Bid Cobra

HILL CO (0909-37-068)

Items: 39

County: HILL
Length: N/A
Highway: CO
District: WACO
Control Number: 0909-37-068
DBE Goal: 450.0%
Project: BR 2021(316)
Guaranty: N/A
Time: 75 WORKING DAYS
Engineer's Estimate: $769,812.05
Date: 08/01/2024 (1 year ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (6)
E
Engineer's Estimate
$769,812.05
$759,759.10
Over/Under Est: -1.31% -$10,052.95
Over/Under Est: 5.8% $44,673.15
Amt Left: 7.2% $54,726.10
Over/Under Est: 9.74% $74,945.12
Amt Left: 11.19% $84,998.07
Delta: -3.72% -$30,271.97
$961,090.00
Over/Under Est: 24.85% $191,277.95
Amt Left: 26.5% $201,330.90
Delta: -13.77% -$116,332.83
$974,569.90
Over/Under Est: 26.6% $204,757.85
Amt Left: 28.27% $214,810.80
Delta: -1.40% -$13,479.90
Over/Under Est: 31.06% $239,097.85
Amt Left: 32.79% $249,150.80
Delta: -3.52% -$34,340.00
Subcontractor Percentage Amount
HODGES AND SON CONSTRUCTION COMPANY, INC. 6.35% $48,244.70
FORTSON CONTRACTING, INC. 2.08% $15,802.99
WOLFE CONSTRUCTION GROUP, INCORPORATED 1.32% $10,028.82
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC 0.77% $5,850.15
TORO BRAVO CONSTRUCTION, LLC 0.00% $0.00
Total: 10.52% $79,926.66

