Job Info for 0834-02-031

County: HILL Highway: FM 308 Date: 07/01/2021 (3 years ago) Engineer's Estimate: $3,558,120 Control Number: 0834-02-031
Project: BR 2021(679) District: WACO Time: 135 WORKING DAYS Type: BRIDGE REPLACEMENT

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $3,558,120.00
KNIFE RIVER CORPORATION - SOUTH   $3,137,765.69 1
-11.81% | -$420,354.31
A. L. HELMCAMP, INC.   $3,196,084.19 2
-10.17% | -$362,035.81
1.86% | $58,318.50
ED BELL CONSTRUCTION COMPANY   $3,259,886.92 3
-8.38% | -$298,233.08
3.89% | $122,121.23
2.00% | $63,802.73
NEW WORLD CONTRACTING, LLC   $3,314,982.35 4
-6.83% | -$243,137.65
5.65% | $177,216.66
1.69% | $55,095.43
RAGLE CONSTRUCTION, INC.   $3,319,109.30 5
-6.72% | -$239,010.70
5.78% | $181,343.61
0.12% | $4,126.95
HODGES AND SON CONSTRUCTION COMPANY, INC.   $3,442,804.85 6
-3.24% | -$115,315.15
9.72% | $305,039.16
3.73% | $123,695.55
JAMES CONSTRUCTION GROUP, LLC   $3,485,124.98 7
-2.05% | -$72,995.02
11.07% | $347,359.29
1.23% | $42,320.13

Bid Items

Items: 58, 0 filtered
HILL FM 308  |  WACO  |  0834-02-031  |  07/01/2021  |  $3,558,120  |  BR 2021(679)  |  BRIDGE REPL  |  135 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate KNIFE RIVER CORPORATION - SOUTH A. L. HELMCAMP, INC. ED BELL CONSTRUCTION COMPANY NEW WORLD CONTRACTING, LLC RAGLE CONSTRUCTION, INC. HODGES AND SON CONSTRUCTION COMPANY, INC. JAMES CONSTRUCTION GROUP, LLC
100 6002 PREPARING ROW STA 23.000 $2,500.000 $1,500.000 $600.000 $500.000 $3,920.000 $10,000.000 $1,800.000 $15,200.000
105 6011 REMOVING STAB BASE AND ASPH PAV (2"-6") SY 5,458.000 $5.000 $2.250 $3.500 $1.000 $2.000 $3.000 $6.000 $2.240
110 6001 EXCAVATION (ROADWAY) CY 276.000 $20.000 $15.000 $14.000 $15.000 $15.000 $100.000 $20.000 $13.510
110 6002 EXCAVATION (CHANNEL) CY 1,030.000 $20.000 $15.000 $14.000 $15.000 $20.000 $13.000 $15.000 $11.360
132 6006 EMBANKMENT (FINAL)(DENS CONT)(TY C) CY 5,943.000 $20.000 $15.000 $18.000 $15.000 $25.000 $15.000 $20.000 $26.630
160 6003 FURNISHING AND PLACING TOPSOIL (4") SY 14,331.000 $2.000 $0.500 $1.000 $0.750 $2.000 $1.100 $2.250 $0.830
164 6003 BROADCAST SEED (PERM) (RURAL) (CLAY) SY 14,331.000 $0.700 $0.170 $0.180 $0.190 $0.200 $0.170 $0.500 $0.140
164 6071 BROADCAST SEED (TEMP)(WARM OR COOL) SY 14,331.000 $0.700 $0.150 $0.160 $0.150 $0.150 $0.150 $0.500 $0.140
168 6001 VEGETATIVE WATERING MG 232.000 $20.000 $20.000 $20.000 $60.500 $15.000 $26.000 $1.000 $18.500
169 6003 SOIL RETENTION BLANKETS (CL 1) (TY C) SY 11,832.000 $1.500 $1.000 $0.930 $0.890 $1.200 $0.890 $2.000 $0.800
247 6053 FL BS (CMP IN PLC)(TYD GR1-2)(FNAL POS) CY 2,073.000 $40.000 $52.000 $50.000 $55.000 $45.000 $50.000 $65.000 $63.390
251 6023 REWORK BS MTL (TY A) (6") (DENS CONT) SY 5,458.000 $4.000 $0.600 $2.000 $1.000 $4.750 $0.650 $8.000 $2.190
