Job Info for 0528-01-121

County: HIDALGO Highway: SH 107 Date: 11/02/2022 (2 years ago) Engineer's Estimate: $6,258,578 Control Number: 0528-01-121
Project: C 528-1-121 District: PHARR Time: 60 WORKING DAYS Type: PREVENTIVE MAINTENANCE
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9
Plans: Plans | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $6,258,578.05
IOC COMPANY LLC   $5,739,476.01 1
-8.29% | -$519,102.04
FOREMOST PAVING, INC.   $5,872,238.75 2
-6.17% | -$386,339.30
2.31% | $132,762.74
TEXAS CORDIA CONSTRUCTION, LLC   $7,038,634.50 3
12.46% | $780,056.45
22.64% | $1,299,158.49
19.86% | $1,166,395.75

Bid Items

Items: 55, 0 filtered
HIDALGO SH 107  |  PHARR  |  0528-01-121  |  11/02/2022  |  $6,258,578  |  C 528-1-121  |  PREVENT MAINT  |  60 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate IOC COMPANY LLC FOREMOST PAVING, INC. TEXAS CORDIA CONSTRUCTION, LLC
104 6054 REMOVING CONCRETE(MOW STRIP) LF 1,912.000 $8.000 $8.000 $9.000 $6.000
134 6006 BACKFILL (TY A) LF 7,341.000 $2.100 $3.000 $3.000 $2.000
351 6008 FLEXIBLE PAVEMENT STRUCTURE REPAIR(12") SY 18,708.000 $65.000 $21.000 $32.000 $47.000
354 6041 PLANE ASPH CONC PAV (1.5") SY 274,955.000 $1.900 $1.500 $1.550 $1.250
354 6139 PLANE ASPH CONC PAV (1.5" TO 3") SY 31,462.000 $2.500 $2.500 $2.500 $2.000
432 6045 RIPRAP (MOW STRIP)(4 IN) CY 386.000 $500.000 $525.000 $500.000 $708.000
500 6001 MOBILIZATION LS 1.000 $300,000.000 $500,000.000 $408,000.000 $500,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 3.000 $5,000.000 $2,750.000 $13,250.000 $38,000.000
506 6041 BIODEG EROSN CONT LOGS (INSTL) (12") LF 1,428.000 $5.000 $1.000 $5.000 $6.000
506 6043 BIODEG EROSN CONT LOGS (REMOVE) LF 1,428.000 $1.000 $0.500 $2.000 $1.000
540 6001 MTL W-BEAM GD FEN (TIM POST) LF 7,341.000 $27.000 $23.150 $24.000 $26.000
540 6006 MTL BEAM GD FEN TRANS (THRIE-BEAM) EA 17.000 $2,500.000 $2,305.000 $1,900.000 $1,958.000
542 6001 REMOVE METAL BEAM GUARD FENCE LF 7,681.000 $3.250 $1.500 $2.000 $2.000
542 6002 REMOVE TERMINAL ANCHOR SECTION EA 8.000 $250.000 $175.000 $120.000 $129.000
542 6003 REMOVE DOWNSTREAM ANCHOR TERMINAL EA 1.000 $260.000 $175.000 $120.000 $129.000
542 6004 RM MTL BM GD FENCE TRANS (THRIE-BEAM) EA 10.000 $250.000 $175.000 $200.000 $193.000
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 18.000 $3,400.000 $3,325.000 $3,000.000 $3,202.000
544 6003 GUARDRAIL END TREATMENT (REMOVE) EA 10.000 $285.000 $175.000 $275.000 $290.000
545 6025 CRASH CUSHION ATTEN (INSTALL)(REACT)(N) EA 1.000 $10,000.000 $30,475.000 $31,700.000 $33,130.000
658 6060 REMOVE DELIN & OBJECT MARKER ASSMS EA 111.000 $25.000 $29.000 $10.000 $10.000
658 6061 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2 EA 295.000 $30.000 $40.220 $23.000 $24.000
662 6109 WK ZN PAV MRK SHT TERM (TAB)TY W EA 11,933.000 $1.000 $1.000 $1.000 $2.000