Bid Items & Bid Tabulations

39 Total 0 of 39
HILL  |  CO  |  WACO  |  0909-37-068  |  08/01/2024  |  $769,812.05  |  BR 2021(316)  |  BRIDGE REPL  |  75 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
PMCO CONSTRUCTION LLC
KNIFE RIVER CORPORATION - SOUTH
TALBERT COMPANIES LLC
SKYLINE BRIDGE LLC
C. E. BARKER, LTD.
HODGES AND SON CONSTRUCTION COMPANY, INC.
PREPARING ROW
STA 5.000 $4,262.000 $3,000.000 $4,500.000 $2,737.500 $4,000.000 $19,000.000 $6,000.000
EXCAVATION (ROADWAY)
CY 287.000 $20.000 $20.000 $30.000 $20.020 $25.000 $43.890 $50.000
EXCAVATION (CHANNEL)
CY 525.000 $10.000 $20.000 $20.000 $43.800 $18.000 $43.890 $40.000
EMBANKMENT (FINAL)(DENS CONT)(TY B)
CY 1,064.000 $15.000 $22.000 $25.000 $21.350 $35.000 $43.890 $40.000
FURNISHING AND PLACING TOPSOIL (4")
SY 1,973.000 $1.000 $3.500 $1.000 $2.150 $3.500 $5.370 $6.000
BROADCAST SEED (PERM) (RURAL) (CLAY)
SY 1,973.000 $2.300 $1.100 $0.800 $0.600 $1.500 $1.030 $4.000
BROADCAST SEED (TEMP)(WARM OR COOL)
SY 1,973.000 $0.530 $1.100 $0.800 $0.450 $1.500 $1.030 $1.000
VEGETATIVE WATERING
MG 32.000 $43.000 $50.000 $50.000 $38.240 $1.000 $156.870 $1.000
SOIL RETENTION BLANKETS (CL 1) (TY A)
SY 1,973.000 $1.000 $1.250 $1.450 $1.120 $2.500 $1.710 $5.000
FL BS (CMP IN PLC)(TY D GR 3)(FNAL POS)
CY 215.000 $72.000 $140.000 $98.000 $98.550 $225.000 $76.810 $80.000
CEM STABIL BKFL
CY 118.000 $264.000 $245.000 $285.000 $274.670 $300.000 $192.020 $300.000
DRILL SHAFT (18 IN)
LF 40.000 $52.000 $136.000 $285.000 $273.750 $550.000 $133.960 $200.000
DRILL SHAFT (36 IN)
LF 147.000 $275.000 $375.000 $385.000 $383.250 $650.000 $452.160 $300.000
CL C CONC (ABUT)
CY 43.000 $1,491.000 $1,300.000 $1,480.000 $1,423.500 $1,300.000 $1,670.580 $1,800.000
REINF CONC SLAB
SF 2,600.000 $25.000 $30.000 $34.000 $26.190 $35.000 $35.660 $40.000
PRESTR CONC GIRDER (TX40)
LF 397.930 $222.000 $275.000 $335.000 $202.580 $275.000 $298.540 $430.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 824.000 $200.000 $154.000 $138.000 $219.000 $185.000 $111.100 $200.000
RAIL (TY T223)
LF 250.000 $168.000 $149.000 $150.000 $171.630 $150.000 $194.310 $150.000
ARMOR JOINT (SEALED)
LF 46.000 $152.000 $150.000 $160.000 $148.260 $175.000 $82.290 $200.000
RC PIPE (CL III)(30 IN)
LF 55.000 $184.000 $130.000 $110.000 $191.630 $250.000 $164.690 $150.000
SET (TY II) (30 IN) (RCP) (6: 1) (P)
EA 2.000 $3,425.000 $3,850.000 $3,900.000 $4,380.000 $5,500.000 $6,357.600 $5,000.000
REMOV STR (PIPE)
LF 24.000 $21.000 $40.000 $44.000 $22.180 $200.000 $192.020 $10.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 1.000 $31,000.000 $25,000.000 $17,500.000 $21,900.000 $25,000.000 $54,863.200 $40,000.000
MOBILIZATION
LS 1.000 $75,000.000 $65,000.000 $81,000.000 $76,981.200 $80,000.000 $90,000.000 $92,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 5.000 $4,535.000 $1,500.000 $1,500.000 $8,277.690 $2,500.000 $905.240 $3,000.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 214.000 $50.000 $40.000 $35.000 $29.290 $40.000 $48.010 $1.000
ROCK FILTER DAMS (REMOVE)
LF 214.000 $10.000 $10.000 $15.000 $11.000 $10.000 $20.570 $1.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 901.000 $4.000 $4.000 $8.000 $8.210 $3.750 $6.860 $1.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 901.000 $1.000 $1.000 $2.000 $2.010 $1.500 $2.740 $1.000
DRIVEWAYS (BASE)
SY 74.000 $42.000 $70.000 $40.000 $32.850 $90.000 $64.010 $55.000
MTL W-BEAM GD FEN (STEEL POST)
LF 125.000 $29.000 $32.800 $35.000 $36.070 $40.000 $45.180 $30.000
MTL BEAM GD FEN TRANS (TL2)
EA 2.000 $1,598.000 $1,425.000 $1,425.000 $1,650.430 $2,750.000 $2,067.300 $1,800.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 2.000 $1,366.000 $1,475.000 $1,495.000 $1,634.040 $2,200.000 $2,046.770 $1,800.000
MTL BM GD FEN TRANS (NON - SYM)
EA 2.000 $1,106.000 $907.000 $920.000 $887.520 $2,000.000 $1,111.690 $1,500.000
GUARDRAIL END TREATMENT (INSTALL)
EA 2.000 $3,106.000 $3,700.000 $3,450.000 $4,445.470 $4,000.000 $5,568.330 $3,000.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 6.000 $22.000 $36.000 $30.000 $22.570 $50.000 $28.270 $50.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 9.000 $37.000 $50.000 $40.000 $57.770 $50.000 $72.360 $50.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 28.000 $115.000 $49.000 $150.000 $171.500 $250.000 $109.730 $150.000
SUBSURFACE UTIL LOCATE (OUTSIDE RDBED)
EA 2.000 $1,000.000 $500.000 $1,400.000 $657.000 $5,000.000 $480.050 $2,000.000
Totals: $769,812.050 $759,759.100 $814,485.200 $844,757.179 $961,090.000 $974,569.902 $1,008,909.900