Show Job Controls
Bid Cobra

HENDERSON FM 59 (0458-01-025)

Items: 92

County: HENDERSON
Length: N/A
Highway: FM 59
District: TYLER
Control Number: 0458-01-025
DBE Goal: N/A
Project: STP 2020(960)HES
Guaranty: N/A
Time: 165 WORKING DAYS
Engineer's Estimate: $1,754,398.70
Date: 07/09/2020 (5 years ago)
Contract Number: N/A
Type: GRADING,ACP BS&SURF, BS RPR, OCST,MBGF,SIGNS,PVMK
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (6)
E
Engineer's Estimate
$1,754,398.70
$1,730,130.35
Over/Under Est: -1.38% -$24,268.35
Over/Under Est: 14.81% $259,805.87
Amt Left: 16.42% $284,074.22
$2,047,149.09
Over/Under Est: 16.69% $292,750.39
Amt Left: 18.32% $317,018.74
Delta: -1.64% -$32,944.52
$2,115,880.14
Over/Under Est: 20.6% $361,481.44
Amt Left: 22.3% $385,749.79
Delta: -3.36% -$68,731.05
Over/Under Est: 21.98% $385,530.25
Amt Left: 23.69% $409,798.60
Delta: -1.14% -$24,048.81
Over/Under Est: 53.59% $940,232.55
Amt Left: 55.75% $964,500.90
Delta: -25.92% -$554,702.30

Bid Items & Bid Tabulations

92 Total 0 of 92
HENDERSON  |  FM 59  |  TYLER  |  0458-01-025  |  07/09/2020  |  $1,754,398.70  |  STP 2020(960)HES  |  GRADING,ACP BS&SURF, BS RPR, OCST,MB...  |  165 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
BIG CREEK CONSTRUCTION, LTD.
LONGVIEW BRIDGE AND ROAD, LTD.
A. L. HELMCAMP, INC.
REYNOLDS & KAY, LTD.
EAST TEXAS BRIDGE, INC.
TEXAS MATERIALS GROUP, INC.
PREPARING ROW
STA 2.000 $800.000 $5,000.000 $2,500.000 $3,200.000 $2,000.000 $10,000.000 $4,400.000
REMOVING CONC (RIPRAP)
SY 156.000 $12.000 $20.000 $30.000 $20.000 $14.000 $20.000 $30.000
REMOVING CONC (DRIVEWAYS)
SY 43.000 $20.000 $50.000 $30.000 $50.000 $14.000 $20.000 $40.000
SUBGRADE WIDENING (ORD COMP)
STA 69.470 $255.000 $850.000 $250.000 $300.000 $565.000 $500.000 $900.000
EMBANKMENT (VEHICLE)(ORD COMP)(TY C)
CY 918.000 $25.000 $20.000 $14.000 $25.000 $21.000 $25.000 $28.000
BACKFILL (TY A)
STA 99.140 $220.000 $250.000 $195.000 $200.000 $212.000 $300.000 $200.000
BLADING
STA 102.450 $300.000 $100.000 $190.000 $60.000 $145.000 $300.000 $175.000
FURNISHING AND PLACING TOPSOIL (4")
SY 1,759.000 $2.000 $3.000 $4.000 $4.000 $3.400 $3.000 $1.250
BROADCAST SEED (PERM) (RURAL) (SANDY)
SY 10,555.000 $0.200 $0.200 $0.150 $0.180 $0.150 $0.140 $0.130
BOND FBR MTRX SEED (PERM)(RURAL)(SAND)
SY 21,109.000 $0.850 $0.650 $0.780 $0.650 $0.750 $0.850 $0.800
BONDED FBR MTRX SEED (TEMP)(WARM)
SY 10,555.000 $0.650 $0.650 $0.650 $0.650 $0.600 $0.660 $0.650
BONDED FBR MTRX SEED (TEMP)(COOL)
SY 10,555.000 $0.650 $0.650 $0.600 $0.650 $0.580 $0.660 $0.650
VEGETATIVE WATERING
MG 581.000 $11.500 $12.000 $5.000 $15.000 $5.000 $12.000 $26.000
EMULS ASPH (EROSN CONT)(CSS-1)
GAL 50.000 $3.700 $10.000 $8.000 $8.000 $3.500 $10.000 $11.000
ASPH (AC-20XP, AC-10-2TR, OR AC-20-5TR)
