HIDALGO FM 907 (1586-01-076)

Items: 131

County: HIDALGO
Length: N/A
Highway: FM 907
District: PHARR
Control Number: 1586-01-076
DBE Goal: N/A
Project: STP 2019(893)
Guaranty: N/A
Time: 365 WORKING DAYS
Engineer's Estimate: $6,095,617.83
Date: 05/08/2019 (7 years ago)
Contract Number: N/A
Type: REHABILITATE ROADWAY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (3)
E
Engineer's Estimate
$6,095,617.83
$6,912,455.00
Over/Under Est: 13.4% $816,837.17
$7,180,440.76
Over/Under Est: 17.8% $1,084,822.93
Amt Left: 3.88% $267,985.76
Over/Under Est: 28.64% $1,745,814.38
Amt Left: 13.44% $928,977.21
Delta: -9.21% -$660,991.45

Bid Items & Bid Tabulations

131 Total 0 of 131
HIDALGO  |  FM 907  |  PHARR  |  1586-01-076  |  05/08/2019  |  $6,095,617.83  |  STP 2019(893)  |  REHAB ROADWAY  |  365 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
TEXAS CORDIA CONSTRUCTION, LLC
FOREMOST PAVING, INC.
REIM CONSTRUCTION, INC.
PREPARING ROW
STA 122.000 $600.000 $225.000 $4,650.000 $973.000
REMOVING CONC (SIDEWALKS)
SY 1,930.000 $8.000 $2.000 $15.000 $11.250
REMOVING CONC (DRIVEWAYS)
SY 854.000 $9.000 $2.000 $17.000 $11.750
REMOVING CONC (CURB AND GUTTER)
LF 16,675.000 $5.000 $2.000 $4.000 $2.750
REMOVE CONC (GUTTER)
LF 968.000 $7.000 $2.000 $4.000 $5.550
REMOVING CONC (WHEELCHAIR RAMP)
SY 500.000 $14.000 $2.000 $12.000 $10.500
REMOVING STAB BASE AND ASPH PAV(15")
SY 53,295.000 $4.500 $4.000 $5.250 $7.000
FURNISHING AND PLACING TOPSOIL
CY 50.000 $28.000 $25.000 $30.000 $37.000
CELL FBR MLCH SEED(PERM)(URBAN)(CLAY)
SY 13,044.000 $0.350 $0.450 $0.350 $0.470
CELL FBR MLCH SEED(TEMP)(WARM)
SY 13,044.000 $0.270 $0.450 $0.350 $0.470
VEGETATIVE WATERING
MG 239.000 $20.000 $33.000 $25.000 $37.000
SPRINKLING (DUST CONTROL)
MG 488.000 $11.000 $10.000 $1.000 $1.250
FL BS (RDWY DEL)(TY E GR 4)(FNAL POS)
CY 17,764.000 $22.000 $25.000 $20.250 $29.500
LIME TRT (EXST MATL) (12")
SY 56,929.000 $1.750 $1.000 $3.000 $2.800
LIME (HYD, COM OR QK)(SLURRY)
TON 1,665.000 $140.000 $240.000 $128.000 $173.000
CEMENT
TON 589.000 $150.000 $175.000 $148.000 $178.000
CEMENT TREAT (NEW BASE)(12")
SY 53,294.000 $1.750 $1.000 $3.500 $2.800
PRIME COAT (MC-30)
GAL 17,128.000 $4.000 $4.000 $3.750 $5.500
ASPH (TIER II)
GAL 25,694.000 $4.000 $4.000 $5.000 $4.650
AGGR (TY-D GR-4P)(SAC-B)
CY 713.000 $40.000 $82.000 $35.000 $43.250
SUPERPAVE MIXTURES SP-D SAC-A PG76-22
TON 14,253.000 $81.000 $110.000 $88.000 $101.000
PLANE ASPH CONC PAV (1.5")
SY 1,429.000 $1.500 $10.000 $5.000 $4.950
PLANE ASPH CONC PAV (3")
SY 33,282.000 $2.000 $2.000 $2.650 $2.450
CEM STABIL BKFL
CY 6,743.000 $51.000 $35.000 $50.000 $63.500
CUT & RESTORE ASPH PAVING
SY 116.000 $50.000 $60.000 $50.000 $61.500
STRUCT EXCAV (SPECIAL)
