)
CY 11,924.000 $36.000 $30.000 $40.000 $35.000 $56.000 $55.000 $62.000
REWORK BS MTL (TY C) (6") (DENS CONT)
SY 32,410.000 $2.500 $1.870 $2.100 $1.750 $1.500 $3.000 $3.500
CEMENT
TON 550.000 $150.000 $130.000 $135.000 $130.000 $100.000 $125.000 $171.000
CEMENT TREAT(EXIST MATL)(8")
SY 45,802.000 $2.000 $2.000 $1.500 $1.750 $2.000 $4.000 $3.850
SALV, HAUL & STKPL RCL ASPH PV (10")
SY 1,964.000 $5.000 $5.000 $9.760 $5.250 $5.250 $12.000 $20.000
EMULS ASPH (BS OR SUBGR TRT)(MS-2)
GAL 21,666.000 $3.000 $2.200 $3.000 $2.550 $3.000 $2.000 $6.500
ASPH (CRS-2)
GAL 28,618.000 $2.000 $1.800 $1.870 $2.910 $2.840 $1.950 $6.500
AGGR (TY-PD GR-4 OR TY-PL GR-4)(SAC-B)
CY 382.000 $110.000 $120.000 $118.000 $85.000 $123.000 $121.000 $125.000
ASPH(AC-15P,AC-20XP,AC10-2TR,AC-12-5TR)
GAL 16,694.000 $3.600 $2.800 $2.400 $3.000 $3.400 $3.000 $6.500
AGGR(TY D GR 3 OR TY L GR 3)
CY 502.000 $120.000 $80.000 $105.000 $85.000 $127.000 $107.000 $125.000
D-GR HMA TY-B PG64-22
TON 1,064.000 $60.000 $75.000 $75.000 $87.000 $125.000 $95.000 $140.000
D-GR HMA TY-D PG64-22
TON 266.000 $77.000 $90.000 $98.000 $100.000 $125.000 $110.000 $140.000
PLANE ASPH CONC PAV (1.5")
SY 32,410.000 $2.000 $1.000 $0.450 $0.900 $0.550 $2.000 $4.000
PLANE ASPH CONC PAV (0" TO 5")
SY 184.000 $3.000 $10.000 $17.390 $7.000 $5.250 $15.000 $10.000
CEM STABIL BKFL
CY 256.100 $140.000 $150.000 $177.000 $120.000 $120.000 $173.000 $140.000
CUT & RESTORING PAV
SY 85.600 $80.000 $100.000 $158.000 $150.000 $80.000 $150.000 $200.000
TRENCH EXCAVATION PROTECTION
LF 117.200 $5.000 $25.000 $6.390 $1.000 $26.250 $6.050 $3.500
TEMPORARY SPL SHORING
SF 284.000 $35.000 $20.000 $13.850 $30.000 $78.750 $13.050 $300.000
RIPRAP (CONC)(CL B)(5 IN)
CY 158.100 $450.000 $450.000 $418.000 $605.000 $577.500 $406.000 $650.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 51.000 $140.000 $200.000 $155.000 $125.000 $115.000 $150.000 $185.000
RETROFIT RAIL (TY T131RC)
LF 187.000 $200.000 $300.000 $178.000 $174.000 $183.750 $115.000 $185.000
CONC BOX CULV (6 FT X 5 FT)
LF 112.000 $350.000 $500.000 $496.000 $500.000 $630.000 $482.000 $400.000
CONC BOX CULV (6 FT X 5 FT)(EXTEND)
LF 79.000 $600.000 $1,000.000 $856.000 $684.000 $630.000 $832.000 $540.000
RC PIPE (CL III)(18 IN)
LF 320.000 $60.000 $70.000 $51.000 $58.000 $50.000 $49.200 $65.000
RC PIPE (CL III)(24 IN)
LF 488.000 $70.000 $80.000 $68.000 $71.500 $71.000 $66.500 $85.000
RC PIPE (CL III)(30 IN)
LF 144.000 $85.000 $100.000 $92.000 $85.000 $102.000 $90.000 $105.000
RC PIPE (CL III)(36 IN)
LF 144.000 $150.000 $120.000 $129.000 $116.000 $144.000 $125.000 $150.000
INLET (COMPL)(PSL)(FG)(4FTX4FT-4FTX4FT)
EA 1.000 $4,800.000 $5,000.000 $4,200.000 $4,500.000 $4,512.000 $4,058.000 $5,000.000
HEADWALL (CH - PW - 0) (DIA= 24 IN)