310 6027 PRIME COAT(MC-30 OR AE-P) GAL 1,205.000 $5.000 $4.500 $5.000 $4.250 $4.400 $4.200 $5.000 $4.200
316 6022 ASPH (CRS-2) GAL 2,710.000 $6.000 $3.300 $6.000 $3.250 $3.350 $3.200 $5.000 $3.200
316 6397 AGGR(TY-D GR-4 OR TY-L GR-4) CY 46.000 $300.000 $200.000 $290.000 $275.000 $273.000 $260.000 $300.000 $260.000
400 6005 CEM STABIL BKFL CY 373.000 $140.000 $180.000 $175.000 $150.000 $150.000 $80.000 $200.000 $165.230
416 6004 DRILL SHAFT (36 IN) LF 1,483.000 $210.000 $190.000 $150.000 $149.000 $190.000 $130.000 $145.000 $106.220
420 6011 CL B CONC (FLUME) CY 11.500 $500.000 $850.000 $700.000 $600.000 $400.000 $510.000 $550.000 $891.360
420 6014 CL C CONC (ABUT)(HPC) CY 111.400 $1,000.000 $950.000 $1,250.000 $1,000.000 $1,000.000 $900.000 $1,100.000 $757.900
420 6030 CL C CONC (CAP)(HPC) CY 76.500 $1,200.000 $950.000 $1,350.000 $1,000.000 $1,250.000 $1,100.000 $1,150.000 $861.180
420 6038 CL C CONC (COLUMN)(HPC) CY 46.300 $1,500.000 $950.000 $1,050.000 $1,000.000 $1,250.000 $900.000 $1,400.000 $893.590
422 6001 REINF CONC SLAB SF 18,020.000 $16.000 $19.000 $20.000 $20.000 $16.500 $19.000 $20.000 $18.380
422 6015 APPROACH SLAB CY 154.200 $425.000 $520.000 $900.000 $550.000 $400.000 $500.000 $650.000 $568.440
425 6020 PRESTR CONC BOX BEAM (5XB20) LF 912.000 $250.000 $230.000 $250.000 $251.000 $270.000 $225.000 $250.000 $219.840
425 6022 PRESTR CONC BOX BEAM (5XB28) LF 1,192.000 $300.000 $230.000 $240.000 $238.000 $265.000 $225.000 $250.000 $194.770
432 6035 RIPRAP (STONE PROTECTION)(24 IN) CY 3,396.000 $115.000 $100.000 $70.000 $120.000 $100.000 $95.000 $130.000 $96.580
432 6045 RIPRAP (MOW STRIP)(4 IN) CY 109.000 $420.000 $495.000 $470.000 $550.000 $395.000 $450.000 $500.000 $514.750
450 6003 RAIL (TY T1W) LF 1,164.000 $150.000 $190.000 $230.000 $180.000 $145.000 $160.000 $200.000 $159.500
454 6018 SEALED EXPANSION JOINT (4 IN) (SEJ - M) LF 231.000 $110.000 $125.000 $90.000 $100.000 $115.000 $125.000 $100.000 $100.860
464 6005 RC PIPE (CL III)(24 IN) LF 68.000 $75.000 $82.000 $95.000 $90.000 $85.000 $90.000 $60.000 $105.720
467 6395 SET (TY II) (24 IN) (RCP) (6: 1) (P) EA 4.000 $1,500.000 $1,200.000 $950.000 $1,250.000 $1,575.000 $1,400.000 $2,000.000 $1,456.960
496 6004 REMOV STR (SET) EA 6.000 $450.000 $200.000 $600.000 $200.000 $200.000 $500.000 $500.000 $303.660
496 6010 REMOV STR (BRIDGE 100 - 499 FT LENGTH) EA 3.000 $90,000.000 $40,000.000 $20,000.000 $17,500.000 $24,000.000 $88,500.000 $34,000.000 $93,002.000
496 6016 REMOV STR (PIPE) EA 3.000 $400.000 $250.000 $750.000 $300.000 $500.000 $300.000 $500.000 $618.150
500 6001 MOBILIZATION LS 1.000 $325,000.000 $300,000.000 $300,000.000 $413,000.000 $350,000.000 $300,000.000 $310,000.000 $348,329.280
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 9.000 $5,000.000 $1,500.000 $5,000.000 $5,250.000 $4,500.000 $2,000.000 $2,555.000 $1,308.890
