HAYS CR (0914-33-088)
Items: 72
County: HAYS
Length: N/A
Highway: CR
District: AUSTIN
Control Number: 0914-33-088
DBE Goal: N/A
Project: STP 2022(313)TAPS
Guaranty: N/A
Time: 120 WORKING DAYS
Engineer's Estimate: $1,304,314.90
Date: 09/06/2023 (2 years ago)
Contract Number: N/A
Type: CONSTRUCT PEDESTRIAN INFRASTRUCTURE
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (9)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$1,304,314.90 | |||
| $1,277,863.00 |
-2.03%
-$26,451.90
|
|||
| $1,502,697.46 |
15.21%
$198,382.56
|
17.59%
$224,834.46
|
||
| $1,630,655.24 |
25.02%
$326,340.34
|
27.61%
$352,792.24
|
-8.52%
-$127,957.78
|
|
| $1,715,019.40 |
31.49%
$410,704.50
|
34.21%
$437,156.40
|
-5.17%
-$84,364.16
|
|
| $1,797,832.40 |
37.84%
$493,517.50
|
40.69%
$519,969.40
|
-4.83%
-$82,813.00
|
|
| $1,838,244.00 |
40.94%
$533,929.10
|
43.85%
$560,381.00
|
-2.25%
-$40,411.60
|
|
| $1,899,665.50 |
45.64%
$595,350.60
|
48.66%
$621,802.50
|
-3.34%
-$61,421.50
|
|
| $1,905,227.61 |
46.07%
$600,912.71
|
49.09%
$627,364.61
|
-0.29%
-$5,562.11
|
|
| $2,002,721.25 |
53.55%
$698,406.35
|
56.72%
$724,858.25
|
-5.12%
-$97,493.64
|
E
Engineer's Estimate
$1,304,314.90
1
Awarded
$1,277,863.00
Over/Under Est:
-2.03%
-$26,451.90
$1,502,697.46
Over/Under Est:
15.21%
$198,382.56
Amt Left:
17.59%
$224,834.46
$1,630,655.24
Over/Under Est:
25.02%
$326,340.34
Amt Left:
27.61%
$352,792.24
Delta:
-8.52%
-$127,957.78
$1,715,019.40
Over/Under Est:
31.49%
$410,704.50
Amt Left:
34.21%
$437,156.40
Delta:
-5.17%
-$84,364.16
$1,797,832.40
Over/Under Est:
37.84%
$493,517.50
Amt Left:
40.69%
$519,969.40
Delta:
-4.83%
-$82,813.00
$1,838,244.00
Over/Under Est:
40.94%
$533,929.10
Amt Left:
43.85%
$560,381.00
Delta:
-2.25%
-$40,411.60
$1,899,665.50
Over/Under Est:
45.64%
$595,350.60
Amt Left:
48.66%
$621,802.50
Delta:
-3.34%
-$61,421.50
$1,905,227.61
Over/Under Est:
46.07%
$600,912.71
Amt Left:
49.09%
$627,364.61
Delta:
-0.29%
-$5,562.11
$2,002,721.25
Over/Under Est:
53.55%
$698,406.35
Amt Left:
56.72%
$724,858.25
Delta:
-5.12%
-$97,493.64
| Subcontractor | Percentage | Amount |
|---|---|---|
| THE LEVY COMPANY, INC. | 7.89% | $114,712.29 |
| AWP SAFETY | 0.36% | $5,234.02 |
| FIBERTEL, LLC | 0.35% | $5,088.63 |
| D. I. J. CONSTRUCTION, INC. | 0.00% | $0.00 |
| Total: | 8.60% | $125,034.94 |
Bid Items & Bid Tabulations
72
Total
0 of 72