662 6111 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 EA 2,446.000 $1.500 $0.750 $1.000 $3.000
666 6030 REFL PAV MRK TY I (W)8"(DOT)(100MIL) LF 383.000 $2.000 $0.900 $1.300 $1.000
666 6036 REFL PAV MRK TY I (W)8"(SLD)(100MIL) LF 17,785.000 $1.100 $0.900 $1.000 $1.000
666 6042 REFL PAV MRK TY I (W)12"(SLD)(100MIL) LF 746.000 $3.500 $1.250 $3.600 $1.000
666 6048 REFL PAV MRK TY I (W)24"(SLD)(100MIL) LF 9,595.000 $8.000 $3.000 $3.000 $3.000
666 6214 REFL PAV MRK TY II (Y) 24" (SLD) LF 253.000 $2.900 $3.000 $3.000 $3.000
666 6300 RE PM W/RET REQ TY I (W)4"(BRK)(100MIL) LF 18,799.000 $0.450 $0.450 $0.450 $0.500
666 6303 RE PM W/RET REQ TY I (W)4"(SLD)(100MIL) LF 49,930.000 $0.450 $0.450 $0.450 $0.500
666 6312 RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL) LF 1,982.000 $0.450 $0.440 $0.450 $0.450
666 6315 RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL) LF 55,997.000 $0.500 $0.440 $0.450 $0.450
666 6342 REF PROF PAV MRK TY I(W)4"(SLD)(100MIL) LF 4,581.000 $0.500 $0.600 $0.600 $1.000
668 6005 PREFAB PAV MRK TY B (W)(4")(BRK)CNTST LF 368.000 $16.500 $11.000 $11.000 $11.000
668 6077 PREFAB PAV MRK TY C (W) (ARROW) EA 74.000 $225.000 $175.000 $175.000 $179.000
668 6085 PREFAB PAV MRK TY C (W) (WORD) EA 74.000 $265.000 $250.000 $250.000 $255.000
668 6089 PREFAB PAV MRK TY C (W) (RR XING) EA 8.000 $800.000 $450.000 $450.000 $459.000
668 6094 PREFAB PAV MRK TY C (W)(BIKE ARROW) EA 18.000 $100.000 $100.000 $100.000 $102.000
668 6096 PREFAB PAV MRK TY C (W)(BIKE SYMBOL) EA 18.000 $100.000 $225.000 $225.000 $230.000
672 6007 REFL PAV MRKR TY I-C EA 931.000 $4.000 $3.500 $3.600 $4.000
672 6009 REFL PAV MRKR TY II-A-A EA 1,330.000 $4.750 $3.500 $3.600 $4.000
672 6010 REFL PAV MRKR TY II-C-R EA 1,021.000 $4.750 $3.500 $3.600 $4.000
677 6001 ELIM EXT PAV MRK & MRKS (4") LF 6,299.000 $0.500 $0.300 $0.400 $0.300
677 6003 ELIM EXT PAV MRK & MRKS (8") LF 728.000 $1.000 $0.600 $0.650 $1.000
677 6005 ELIM EXT PAV MRK & MRKS (12") LF 2,156.000 $2.000 $0.900 $1.000 $1.000
677 6007 ELIM EXT PAV MRK & MRKS (24") LF 923.000 $4.000 $1.500 $1.500 $2.000
688 6004 VEH LP DETECT (SAWCUT) LF 13,430.000 $10.000 $11.500 $22.000 $12.000
3077 6065 SP MIXES SP-D SAC-A PG76-22 TON 26,199.000 $115.000 $126.850 $120.000 $150.000
3077 6075 TACK COAT GAL 21,685.000 $5.500 $3.500 $4.000 $6.000
6038 6001 MULTIPOLYMER PAV MRK (W)(4")(SLD) LF 1,604.000 $0.880 $8.000 $8.000 $8.000
6038 6002 MULTIPOLYMER PAV MRK (W)(4")(BRK) LF 728.000 $0.660 $10.000 $10.000 $10.000
6038 6007 MULTIPOLYMER PAV MRK (W)(8")(SLD) LF 368.000 $1.100 $15.000 $15.000 $15.000
6038 6014 MULTIPOLYMER PAV MRK (Y)(4")(SLD) LF 1,604.000 $1.000 $8.000 $8.000 $8.000
6185 6002 TMA (STATIONARY) DAY 60.000 $100.000 $0.100 $50.000 $150.000
6185 6005 TMA (MOBILE OPERATION) DAY 30.000 $150.000 $0.010 $0.010 $200.000
Totals: $6,258,578.05 $5,739,476.01 $5,872,238.75 $7,038,634.50