GAL 13,298.000 $3.000 $3.250 $4.000 $2.900 $2.800 $4.500 $4.500
AGGR (TY-PD GR-3 OR TY-PL GR-3)
CY 317.000 $125.000 $135.000 $200.000 $120.000 $125.000 $125.000 $200.000
D-GR HMA(SQ) TY-D PG64-22
TON 474.000 $175.000 $110.000 $145.000 $150.000 $183.000 $185.000 $255.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
SY 1,000.000 $55.000 $45.000 $60.000 $70.000 $65.000 $55.000 $65.000
PLANE ASPH CONC PAV (0" TO 1 1/2")
SY 1,217.000 $2.500 $7.000 $3.750 $5.000 $8.000 $10.000 $7.000
CUT & RESTORING PAV
SY 30.000 $110.000 $100.000 $100.000 $135.000 $133.000 $120.000 $55.000
FLOWABLE BACKFILL
CY 87.000 $180.000 $175.000 $155.000 $155.000 $155.000 $350.000 $200.000
TRENCH EXCAVATION PROTECTION
LF 27.000 $15.000 $20.000 $24.000 $22.000 $5.000 $10.000 $10.500
TEMPORARY SPL SHORING
SF 688.000 $45.000 $40.000 $40.000 $45.000 $39.000 $40.000 $21.000
CL E CONC (SEAL SLAB)(NON-REINF)
CY 5.000 $250.000 $850.000 $550.000 $700.000 $725.000 $400.000 $1,100.000
RIPRAP (CONC)(5 IN)
CY 21.000 $480.000 $500.000 $550.000 $560.000 $725.000 $450.000 $650.000
RIPRAP (STONE COMMON)(DRY)(12 IN)
CY 92.000 $200.000 $150.000 $200.000 $145.000 $190.000 $150.000 $155.000
RIPRAP (MOW STRIP)(4 IN)
CY 66.000 $520.000 $500.000 $510.000 $550.000 $700.000 $425.000 $650.000
CONC BOX CULV (5 FT X 5 FT)
LF 40.000 $550.000 $550.000 $575.000 $500.000 $315.000 $700.000 $465.000
CONC BOX CULV (5 FT X 5 FT)(EXTEND)
LF 22.000 $525.000 $750.000 $700.000 $900.000 $825.000 $700.000 $655.000
RC PIPE (CL III)(18 IN)
LF 1,366.000 $38.000 $60.000 $46.000 $55.000 $44.000 $50.000 $60.000
RC PIPE (CL III)(24 IN)
LF 386.000 $50.000 $75.000 $60.000 $75.000 $60.000 $65.000 $75.000
WINGWALL (PW - 1) (HW=7 FT)
EA 3.000 $9,200.000 $17,500.000 $14,500.000 $20,000.000 $14,000.000 $12,000.000 $16,000.000
WINGWALL (SPL)
EA 1.000 $10,000.000 $25,000.000 $15,500.000 $20,000.000 $19,500.000 $15,000.000 $17,000.000
SET (TY I)(S=3 FT)(HW=2FT)(3:1)(C)
EA 1.000 $4,500.000 $6,500.000 $7,000.000 $6,200.000 $6,200.000 $4,000.000 $4,900.000
SET (TY I)(S=3 FT)(HW=2FT)(4:1)(C)
EA 1.000 $5,000.000 $7,000.000 $7,300.000 $6,200.000 $6,300.000 $4,000.000 $5,900.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 118.000 $540.000 $750.000 $700.000 $700.000 $725.000 $570.000 $1,000.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 22.000 $875.000 $1,000.000 $800.000 $950.000 $990.000 $900.000 $1,300.000
REMOV STR (BOX CULVERT)
LF 26.000 $50.000 $100.000 $250.000 $35.000 $55.000 $55.000 $120.000
REMOV STR (PIPE)
EA 45.000 $220.000 $550.000 $150.000 $500.000 $450.000 $500.000 $200.000
MOBILIZATION
