HILL FM 339 (1662-02-013)

Items: 82

County: HILL
Length: N/A
Highway: FM 339
District: WACO
Control Number: 1662-02-013
DBE Goal: N/A
Project: F 2023(278)
Guaranty: N/A
Time: 165 WORKING DAYS
Engineer's Estimate: $2,652,025.20
Date: 12/02/2022 (3 years ago)
Contract Number: N/A
Type: REHABILITATE EXISTING ROADWAY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$2,652,025.20
$2,487,780.12
Over/Under Est: -6.19% -$164,245.08
Over/Under Est: 12.06% $319,766.28
Amt Left: 19.46% $484,011.36
Over/Under Est: 19.74% $523,562.88
Amt Left: 27.65% $687,807.96
Delta: -6.86% -$203,796.60

Bid Items & Bid Tabulations

82 Total 0 of 82
HILL  |  FM 339  |  WACO  |  1662-02-013  |  12/02/2022  |  $2,652,025.20  |  F 2023(278)  |  REHAB EXIST ROADWAY  |  165 WORKING DAYS
Alt
Item Code
Description
Unit
Quantity
Engineer's Estimate
BIG CREEK CONSTRUCTION, LTD.
KNIFE RIVER CORPORATION - SOUTH
TEXAS MATERIALS GROUP, INC.
PREPARING ROW
STA 70.000 $1,500.000 $1,000.000 $650.000 $850.000
EXCAVATION (ROADWAY)
CY 5,847.000 $13.500 $15.000 $6.500 $9.250
EMBANKMENT (FINAL)(DENS CONT)(TY B)
CY 5,891.000 $16.000 $15.000 $19.500 $16.000
FURNISHING AND PLACING TOPSOIL (4")
SY 40,261.000 $1.650 $1.000 $2.350 $0.300
DRILL SEEDING (PERM) (RURAL) (CLAY)
SY 40,261.000 $0.200 $0.190 $0.210 $0.170
DRILL SEED (TEMP)(WARM OR COOL)
SY 40,261.000 $0.200 $0.150 $0.190 $0.160
VEGETATIVE WATERING
MG 655.000 $25.000 $15.000 $1.000 $30.000
SOIL RETENTION BLANKETS (CL 1) (TY D)
SY 10,066.000 $1.500 $1.250 $1.250 $1.000
PROOF ROLLING
HR 14.000 $125.000 $150.000 $105.000 $150.000
FL BS (CMP IN PLC)(TYD GR1-2)(FNAL POS)
CY 3,876.000 $56.000 $55.000 $67.650 $86.000
FL BS (RDWY DEL) (TY D GR 3)
TON 923.000 $22.000 $35.000 $34.100 $57.000
REWRKING BS MATL (TY C)(10")(ORD COMP)
SY 21,694.000 $2.750 $2.000 $1.400 $3.500
CEMENT
TON 290.000 $265.000 $250.000 $258.000 $275.000
CEMENT TREAT(EXIST MATL)(8")
SY 23,985.000 $2.750 $3.500 $2.950 $3.300
SALV, HAUL & STKPL RCL APH PV (0 TO 6")
SY 1,319.000 $3.500 $7.000 $20.450 $21.000
EMULS ASPH (BS OR SUBGR TRT)(MS-2)
GAL 13,493.000 $3.500 $4.000 $0.010 $4.500
ASPH (CRS-2)
GAL 10,458.000 $5.500 $3.750 $4.000 $3.500
AGGR(TY-D GR-4 OR TY-L GR-4)
CY 175.000 $245.000 $100.000 $212.850 $175.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
SY 1,500.000 $77.000 $60.000 $70.000 $70.000
PLANE ASPH CONC PAV (2")
SY 6,878.000 $3.050 $3.500 $4.100 $4.000
CEM STABIL BKFL
CY 46.000 $175.000 $150.000 $236.000 $295.000
CUT & RESTORING PAV
SY 66.000 $212.500 $100.000 $115.000 $155.000
TRENCH EXCAVATION PROTECTION
LF 37.000 $30.000 $20.000 $9.150 $10.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 37.000 $220.000 $200.000 $255.000 $300.000
CONC BOX CULV (4 FT X 2 FT)
LF 36.000 $405.000 $500.000 $533.840 $440.000
CONC BOX CULV (8 FT X 5 FT)
LF 96.000 $818.750 $1,000.000 $1,181.000 $1,200.000
MANH (COMPL)(PRM)(48IN)
EA 1.000 $4,600.000 $7,000.000 $9,672.210 $5,300.000
HEADWALL (CH - PW - 0) (DIA= 36 IN)
EA 2.000 $9,687.500 $9,000.000 $7,635.400 $20,000.000
WINGWALL (PW - 1) (HW=8 FT)
EA 1.000 $31,375.000 $35,000.000 $22,127.000 $30,000.000
WINGWALL (PW - 1) (HW=9 FT)
EA 1.000 $38,875.000 $40,000.000 $25,993.000 $35,000.000
SET (TY I)(S= 4 FT)(HW= 3 FT)(6:1) (P)
EA 2.000 $8,700.000 $7,500.000 $13,325.000 $11,300.000
SET (TY II) (18 IN) (RCP) (4: 1) (C)
EA 1.000 $1,160.000 $1,100.000 $1,352.940 $1,000.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 15.000 $1,440.000 $1,250.000 $1,544.250 $1,105.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 2.000 $2,190.000 $1,500.000 $1,859.300 $1,430.000
SET (TY II) (36 IN) (RCP) (6: 1) (P)
EA 4.000 $5,190.000 $4,500.000 $5,496.000 $5,200.000
CLEAN EXIST CULVERTS
EA 1.000 $3,250.000 $2,500.000 $1,500.000 $2,000.000