EA 5.000 $4,100.000 $3,500.000 $6,000.000 $5,500.000 $5,775.000 $5,828.000 $18,000.000
WINGWALL (PW - 1) (HW=7 FT)
EA 4.000 $15,000.000 $45,000.000 $18,650.000 $33,500.000 $18,900.000 $18,100.000 $18,000.000
WINGWALL (PW - 1) (HW=8 FT)
EA 2.000 $25,000.000 $46,000.000 $15,800.000 $40,000.000 $20,475.000 $15,305.000 $25,000.000
SET (TY II) (18 IN) (RCP) (4: 1) (C)
EA 2.000 $1,000.000 $600.000 $930.000 $1,500.000 $675.000 $905.000 $1,000.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 20.000 $900.000 $700.000 $930.000 $1,000.000 $675.000 $905.000 $1,500.000
SET (TY II) (24 IN) (RCP) (4: 1) (C)
EA 11.000 $800.000 $800.000 $930.000 $1,050.000 $1,035.000 $905.000 $2,000.000
SET (TY II) (24 IN) (RCP) (6: 1) (C)
EA 1.000 $1,200.000 $1,000.000 $1,252.000 $2,000.000 $1,410.000 $1,217.000 $2,500.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 6.000 $1,100.000 $1,000.000 $1,080.000 $1,370.000 $1,410.000 $1,050.000 $3,000.000
SET (TY II) (30 IN) (RCP) (4: 1) (C)
EA 4.000 $1,200.000 $1,200.000 $1,250.000 $2,500.000 $1,670.000 $1,215.000 $3,000.000
SET (TY II) (30 IN) (RCP) (6: 1) (P)
EA 4.000 $2,100.000 $1,400.000 $1,785.000 $1,890.000 $1,836.000 $1,730.000 $3,000.000
SET (TY II) (36 IN) (RCP) (6: 1) (P)
EA 6.000 $3,000.000 $3,200.000 $4,795.000 $3,475.000 $4,845.000 $4,655.000 $3,000.000
CLEAN EXIST CULVERTS
EA 6.000 $1,400.000 $2,000.000 $800.000 $1,000.000 $1,575.000 $785.000 $850.000
REMOV STR (WINGWALL)
EA 2.000 $1,400.000 $2,500.000 $1,130.000 $1,200.000 $1,575.000 $1,100.000 $1,500.000
REMOV STR (HEADWALL)
EA 3.000 $2,400.000 $750.000 $1,130.000 $1,500.000 $1,155.000 $1,100.000 $1,500.000
REMOV STR (PIPE)
LF 771.100 $16.000 $12.000 $8.500 $10.000 $10.500 $8.050 $30.000
REMOV STR (BOX CULVERT)
LF 33.200 $50.000 $150.000 $340.000 $40.000 $78.750 $330.000 $350.000
MOBILIZATION
LS 1.000 $175,000.000 $199,000.000 $259,000.000 $215,000.000 $261,000.000 $390,000.000 $420,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 8.000 $3,000.000 $3,000.000 $19,500.000 $6,000.000 $1,650.000 $34,000.000 $8,500.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 112.000 $30.000 $25.000 $29.000 $25.000 $30.000 $30.000 $30.000
ROCK FILTER DAMS (REMOVE)
LF 112.000 $10.000 $5.000 $6.000 $7.000 $8.000 $8.000 $15.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 188.000 $15.000 $12.000 $13.250 $15.000 $30.000 $30.000 $45.000
CONSTRUCTION EXITS (REMOVE)
SY 188.000 $5.000 $3.000 $4.000 $7.000 $8.000 $8.000 $20.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,802.000 $3.000 $5.000 $4.000 $3.000 $3.000 $3.000 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,802.000 $0.500 $0.500 $0.250 $1.000 $1.000 $0.750 $2.000
CONSTRUCTING DETOURS
SY 665.000 $90.000 $50.000 $50.000 $70.000 $40.000 $100.000 $45.000
DRIVEWAYS (SURF TREAT)
SY 1,775.000 $15.000 $20.000 $30.000 $45.000 $17.850 $60.000 $42.000
