HIDALGO VARIOUS (0921-00-091)

Items: 65

County: HIDALGO
Length: 0.0000 MILES
Highway: VARIOUS
District: PHARR
Control Number: 0921-00-091
DBE Goal: 0.0%
Project: F 2026(760)
Guaranty: $48,000.00
Time: 153 WORKING DAYS
Engineer's Estimate: $2,404,056.00
Date: 07/02/2026 1:00 PM CDT (16 days ago)
Contract Number: 7263205
Type: CONSTRUCT PEDESTRIAN INFRASTRUCTURE
Project ID: A00183413
Contract Type: FEDERAL
Project Description: ADA REMEDIATION AND NEW CONSTRUCTION
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
JESUS NORIEGA
ARLEENE GARCIA
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (8)
E
Engineer's Estimate
$2,404,056.00
$1,942,734.90
Over/Under Est: -19.19% -$461,321.10
$1,944,879.37
Over/Under Est: -19.1% -$459,176.63
Amt Left: 0.11% $2,144.47
$2,197,522.00
Over/Under Est: -8.59% -$206,534.00
Amt Left: 13.11% $254,787.10
Delta: -12.99% -$252,642.63
$2,230,825.10
Over/Under Est: -7.21% -$173,230.90
Amt Left: 14.83% $288,090.20
Delta: -1.52% -$33,303.10
Over/Under Est: -5.13% -$123,247.83
Amt Left: 17.4% $338,073.27
Delta: -2.24% -$49,983.07
$2,349,081.59
Over/Under Est: -2.29% -$54,974.41
Amt Left: 20.92% $406,346.69
Delta: -2.99% -$68,273.42
Over/Under Est: 1.04% $24,972.90
Amt Left: 25.03% $486,294.00
Delta: -3.40% -$79,947.31
Over/Under Est: 21.83% $524,755.00
Amt Left: 50.76% $986,076.10
Delta: -20.58% -$499,782.10

Bid Items & Bid Tabulations

65 Total 0 of 65
HIDALGO  |  VARIOUS  |  PHARR  |  0921-00-091  |  07/02/2026 1:00 PM CDT  |  $2,404,056.00  |  F 2026(760)  |  CONSTRUCT PEDESTRIAN INFRASTRUCT  |  153 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
CASTILLO ARANDA LLC
3LW CIVIL LLC
ARTILLERY L.L.C.
EARTHWORKS ENTERPRISE
GO UNDERGROUND, LIMITED LIABILITY COMPANY
STX CIVIL
LUCANIA CONTRACTORS LLC
TEXAS CORDIA CONSTRUCTION, LLC
PREPARING ROW
AC 1.000 $58,000.000 $100,000.000 $12,114.594 $10,000.000 $32,000.000 $22,000.000 $7,500.000 $6,000.000 $23,000.000
REMOV CONC (RIPRAP)
SY 10.000 $35.000 $10.000 $25.053 $18.000 $60.000 $100.000 $15.000 $45.000 $133.000
REMOV CONC (DRIVEWAYS)
SY 2,878.000 $20.000 $10.000 $9.543 $18.000 $35.000 $12.000 $20.000 $18.000 $13.000
REMOV CONC (SIDEWALK, RAMP OR SUP)
SY 686.000 $20.000 $10.000 $11.838 $18.000 $29.000 $12.000 $16.000 $18.000 $14.000
REMOV CONC (CURB OR CURB & GUTTER)
LF 9,121.000 $15.000 $3.000 $4.642 $9.000 $7.000 $12.000 $6.000 $9.000 $6.000
RMV (0"-12") TRT/UNTRT BASE & ASPH PAV
SY 1,898.000 $8.000 $20.000 $13.003 $18.000 $16.000 $6.000 $8.000 $18.000 $17.000
FURN & PLACE TOPSOIL (4")
SY 3,381.000 $3.000 $4.000 $17.751 $7.000 $31.000 $12.000 $4.000 $6.000 $20.000
BLOCK SODDING
SY 3,381.000 $10.000 $7.000 $9.900 $10.000 $9.000 $10.270 $6.000 $10.000 $9.000
VEGETATIVE WATERING
TGL 62.300 $50.000 $75.000 $210.000 $50.000 $132.000 $400.000 $55.000 $10.000 $60.000
RDSIDE AMENITY (WHEEL STOP)
EA 22.000 $300.000 $250.000 $451.792 $200.000 $106.000 $330.000 $385.000 $250.000 $130.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(10")
SY 400.000 $76.000 $115.000 $155.506 $100.000 $126.000 $64.000 $75.000 $125.000 $72.000
CL A CONC (COLLAR)
EA 2.000 $1,700.000 $5,500.000 $528.172 $2,500.000 $1,650.000 $7,000.000 $900.000 $2,300.000 $4,500.000
CL C CONC (MISC)