CY 5,361.000 $36.000 $43.000 $45.000 $65.500
TRENCH EXCAVATION PROTECTION
LF 5,331.000 $2.500 $4.000 $1.750 $3.350
RC PIPE (CL III)(18 IN)(SPL)
LF 152.000 $34.000 $35.000 $35.000 $44.250
RC PIPE (CL III)(42 IN)(SPL)
LF 629.000 $100.000 $125.000 $115.000 $127.000
RC PIPE (CL III)(48 IN)(SPL)
LF 1,724.000 $116.000 $154.000 $123.000 $147.000
RC PIPE (CL III)(54 IN)(SPL)
LF 2,124.000 $138.000 $181.000 $170.000 $175.000
RC PIPE (CL III)(60 IN)(SPL)
LF 702.000 $167.000 $230.000 $216.000 $210.000
INLET (COMPL)(PCU)(4FT)(NONE)
EA 7.000 $3,500.000 $5,560.000 $5,750.000 $5,680.000
INLET (COMPL)(PCU)(4FT)(BOTH)
EA 1.000 $4,600.000 $7,000.000 $6,750.000 $7,310.000
INLET (COMPL)(PCU)(5FT)(NONE)
EA 9.000 $3,000.000 $5,600.000 $5,875.000 $5,730.000
INLET (COMPL)(PCU)(5FT)(BOTH)
EA 2.000 $4,800.000 $7,000.000 $7,000.000 $7,030.000
REMOV STR (INLET)
EA 19.000 $450.000 $700.000 $350.000 $303.000
REMOV STR (PIPE)
LF 5,331.000 $8.000 $5.000 $21.000 $15.750
MOBILIZATION
LS 1.000 $505,000.000 $200,000.000 $600,000.000 $565,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 24.000 $3,500.000 $3,200.000 $3,500.000 $3,330.000
CONSTRUCTION EXITS (INSTALL) (TY 2)
SY 778.000 $20.000 $9.000 $20.000 $14.500
CONSTRUCTION EXITS (REMOVE)
SY 778.000 $8.000 $4.000 $8.000 $8.150
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 1,728.000 $3.000 $6.000 $4.500 $5.850
BIODEG EROSN CONT LOGS (REMOVE)
LF 2,928.000 $0.750 $0.500 $0.500 $0.600
BIODEG EROSN CONT LOGS (INSTL) (6")
LF 1,200.000 $1.000 $5.000 $4.000 $5.200
PORT CTB (FUR & INST)(LOW PROF)(TY 1)
LF 3,940.000 $22.000 $115.000 $20.000 $50.500
PORT CTB (FUR & INST)(LOW PROF)(TY 2)
LF 1,440.000 $30.000 $98.000 $20.000 $50.000
PORT CTB (MOVE)(LOW PROF)(TY 1)
LF 4,440.000 $5.000 $8.000 $6.000 $7.600
PORT CTB (MOVE)(LOW PROF)(TY 2)
LF 1,360.000 $8.000 $8.000 $6.000 $7.600
PORT CTB (REMOVE)(LOW PROF)(TY 1)
LF 3,940.000 $4.000 $9.000 $7.000 $11.000
PORT CTB (REMOVE)(LOW PROF)(TY 2)
LF 1,440.000 $5.000 $9.000 $7.000 $11.000
CONC CURB & GUTTER (TY B) (MOUNTABLE)
LF 9,540.000 $10.000 $12.000 $10.000 $14.250
CONC CURB & GUTTER(VALLEY GUTTER)(48")
LF 635.000 $20.000 $31.000 $35.000 $49.250
CONC. CURB TY A (BARRIER)
LF 7,350.000 $9.000 $6.000 $11.500 $9.850
DRIVEWAYS (CONC)
SY 854.000 $48.000 $53.000 $52.500 $48.000
DRIVEWAYS (ACP)
SY 4,272.000 $27.000 $20.000 $25.000 $30.750
CONC SIDEWALKS (4")
SY 2,622.000 $35.000 $28.000 $27.000 $37.250
CURB RAMPS (TY 1)
EA 20.000 $1,000.000 $1,040.000 $1,100.000 $1,100.000
CURB RAMPS (TY 2)
EA 1.000 $1,400.000 $1,040.000 $1,250.000 $1,120.000
CURB RAMPS (TY 10)
EA 29.000 $1,300.000 $1,040.000 $1,025.000 $1,210.000
REPLACE LUMINAIRE W/LED (250W EQ)
EA 12.000 $900.000 $825.000 $675.000 $765.000
CONDT (PVC) (SCH 40) (1")
