Bid Cobra

HENDERSON SH0019 (6470-97-001)

Items: 10

County: HENDERSON
Length: 0.0100 MILES
Highway: SH0019
District: TYLER
Control Number: 6470-97-001
DBE Goal: N/A
Project: BPM - 647097001
Guaranty: $9,000.00
Time: 240 CALENDAR DAYS
Engineer's Estimate: $431,410.00
Date: 09/17/2024 (1 year ago)
Contract Number: 9241001
Type: BRIDGE JOINT CLEANING AND SEALING
Project ID: A00211439
Project Description: FOR THE PURPOSE OF BRIDGE PREVENTATIVE MAINTENANCE CONSISTING OF CLEANING AND SEALING EXISTING BRIDGE JOINTS.
Mail/Deliver Bids To: N/A
DANNY HENDERSON
EDUARDO CASTANEDA
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (7)
E
Engineer's Estimate
$431,410.00
$460,630.00
Over/Under Est: 6.77% $29,220.00
Over/Under Est: 15.29% $65,950.00
Amt Left: 7.97% $36,730.00
Over/Under Est: 15.58% $67,205.00
Amt Left: 8.25% $37,985.00
Delta: -0.25% -$1,255.00
Over/Under Est: 17.94% $77,415.68
Amt Left: 10.46% $48,195.68
Delta: -2.05% -$10,210.68
Over/Under Est: 19.58% $84,460.00
Amt Left: 11.99% $55,240.00
Delta: -1.38% -$7,044.32
Over/Under Est: 35.85% $154,655.00
Amt Left: 27.23% $125,435.00
Delta: -13.61% -$70,195.00
Over/Under Est: 59.25% $255,615.00
Amt Left: 49.15% $226,395.00
Delta: -17.23% -$100,960.00

Bid Items & Bid Tabulations

10 Total 0 of 10
HENDERSON  |  SH0019  |  TYLER  |  6470-97-001  |  09/17/2024  |  $431,410.00  |  BPM - 647097001  |  BRIDGE JOINT CLEANING AND SEALING  |  240 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
B & MS CONSTRUCTION, INC.
RED BARON BUILDING COMPANY, LLC
SCR CIVIL CONSTRUCTION, LLC
12TWELVE ROAD AND BRIDGE LLC
ICOS MANAGEMENT, LLC
PATHFIELD INVESTMENTS LLC
CRACKSEAL OF TEXAS, LLC
CONC STR REPAIR (EPOXY MORTAR)
SF 50.000 $100.000 $185.000 $175.000 $100.000 $100.000 $100.000 $100.000 $143.000
CLEANING AND SEALING EXISTING JOINTS
LF 100.000 $40.000 $29.000 $30.000 $240.000 $50.000 $30.000 $50.000 $11.000
CLEANING AND SEALING EXIST JOINTS (CL3)
LF 2,155.000 $50.000 $42.000 $27.000 $50.000 $40.000 $20.000 $45.000 $31.000
CLEANING AND SEALING EXIST JOINTS (CL7)
LF 3,926.000 $40.000 $40.000 $30.000 $43.000 $50.000 $20.000 $45.000 $40.000
CLEANING EXISTING JOINTS
LF 100.000 $20.000 $30.000 $18.000 $10.000 $10.000 $10.000 $50.000 $11.000
MOBILIZATION (CALLOUT)
EA 2.000 $5,000.000 $850.000 $5,000.000 $24,900.000 $2,000.000 $1,000.000 $20,000.000 $50,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 73.000 $140.000 $210.000 $150.000 $45.000 $0.010 $100.000 $200.000 $10.000
TMA (STATIONARY)
DAY 45.000 $300.000 $300.000 $300.000 $120.000 $0.010 $7,000.000 $500.000 $10.000
BRIDGE JOINT REPAIR (HEADER)
LF 1,174.000 $100.000 $135.000 $230.000 $113.000 $180.000 $50.000 $180.000 $300.000
MAINTENANCE SPEED LIMIT SIGNING
DAY 45.000 $100.000 $198.000 $75.000 $20.000 $0.100 $50.000 $200.000 $10.000
Totals: $431,410.000 $460,630.000 $497,360.000 $498,615.000 $508,825.680 $515,870.000 $586,065.000 $687,025.000