CY 2.900 $1,000.000 $850.000 $771.905 $750.000 $371.000 $200.000 $1,000.000 $1,000.000 $1,700.000
RIPRAP (CONC)(6 IN)
CY 3.200 $550.000 $525.000 $582.161 $1,000.000 $583.000 $700.000 $1,000.000 $1,000.000 $1,200.000
RC PIPE (CL III)(18 IN)
LF 30.000 $100.000 $160.000 $92.758 $120.000 $91.000 $83.000 $200.000 $200.000 $200.000
INLET (COMPL)(PCO)(3FT)(LEFT)
EA 1.000 $7,000.000 $5,500.000 $10,132.288 $6,000.000 $6,900.000 $4,400.000 $8,500.000 $7,500.000 $9,630.000
INLET (COMPL)(PSL)(RC)(3FTX3FT)
EA 1.000 $6,500.000 $4,500.000 $6,085.460 $5,000.000 $6,900.000 $4,400.000 $7,500.000 $6,000.000 $5,620.000
GRATE & FRAME
EA 3.000 $2,000.000 $2,500.000 $6,979.820 $5,000.000 $3,900.000 $4,400.000 $1,850.000 $5,500.000 $5,860.000
ADJUSTING MANHOLES (WATER VALVE BOX)
EA 20.000 $700.000 $1,200.000 $666.104 $300.000 $349.000 $1,200.000 $500.000 $1,000.000 $3,680.000
ADJUSTING MANHOLES (WATER METER)
EA 8.000 $800.000 $500.000 $987.430 $300.000 $249.000 $1,200.000 $650.000 $900.000 $6,840.000
REMOV STR (INLET)
EA 1.000 $1,000.000 $500.000 $451.972 $1,000.000 $2,300.000 $640.000 $2,055.000 $900.000 $1,500.000
MOBILIZATION
LS 1.000 $220,000.000 $130,000.000 $196,996.550 $100,000.000 $250,000.000 $192,500.000 $185,781.190 $238,000.000 $250,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 10.000 $5,000.000 $8,500.000 $2,623.756 $4,000.000 $1,250.000 $8,000.000 $5,000.000 $1,500.000 $500.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $9,000.000 $15,000.000 $1,800.000 $15,000.000 $18,800.000 $5,200.000 $7,200.000 $10,000.000 $200.000
TMA (STATIONARY)
DAY 150.000 $200.000 $200.000 $222.000 $500.000 $225.000 $250.000 $150.000 $200.000 $50.000
TMA (MOBILE OPERATION)
DAY 3.000 $205.000 $1,500.000 $396.432 $1,000.000 $360.000 $250.000 $200.000 $500.000 $60.000
SANDBAGS FOR EROSION CONTROL
EA 1,500.000 $9.000 $18.000 $1.500 $10.000 $7.000 $5.000 $10.000 $4.000 $6.000
BIODEG EROSN CONT LOGS (INSTL) (6")
LF 5,000.000 $5.000 $8.000 $6.300 $7.000 $7.500 $6.000 $6.000 $7.000 $6.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 5,000.000 $1.250 $1.000 $1.200 $2.000 $1.500 $0.010 $1.000 $1.500 $1.000
CONC CURB & GUTTER (TY I)
LF 231.000 $30.000 $15.000 $32.267 $40.000 $34.000 $17.660 $20.000 $40.000 $56.000
CONC CURB & GUTTER (TY II)
LF 8,942.000 $40.000 $12.000 $28.221 $45.000 $37.000 $17.660 $30.000 $38.000 $29.000
CONC CURB (SLOTTED)
LF 132.000 $40.000 $15.000 $44.438 $50.000 $34.000 $17.660 $65.000 $65.000 $241.000
CONCRETE C&G (VALLEY GUTTER)
LF 120.000 $70.000 $30.000 $56.894 $60.000 $62.000 $24.000 $80.000 $70.000 $109.000
CONC CURB (RIBBON)
LF 274.000 $30.000 $65.000 $30.092 $50.000 $40.000 $17.660 $50.000 $30.000 $80.000
DRIVEWAYS (CONC)
SY 4,783.000 $110.000 $80.000 $70.732 $90.000 $88.000 $133.000 $125.000 $82.000 $103.000
DRIVEWAYS (ACP)
SY 260.000 $80.000 $80.000 $76.047 $70.000 $52.000 $65.000 $70.000 $60.000 $64.000
CONC SIDEWALKS (4")
SY 3,121.000 $70.000 $70.000 $73.604 $72.000 $66.000 $65.000 $100.000 $73.000 $87.000
CONC SIDEWALKS (6")
SY 76.000 $90.000 $85.000 $87.930 $90.000 $79.000 $38.680 $115.000 $75.000 $125.000
CURB RAMPS (TY 1)
SY 24.000 $260.000 $145.000 $180.695 $120.000 $123.000 $300.000 $160.000 $140.000 $1,030.000
CURB RAMPS (TY 2)