LS 1.000 $130,000.000 $150,000.000 $190,000.000 $190,000.000 $235,000.000 $200,000.000 $267,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 11.000 $3,800.000 $2,500.000 $4,000.000 $8,500.000 $2,500.000 $8,000.000 $30,775.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 60.000 $28.000 $25.000 $30.000 $35.000 $30.000 $33.000 $48.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 420.000 $32.000 $30.000 $36.000 $35.000 $37.000 $38.000 $37.000
ROCK FILTER DAMS (REMOVE)
LF 480.000 $10.500 $5.000 $13.000 $5.000 $12.000 $12.000 $11.000
EARTHWORK (EROSN & SEDMT CONT, IN VEH)
CY 120.000 $20.000 $25.000 $40.000 $20.000 $13.000 $20.000 $17.000
BACKHOE WORK (EROSION & SEDMT CONT)
HR 100.000 $75.000 $60.000 $150.000 $50.000 $50.000 $75.000 $93.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,620.000 $3.000 $3.500 $2.550 $2.500 $2.550 $3.000 $3.550
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,620.000 $1.500 $1.000 $1.100 $0.500 $1.000 $1.000 $1.020
TRACKHOE WORK (EROSION & SEDMT CONT)
HR 100.000 $95.000 $60.000 $150.000 $70.000 $85.000 $75.000 $122.000
INTERSECTIONS (ACP)
SY 864.000 $55.000 $25.000 $35.000 $30.000 $46.500 $40.000 $48.000
DRIVEWAYS (ACP)
SY 3,202.000 $35.000 $25.000 $40.000 $28.000 $33.000 $30.000 $40.000
TURNOUTS (ACP)
SY 362.000 $31.000 $35.000 $46.000 $30.000 $59.000 $30.000 $50.000
DRIVEWAYS (CONC) (HES)
SY 426.000 $100.000 $125.000 $95.000 $130.000 $109.000 $95.000 $110.000
MTL W-BEAM GD FEN (TIM POST)
LF 186.000 $20.000 $26.000 $23.000 $19.000 $20.000 $24.000 $26.000
MTL W-BEAM GD FEN (STEEL POST)
LF 12.500 $80.000 $105.000 $80.000 $48.000 $50.000 $80.000 $34.000
SHORT RADIUS
LF 27.900 $25.000 $70.000 $50.000 $20.000 $21.000 $50.000 $40.000
MTL BM GD FEN (LONG SPAN SYSTEM)
EA 1.000 $850.000 $1,000.000 $1,155.000 $950.000 $1,000.000 $1,300.000 $930.000
REMOVE METAL BEAM GUARD FENCE
LF 222.000 $2.300 $12.000 $2.750 $2.100 $2.000 $4.000 $2.650
REMOVE TERMINAL ANCHOR SECTION
EA 1.000 $170.000 $250.000 $220.000 $160.000 $170.000 $300.000 $209.000
GUARDRAIL END TREATMENT (INSTALL)
EA 3.000 $2,600.000 $2,600.000 $2,750.000 $2,500.000 $2,600.000 $3,000.000 $3,020.000
GUARDRAIL END TREATMENT (REMOVE)
EA 2.000 $200.000 $300.000 $165.000 $220.000 $225.000 $200.000 $290.000
MAILBOX INSTALL-S (TWG-POST) TY 2
EA 28.000 $266.000 $250.000 $275.000 $260.000 $280.900 $275.000 $278.000
MAILBOX INSTALL-D (TWG-POST) TY 2
EA 1.000 $300.000 $300.000 $310.000 $300.000 $317.980 $300.000 $318.000
MAILBOX INSTALL-M (TWG-POST) TY 2
EA 3.000 $425.000 $450.000 $455.000 $440.000 $466.290 $500.000 $475.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 1.000 $625.000 $650.000 $710.000 $680.000 $723.600 $700.000 $705.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 2.000 $845.000 $850.000 $895.000 $860.000 $915.740 $900.000 $730.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 1.000 $870.000 $1,000.000 $1,095.000 $1,100.000 $1,117.980 $1,100.000 $1,050.000