506 6002 ROCK FILTER DAMS (INSTALL) (TY 2) LF 696.000 $30.000 $30.130 $30.000 $33.000 $31.000 $27.000 $5.000 $27.000
506 6011 ROCK FILTER DAMS (REMOVE) LF 696.000 $10.000 $9.400 $10.000 $15.000 $8.400 $8.000 $5.000 $8.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 4,553.000 $3.000 $3.750 $2.500 $2.000 $2.500 $2.400 $1.000 $2.400
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 4,553.000 $1.000 $0.560 $0.600 $0.200 $0.650 $0.600 $1.000 $0.600
530 6005 DRIVEWAYS (ACP) SY 83.000 $50.000 $40.000 $75.000 $80.000 $34.000 $50.000 $50.000 $72.200
533 6001 RUMBLE STRIPS (SHOULDER) LF 2,782.000 $0.200 $1.850 $1.240 $1.100 $3.250 $0.900 $1.200 $0.640
533 6002 RUMBLE STRIPS (CENTERLINE) LF 1,391.000 $0.200 $1.850 $1.810 $1.100 $3.250 $0.900 $1.200 $0.640
540 6002 MTL W-BEAM GD FEN (STEEL POST) LF 1,415.000 $25.000 $29.000 $27.000 $25.500 $26.750 $25.500 $1.200 $28.980
540 6006 MTL BEAM GD FEN TRANS (THRIE-BEAM) EA 12.000 $1,750.000 $2,750.000 $2,000.000 $1,900.000 $1,995.000 $1,900.000 $30.000 $2,138.500
542 6001 REMOVE METAL BEAM GUARD FENCE LF 2,398.000 $3.000 $1.850 $2.000 $2.000 $2.100 $2.000 $2.000 $1.230
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 8.000 $2,600.000 $2,750.000 $2,700.000 $2,550.000 $2,675.000 $2,550.000 $2,500.000 $2,998.050
544 6003 GUARDRAIL END TREATMENT (REMOVE) EA 8.000 $325.000 $210.000 $210.000 $200.000 $210.000 $200.000 $500.000 $204.930
644 6076 REMOVE SM RD SN SUP&AM EA 2.000 $100.000 $50.000 $260.000 $125.000 $125.000 $95.450 $500.000 $92.000
658 6014 INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI) EA 30.000 $25.000 $28.000 $18.900 $18.000 $19.000 $18.000 $30.000 $20.130
658 6062 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) EA 59.000 $35.000 $34.000 $26.250 $25.000 $26.000 $25.000 $30.000 $32.450
658 6100 INSTL OM ASSM (OM-2Z)(WFLX)GND(BI) EA 2.000 $125.000 $125.000 $26.250 $250.000 $93.000 $85.000 $60.000 $92.890
666 6303 RE PM W/RET REQ TY I (W)4"(SLD)(100MIL) LF 4,450.000 $2.000 $1.170 $0.950 $0.900 $1.250 $1.200 $1.500 $0.900
666 6312 RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL) LF 492.000 $2.000 $1.330 $1.050 $1.000 $2.100 $2.000 $3.000 $1.000
666 6315 RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL) LF 2,485.000 $2.000 $1.170 $0.950 $0.900 $1.250 $1.200 $1.500 $0.900
672 6009 REFL PAV MRKR TY II-A-A EA 57.000 $20.000 $12.500 $6.300 $6.000 $10.500 $10.000 $10.000 $6.000
3077 6023 SP MIXES SP-C SAC-B PG70-22 TON 663.000 $100.000 $97.000 $120.000 $122.000 $120.000 $114.000 $125.000 $114.000
6001 6002 PORTABLE CHANGEABLE MESSAGE SIGN EA 2.000 $10,000.000 $2,500.000 $10,000.000 $7,500.000 $9,500.000 $10,000.000 $15,000.000 $975.000
Totals: $3,558,120.00 $3,137,765.69 $3,196,084.19 $3,259,886.92 $3,314,982.35 $3,319,109.30 $3,442,804.85 $3,485,124.99