SY 79.000 $260.000 $145.000 $127.936 $120.000 $123.000 $300.000 $160.000 $140.000 $946.000
CURB RAMPS (TY 3)
SY 315.000 $260.000 $145.000 $134.733 $120.000 $123.000 $300.000 $160.000 $140.000 $932.000
CURB RAMPS (TY 7)
SY 15.000 $260.000 $145.000 $169.367 $120.000 $128.000 $400.000 $160.000 $140.000 $930.000
CURB RAMPS (TY 10)
SY 31.000 $260.000 $145.000 $150.273 $120.000 $128.000 $400.000 $160.000 $140.000 $993.000
CONC SIDEWALKS (SPECIAL)
SY 1,905.000 $140.000 $160.000 $106.666 $140.000 $100.000 $133.000 $155.000 $280.000 $248.000
GROUND BOX TY D (162922)
EA 8.000 $1,500.000 $1,550.000 $2,240.739 $1,200.000 $1,660.000 $1,420.000 $1,500.000 $1,700.000 $1,750.000
REMOVE GROUND BOX
EA 7.000 $300.000 $500.000 $837.669 $300.000 $567.000 $485.000 $300.000 $580.000 $599.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 1.000 $1,000.000 $750.000 $1,440.000 $1,000.000 $1,400.000 $2,000.000 $1,100.000 $1,000.000 $949.000
RELOCATE SM RD SN SUP&AM TY S80
EA 20.000 $750.000 $300.000 $1,320.000 $300.000 $1,115.000 $1,100.000 $1,000.000 $600.000 $942.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 36.000 $1.000 $3.000 $4.800 $5.000 $5.500 $4.000 $4.800 $5.750 $4.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 1,599.000 $5.000 $9.000 $14.400 $14.000 $10.000 $12.000 $8.800 $10.500 $13.000
RE PROFILE PM TY I(W)6"(SLD)(100MIL)
LF 110.000 $1.000 $26.000 $12.000 $12.000 $3.000 $10.000 $2.800 $3.500 $11.000
RE PROFILE PM TY I(Y)6"(SLD)(100MIL)
LF 12.000 $1.000 $55.000 $12.000 $12.000 $3.000 $10.000 $2.800 $3.500 $11.000
PAVEMENT SLER 6"
LF 122.000 $1.000 $1.200 $1.200 $2.000 $1.000 $9.840 $0.650 $0.750 $1.000
PAVEMENT SLER 8"
LF 36.000 $1.000 $1.500 $1.800 $2.500 $1.000 $1.500 $1.000 $1.250 $2.000
PAVEMENT SLER 24"
LF 1,599.000 $2.000 $2.000 $5.400 $7.000 $2.000 $4.500 $20.000 $2.500 $5.000
PAVEMENT SLER (ARROW)
EA 26.000 $30.000 $20.000 $96.000 $90.000 $35.000 $80.000 $30.000 $35.000 $87.000
PREFAB PM TY B (W)(ARROW)
EA 26.000 $500.000 $850.000 $240.000 $210.000 $328.000 $200.000 $280.000 $335.000 $216.000
ELIM EXT PM & MRKS (4")
LF 75.000 $1.000 $3.000 $1.200 $2.000 $1.000 $1.000 $1.000 $1.200 $1.000
ELIM EXT PM & MRKS (8")
LF 66.000 $1.000 $4.000 $2.400 $3.000 $2.000 $2.000 $2.000 $2.400 $2.000
ELIM EXT PM & MRKS (12")
LF 1,532.000 $2.000 $4.000 $3.600 $4.000 $2.000 $3.000 $2.500 $3.000 $3.000
ELIM EXT PM & MRKS (24")
LF 395.000 $3.000 $8.000 $4.800 $5.000 $5.500 $4.000 $5.000 $6.000 $4.000
ELIM EXT PM & MRKS (ARROW)
EA 2.000 $100.000 $25.000 $108.000 $100.000 $187.000 $90.000 $160.000 $192.000 $97.000
TRF SIG CBL (TY C)(14 AWG)(2 CONDR)
LF 5,910.000 $1.500 $2.000 $2.175 $3.000 $1.750 $1.650 $3.000 $2.000 $2.000
REMOVE PED PUSH BUTTON POST ASSEM
EA 18.000 $150.000 $40.000 $318.569 $100.000 $40.000 $35.000 $250.000 $42.000 $43.000
PED DETECT PUSH BUTTON (STANDARD)
EA 18.000 $300.000 $400.000 $1,139.076 $700.000 $446.000 $380.000 $1,200.000 $456.000 $469.000
Totals: $2,404,056.000 $1,942,734.900 $1,944,879.382 $2,197,522.000 $2,230,825.100 $2,280,808.170 $2,349,081.590 $2,429,028.900 $2,928,811.000
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $2,000.00
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) $2,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $2,000.00
Total: $6,000.00