REMOV STR (WINGWALL)
EA 2.000 $2,300.000 $2,000.000 $1,545.000 $1,000.000
REMOV STR (HEADWALL)
EA 4.000 $1,500.000 $2,000.000 $1,542.000 $900.000
REMOV STR (PIPE)
LF 263.000 $205.000 $25.000 $12.600 $12.000
REMOV STR (BOX CULVERT)
LF 58.000 $120.000 $60.000 $230.000 $100.000
MOBILIZATION
LS 1.000 $235,889.200 $230,000.000 $292,292.000 $317,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 11.000 $5,500.000 $7,000.000 $9,038.000 $15,000.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 1,075.000 $26.000 $35.000 $37.000 $34.000
ROCK FILTER DAMS (REMOVE)
LF 1,075.000 $8.000 $12.000 $13.750 $10.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 2,000.000 $3.050 $4.000 $6.700 $3.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 2,000.000 $1.000 $1.000 $1.150 $1.000
DRIVEWAYS (ACP)(TYPE 1)
SY 880.000 $30.000 $40.000 $105.000 $80.000
DRIVEWAYS (ACP) (TYPE 2)
SY 439.000 $51.000 $50.000 $150.000 $160.000
TURNOUTS (RAP)
SY 534.000 $85.000 $25.000 $37.000 $12.500
DRIVEWAYS (ACP)(TYPE 3)
SY 2,658.000 $55.000 $45.000 $105.000 $85.000
RUMBLE STRIPS (SHOULDER) ASPHALT
LF 7,500.000 $0.600 $1.000 $1.500 $0.750
RUMBLE STRIPS (CENTERLINE) ASPHALT
LF 3,750.000 $0.600 $1.000 $1.650 $0.950
MAILBOX INSTALL-S (WC-POST) TY 3
EA 10.000 $230.000 $250.000 $230.000 $212.000
MAILBOX INSTALL-D (WC-POST) TY 3
EA 1.000 $235.000 $300.000 $290.000 $257.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 28.000 $530.000 $650.000 $630.000 $641.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 20.000 $650.000 $900.000 $860.000 $873.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 1.000 $805.000 $1,100.000 $975.000 $1,002.000
IN SM RD SN SUP&AM TYS80(1)SA(U-2EXT)
EA 1.000 $1,030.000 $1,200.000 $975.000 $1,197.000
RELOCATE SM RD SN SUP & AM TY TEMP
EA 51.000 $185.000 $200.000 $230.000 $188.000
INSTL OM ASSM (OM-2Y)(WC)GND
EA 4.000 $80.000 $100.000 $230.000 $77.000
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 22,873.000 $0.300 $0.110 $0.110 $0.250
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 624.000 $3.850 $2.000 $1.720 $4.500
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 22,886.000 $0.300 $0.350 $0.360 $0.250
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 887.000 $0.750 $1.250 $1.000 $1.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 331.000 $8.000 $12.000 $12.600 $6.250
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 17,715.000 $0.500 $0.650 $0.690 $0.480
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 1,401.000 $0.850 $0.650 $0.690 $0.550
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 12,124.000 $0.500 $0.650 $0.690 $0.480
REFL PAV MRKR TY II-A-A
EA 224.000 $4.150 $6.000 $6.760 $5.300
FULL - WIDTH MOWING
CYC 2.000 $3,000.000 $1,500.000 $6,500.000 $5,500.000
SP MIXES SP-C SAC-B PG64-22
TON 3,234.000 $106.250 $110.000 $126.900 $156.000
UNDERSEAL COURSE
GAL 7,343.000 $4.500 $4.000 $5.400 $0.010
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $10,650.000 $8,000.000 $2,930.000 $12,000.000
TMA (STATIONARY)
DAY 100.000 $205.000 $200.000 $3.000 $325.000
TMA (MOBILE OPERATION)
HR 250.000 $70.000 $25.000 $45.000 $25.000
1
THERMOPLASTIC PIPE(18 IN)(PP)(TYPE III)
LF 432.000 $45.000 $0.000 $141.000 $45.000
1A
RC PIPE (CL III)(18 IN)
LF 432.000 $45.000 $95.000 $0.000 $0.000
2
THERMOPLASTIC PIPE(24 IN)(PP)(TYPE III)
LF 40.000 $50.000 $0.000 $136.350 $75.000
2A
RC PIPE (CL III)(24 IN)
LF 40.000 $50.000 $120.000 $0.000 $0.000
3
RC PIPE (CL III)(36 IN)
LF 18.000 $237.500 $0.000 $394.000 $256.000
3
THERMOPLASTIC PIPE(36")(PP) (TYPE III)
LF 64.000 $237.500 $0.000 $196.000 $190.000
3A
RC PIPE (CL III)(36 IN)
LF 82.000 $237.500 $200.000 $0.000 $0.000
Totals: $2,692,940.200 $2,487,780.120 $2,971,791.480 $3,175,588.080