LF 487.000 $20.000 $10.000 $8.000 $34.500
CONDT (PVC) (SCH 40) (2")
LF 25.000 $7.000 $18.000 $15.000 $27.250
CONDT (PVC) (SCH 40) (4")
LF 35.000 $18.000 $22.000 $18.000 $32.000
CONDT (PVC) (SCH 80) (4") (BORE)
LF 387.000 $24.000 $40.000 $33.000 $59.000
TRAY CABLE (4 CONDR) (12 AWG)
LF 30.000 $2.250 $2.900 $2.500 $4.300
GROUND BOX TY A (122311)W/APRON
EA 1.000 $800.000 $1,000.000 $950.000 $1,850.000
RELOCATE SM RD SN SUP&AM TY S80
EA 1.000 $550.000 $650.000 $500.000 $494.000
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 3,677.000 $0.300 $0.650 $0.500 $0.630
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 6,495.000 $0.300 $0.650 $0.500 $0.630
WK ZN PAV MRK REMOV (REFL) TY I-C
EA 418.000 $3.000 $6.000 $5.000 $6.150
WK ZN PAV MRK REMOV (REFL) TY II-A-A
EA 1,539.000 $3.000 $5.000 $4.000 $4.950
WK ZN PAV MRK REMOV (W)4"(BRK)
LF 6,381.000 $0.800 $0.700 $0.600 $0.750
WK ZN PAV MRK REMOV (W)4"(DOT)
LF 72.000 $1.000 $0.800 $0.700 $0.870
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 18,911.000 $0.600 $0.700 $0.600 $0.750
WK ZN PAV MRK REMOV (W)8"(SLD)
LF 2,044.000 $1.250 $1.850 $1.500 $1.800
WK ZN PAV MRK REMOV (W)12"(SLD)
LF 2,776.000 $3.000 $3.750 $3.000 $3.650
WK ZN PAV MRK REMOV (W)24"(SLD)
LF 1,029.000 $7.000 $7.500 $6.000 $7.350
WK ZN PAV MRK REMOV (W)(ARROW)
EA 28.000 $90.000 $200.000 $165.000 $204.000
WK ZN PAV MRK REMOV (W)(DBL ARROW)
EA 1.000 $225.000 $350.000 $285.000 $352.000
WK ZN PAV MRK REMOV (W)(RR XING)
EA 2.000 $600.000 $700.000 $575.000 $710.000
WK ZN PAV MRK REMOV (W)(WORD)
EA 18.000 $200.000 $300.000 $250.000 $309.000
WK ZN PAV MRK REMOV (Y)4"(BRK)
LF 7,150.000 $0.700 $0.850 $0.700 $0.850
WK ZN PAV MRK REMOV (Y)4"(DOT)
LF 558.000 $1.300 $0.850 $0.700 $0.850
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 55,497.000 $0.600 $0.750 $0.650 $0.850
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 2,814.000 $1.000 $5.000 $1.000 $0.950
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 5,342.000 $0.750 $5.000 $1.000 $0.950
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 1,232.000 $1.000 $1.000 $0.900 $1.100
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
LF 2,560.000 $2.500 $1.850 $1.500 $1.800
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 793.000 $5.500 $5.750 $4.750 $5.850
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 5,421.000 $0.500 $0.500 $0.450 $0.500
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 1,370.000 $0.300 $0.500 $0.450 $0.550
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 4,351.000 $0.300 $0.500 $0.450 $0.500
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 21,913.000 $0.300 $0.500 $0.420 $0.500
PREFAB PAV MRK TY C (W) (ARROW)
EA 35.000 $200.000 $210.000 $185.000 $228.000
