HIDALGO FM 907 (1586-01-089)
Items: 91
County: HIDALGO
Length: N/A
Highway: FM 907
District: PHARR
Control Number: 1586-01-089
DBE Goal: N/A
Project: F 2022(934)
Guaranty: N/A
Time: 140 WORKING DAYS
Engineer's Estimate: $1,249,261.40
Date: 08/03/2022 (3 years ago)
Contract Number: N/A
Type: TRAFFIC SIGNAL IMPROVEMENTS
Mail/Deliver Bids To: N/A
RENE GARZA
JESUS NORIEGA
Bidders (5)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$1,249,261.40 | |||
| $1,313,573.10 |
5.15%
$64,311.70
|
|||
| $1,393,186.89 |
11.52%
$143,925.49
|
6.06%
$79,613.79
|
||
| $1,446,141.45 |
15.76%
$196,880.05
|
10.09%
$132,568.35
|
-3.80%
-$52,954.56
|
|
| $1,621,720.72 |
29.81%
$372,459.32
|
23.46%
$308,147.62
|
-12.14%
-$175,579.27
|
|
| $1,738,800.77 |
39.19%
$489,539.37
|
32.37%
$425,227.67
|
-7.22%
-$117,080.05
|
E
Engineer's Estimate
$1,249,261.40
1
Awarded
$1,313,573.10
Over/Under Est:
5.15%
$64,311.70
$1,393,186.89
Over/Under Est:
11.52%
$143,925.49
Amt Left:
6.06%
$79,613.79
$1,446,141.45
Over/Under Est:
15.76%
$196,880.05
Amt Left:
10.09%
$132,568.35
Delta:
-3.80%
-$52,954.56
$1,621,720.72
Over/Under Est:
29.81%
$372,459.32
Amt Left:
23.46%
$308,147.62
Delta:
-12.14%
-$175,579.27
$1,738,800.77
Over/Under Est:
39.19%
$489,539.37
Amt Left:
32.37%
$425,227.67
Delta:
-7.22%
-$117,080.05
| Subcontractor | Percentage | Amount |
|---|---|---|
| VALLEY STRIPING CORP. | 10.70% | $140,552.32 |
| R&T CONSTRUCTION | 0.80% | $10,508.58 |
| Total: | 11.50% | $151,060.90 |