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 31.000 $325.000 $450.000 $490.000 $470.000 $500.000 $500.000 $430.000
REMOVE SM RD SN SUP&AM
EA 35.000 $100.000 $110.000 $120.000 $120.000 $120.230 $130.000 $104.000
INSTL OM ASSM (OM-2Z)(FLX)GND
EA 10.000 $45.000 $60.000 $50.000 $60.000 $60.000 $55.000 $12.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 13.000 $32.000 $50.000 $27.000 $30.000 $32.000 $35.000 $15.000
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 19,640.000 $0.200 $0.250 $0.280 $0.260 $0.280 $0.270 $0.270
WK ZN PAV MRK NON-REMOV (W)18"(SLD)
LF 58.000 $1.500 $3.000 $2.750 $2.630 $2.750 $3.000 $2.600
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 290.000 $2.400 $3.000 $2.750 $2.630 $2.750 $3.000 $2.600
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 19,810.000 $0.200 $0.250 $0.280 $0.260 $0.280 $0.270 $0.270
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 994.000 $0.900 $1.500 $1.200 $0.600 $1.000 $2.000 $1.100
WK ZN PAV MRK SHT TERM RMV (Y)(4")
LF 2,232.000 $1.150 $2.000 $1.400 $0.700 $1.100 $2.000 $1.100
REFL PAV MRK TY I (W)18"(SLD)(100MIL)
LF 58.000 $2.650 $5.000 $5.500 $5.250 $5.500 $6.000 $6.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 398.000 $4.250 $5.500 $6.050 $5.800 $6.000 $6.000 $6.350
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 15,590.000 $0.400 $0.500 $0.550 $0.530 $0.550 $0.550 $0.550
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 15,760.000 $0.400 $0.500 $0.550 $0.530 $0.550 $0.550 $0.550
REF PROF PAV MRK TY I(W)4"(SLD)(100MIL)
LF 4,050.000 $0.500 $2.000 $1.650 $1.580 $1.700 $1.650 $1.650
REF PROF PAV MRK TY I(Y)4"(SLD)(100MIL)
LF 4,050.000 $0.500 $2.000 $1.650 $1.580 $1.700 $1.650 $1.650
PREFAB PAV MRK TY C (W) (18")(YLD TRI)
EA 4.000 $30.000 $100.000 $55.000 $52.500 $56.000 $55.000 $54.000
REFL PAV MRKR TY I-A
EA 32.000 $3.150 $4.000 $4.400 $4.200 $4.500 $5.000 $4.600
REFL PAV MRKR TY II-A-A
EA 468.000 $3.050 $4.000 $4.400 $4.200 $4.500 $5.000 $4.600
SP MIXES SP-B PG64-22
TON 2,022.000 $100.000 $75.000 $130.000 $125.000 $144.000 $125.000 $140.000
SP MIXES SP-D PG64-22 (LEVEL-UP)
TON 106.000 $100.000 $150.000 $150.000 $130.000 $137.000 $175.000 $200.000
SP MIXES SP-D SAC-A PG70-22
TON 2,612.000 $115.000 $80.000 $120.000 $130.000 $137.000 $133.000 $145.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 70.000 $100.000 $125.000 $100.000 $130.000 $80.000 $300.000 $100.000
TMA (STATIONARY)
DAY 22.000 $200.000 $200.000 $150.000 $250.000 $140.000 $300.000 $375.000
TMA (MOBILE OPERATION)
DAY 15.000 $75.000 $250.000 $150.000 $50.000 $50.000 $300.000 $375.000
Totals: $1,754,398.700 $1,730,130.350 $2,014,204.570 $2,047,149.090 $2,115,880.140 $2,139,928.950 $2,694,631.250