PREFAB PAV MRK TY C (W) (DBL ARROW)
EA 1.000 $375.000 $340.000 $275.000 $339.000
PREFAB PAV MRK TY C (W) (WORD)
EA 9.000 $250.000 $350.000 $285.000 $352.000
PREFAB PAV MRK TY C (W) (RR XING)
EA 2.000 $500.000 $200.000 $575.000 $710.000
REFL PAV MRKR TY I-C
EA 353.000 $4.000 $4.000 $3.500 $4.300
REFL PAV MRKR TY II-A-A
EA 661.000 $3.000 $4.000 $3.500 $4.300
ELIM EXT PAV MRK & MRKS (4")
LF 16,933.000 $0.500 $0.550 $0.500 $0.600
ELIM EXT PAV MRK & MRKS (8")
LF 661.000 $0.750 $1.150 $1.000 $1.250
ELIM EXT PAV MRK & MRKS (12")
LF 883.000 $1.750 $1.750 $1.500 $1.800
ELIM EXT PAV MRK & MRKS (24")
LF 452.000 $3.500 $3.750 $3.000 $3.750
ELIM EXT PAV MRK & MRKS (ARROW)
EA 32.000 $50.000 $9.000 $7.500 $9.250
ELIM EXT PAV MRK & MRKS (DBL ARROW)
EA 1.000 $60.000 $15.000 $12.000 $14.750
ELIM EXT PAV MRK & MRKS (WORD)
EA 9.000 $55.000 $15.000 $12.000 $14.750
ELIM EXT PAV MRK & MRKS (RR XING)
EA 2.000 $75.000 $25.000 $20.000 $24.750
TEMP TRAF SIGNALS
EA 10.000 $8,800.000 $8,100.000 $6,500.000 $6,420.000
VEH SIG SEC (12")LED(GRN)
EA 38.000 $230.000 $285.000 $230.000 $346.000
VEH SIG SEC (12")LED(GRN ARW)
EA 14.000 $230.000 $285.000 $230.000 $346.000
VEH SIG SEC (12")LED(YEL)
EA 40.000 $220.000 $285.000 $230.000 $346.000
VEH SIG SEC (12")LED(YEL ARW)
EA 14.000 $230.000 $285.000 $230.000 $346.000
VEH SIG SEC (12")LED(RED)
EA 42.000 $210.000 $285.000 $230.000 $346.000
VEH SIG SEC (12")LED(RED ARW)
EA 4.000 $220.000 $285.000 $230.000 $309.000
PED SIG SEC (LED)(COUNTDOWN)
EA 24.000 $600.000 $600.000 $500.000 $938.000
BACK PLATE (12")(3 SEC)
EA 28.000 $70.000 $90.000 $75.000 $123.000
BACK PLATE (12")(4 SEC)
EA 8.000 $80.000 $100.000 $85.000 $136.000
BACK PLATE (12")(5 SEC)
EA 6.000 $90.000 $115.000 $100.000 $142.000
TRF SIG CBL (TY A)(12 AWG)(2 CONDR)
LF 3,426.000 $1.000 $1.850 $1.500 $3.100
TRF SIG CBL (TY A)(12 AWG)(5 CONDR)
LF 30.000 $2.250 $6.050 $5.000 $3.850
TRF SIG CBL (TY A)(12 AWG)(7 CONDR)
LF 30.000 $2.250 $6.300 $5.000 $4.450
PED DETECT PUSH BUTTON (APS)
EA 24.000 $700.000 $900.000 $750.000 $1,110.000
PED DETECTOR CONTROLLER UNIT
EA 3.000 $2,600.000 $5,400.000 $4,400.000 $4,070.000
VEH LP DETECT (SAWCUT)
LF 4,476.000 $13.000 $10.000 $8.000 $15.500
REMOVE TRAFFIC SIGNAL
EA 5.000 $1,400.000 $2,500.000 $2,100.000 $1,360.000
STORM SEWER CLEANING (PIPE)(37"-42"DIA)
LF 1,000.000 $20.000 $11.000 $16.000 $33.750
GEOGRID BASE REINFORCEMENT (TY II)
SY 110,223.000 $1.500 $1.250 $1.500 $1.550
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $8,000.000 $4,300.000 $3,500.000 $1,540.000
TMA (STATIONARY)
EA 2.000 $12,000.000 $6,700.000 $3,500.000 $4,320.000
TMA (MOBILE OPERATION)
DAY 166.000 $230.000 $225.000 $177.000 $123.000
Totals: $6,095,617.830 $6,912,455.000 $7,180,440.760 $7,841,432.210