MTL W-BEAM GD FEN (STEEL POST)
LF 450.000 $22.000 $30.000 $21.000 $25.250 $25.200 $19.750 $25.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $1,500.000 $1,700.000 $2,100.000 $1,690.000 $1,680.000 $1,400.000 $1,850.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $2,300.000 $2,200.000 $2,500.000 $2,250.000 $2,247.000 $2,340.000 $2,850.000
WIRE FENCE (TY C)
LF 263.000 $10.000 $20.000 $15.000 $11.000 $12.000 $25.000 $20.000
MAILBOX INSTALL-S (WC-POST) TY 3
EA 8.000 $200.000 $150.000 $150.000 $250.000 $220.500 $175.000 $650.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 1.000 $500.000 $650.000 $750.000 $425.000 $609.000 $400.000 $650.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 2.000 $520.000 $850.000 $640.000 $525.000 $687.750 $500.000 $650.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U-EXAL)
EA 1.000 $810.000 $900.000 $925.000 $740.000 $745.500 $700.000 $650.000
IN SM RD SN SUP&AM TY10BWG(1)SB(U)
EA 2.000 $1,000.000 $850.000 $600.000 $370.000 $687.750 $350.000 $650.000
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 50.000 $330.000 $350.000 $440.000 $315.000 $294.000 $300.000 $650.000
IN SM RD SN SUP&AM TYTWT(1)WS(T)
EA 2.000 $400.000 $400.000 $500.000 $370.000 $372.750 $350.000 $650.000
REMOVE SM RD SN SUP&AM
EA 20.000 $110.000 $100.000 $80.000 $125.000 $68.250 $100.000 $100.000
RELOCATE SM RD SN SUP & AM TY TEMP
EA 26.000 $200.000 $200.000 $200.000 $185.000 $131.250 $175.000 $650.000
INSTL DEL ASSM (D-SW)SZ 1(FLX)SRF(BI)
EA 8.000 $60.000 $50.000 $75.000 $53.000 $63.000 $50.000 $100.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 2.000 $30.000 $50.000 $18.000 $26.500 $23.100 $25.000 $100.000
INSTL OM ASSM (OM-2X)(WC)GND
EA 22.000 $40.000 $50.000 $50.000 $79.000 $47.250 $75.000 $100.000
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 13,284.000 $0.600 $1.000 $0.750 $0.600 $0.680 $0.550 $0.500
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 172.000 $1.200 $2.000 $2.500 $1.000 $1.680 $1.200 $10.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 130.000 $6.000 $10.000 $8.000 $7.900 $5.600 $7.500 $20.000
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 29,244.000 $0.300 $0.320 $0.330 $0.330 $0.450 $0.310 $0.500
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 2,130.000 $0.300 $0.360 $0.370 $0.370 $0.500 $0.350 $0.500
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 17,918.000 $0.300 $0.330 $0.340 $0.340 $0.450 $0.320 $0.500
REFL PAV MRKR TY II-A-A
EA 322.000 $3.000 $5.000 $4.950 $4.900 $4.000 $4.650 $15.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $15,000.000 $10,000.000 $5,000.000 $8,000.000 $7,500.000 $16,200.000 $16,500.000
Totals: $2,335,603.700 $2,487,232.280 $2,590,748.438 $2,683,461.960 $2,862,595.660 $3,521,094.235 $4,366,902.400