Job Info for 0402-03-042

County: HARRISON Highway: SH 154 Date: 05/05/2023 (1 year ago) Engineer's Estimate: $4,104,966 Control Number: 0402-03-042
Project: STP 2023(698)HES District: ATLANTA Time: 197 WORKING DAYS Type: SAFETY TREAT FIXED OBJECTS
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12
Plans: Plans | Revision | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $4,104,966.05
EAST TEXAS BRIDGE, INC.   $3,492,422.90 1
-14.92% | -$612,543.15
H. V. CAVER, INC.   $3,874,251.69 2
-5.62% | -$230,714.36
10.93% | $381,828.79
CROSS PLUS CONSTRUCTION, LLC   $3,903,346.75 3
-4.91% | -$201,619.30
11.77% | $410,923.85
0.75% | $29,095.06
A. L. HELMCAMP, INC.   $4,144,326.96 4
0.96% | $39,360.91
18.67% | $651,904.06
6.17% | $240,980.21
LONGVIEW BRIDGE AND ROAD, LTD.   $4,487,812.63 5
9.33% | $382,846.58
28.5% | $995,389.73
8.29% | $343,485.67

Bid Items

Items: 31, 0 filtered
HARRISON SH 154  |  ATLANTA  |  0402-03-042  |  05/05/2023  |  $4,104,966  |  STP 2023(698)HES  |  SAFETY TREAT FIXED OBJECTS  |  197 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate EAST TEXAS BRIDGE, INC. H. V. CAVER, INC. CROSS PLUS CONSTRUCTION, LLC A. L. HELMCAMP, INC. LONGVIEW BRIDGE AND ROAD, LTD.
100 6002 PREPARING ROW STA 706.000 $3,400.000 $2,200.000 $3,500.000 $1,489.000 $3,300.000 $2,500.000
104 6009 REMOVING CONC (RIPRAP) SY 83.000 $20.000 $25.000 $25.000 $65.000 $45.000 $50.000
104 6017 REMOVING CONC (DRIVEWAYS) SY 573.000 $20.000 $25.000 $17.000 $65.000 $30.000 $55.000
104 6021 REMOVING CONC (CURB) LF 30.000 $20.000 $15.000 $20.000 $25.000 $55.000 $55.000
132 6021 EMBANKMENT (VEHICLE)(ORD COMP)(TY C) CY 167.750 $50.000 $50.000 $40.000 $55.000 $70.000 $65.000
150 6001 BLADING STA 109.750 $105.000 $300.000 $150.000 $250.000 $350.000 $1,500.000
164 6054 BOND FBR MTRX SEED (PERM)(RURAL)(SAND) SY 221,526.000 $0.700 $0.580 $0.530 $0.500 $0.550 $0.720
164 6071 BROADCAST SEED (TEMP)(WARM OR COOL) SY 221,526.000 $0.100 $0.120 $0.110 $0.500 $0.110 $0.160
168 6001 VEGETATIVE WATERING MG 6,580.400 $10.000 $8.000 $0.010 $20.000 $7.000 $35.000
400 6008 CUT & RESTORE ASPH PAVING SY 384.000 $150.000 $100.000 $90.000 $350.000 $130.000 $185.000
420 6009 CL A CONC (COLLAR) EA 58.000 $1,050.000 $1,700.000 $1,100.000 $1,600.000 $1,550.000 $1,250.000
432 6001 RIPRAP (CONC)(4 IN) CY 6.000 $750.000 $1,200.000 $500.000 $1,200.000 $1,350.000 $1,100.000
464 6003 RC PIPE (CL III)(18 IN) LF 2,512.000 $60.000 $62.000 $42.960 $135.000 $76.000 $75.000
464 6005 RC PIPE (CL III)(24 IN) LF 142.000 $80.000 $82.000 $67.880 $175.000 $105.000 $95.000
464 6007 RC PIPE (CL III)(30 IN) LF 12.000 $115.000 $130.000 $91.810 $289.000 $180.000 $120.000
464 6008 RC PIPE (CL III)(36 IN) LF 48.000 $180.000 $175.000 $131.980 $450.000 $210.000 $155.000
467 6363 SET (TY II) (18 IN) (RCP) (6: 1) (P) EA 430.000 $750.000 $900.000 $720.000 $2,100.000 $970.000 $1,300.000
467 6395 SET (TY II) (24 IN) (RCP) (6: 1) (P) EA 27.000 $1,250.000 $1,350.000 $410.000 $2,199.000 $1,550.000 $1,750.000
467 6423 SET (TY II) (30 IN) (RCP) (6: 1) (P) EA 2.000 $2,000.000 $2,500.000 $2,130.000 $7,500.000 $3,100.000 $4,100.000
467 6454 SET (TY II) (36 IN) (RCP) (6: 1) (P) EA 7.000 $4,050.000 $6,500.000 $5,945.150 $8,121.000 $7,200.000 $6,100.000
480 6001 CLEAN EXIST CULVERTS EA 96.000 $950.000 $1,625.000 $1,250.000 $400.000 $1,300.000 $3,500.000
496 6006 REMOV STR (HEADWALL) EA 4.000 $1,700.000 $1,700.000 $1,500.000 $1,500.000 $7,000.000 $3,000.000
496 6007 REMOV STR (PIPE) LF 2,626.000 $30.000 $16.000 $16.000 $22.000 $22.500 $22.000
500 6001 MOBILIZATION LS 1.000 $370,000.000 $350,000.000 $300,000.000 $375,000.000 $250,000.000 $400,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 13.000 $6,000.000 $15,000.000 $3,389.420 $5,000.000 $2,500.000 $7,000.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 250.000 $3.400 $6.000 $4.500 $5.000 $18.000 $8.000
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 250.000 $1.000 $3.000 $2.000 $5.000 $6.000 $4.000
529 6002 CONC CURB (TY II) LF 30.000 $90.000 $40.000 $50.000 $56.000 $105.000 $200.000
530 6020 DRIVEWAYS (CONC)(TYPE 1) SY 263.000 $100.000 $115.000 $120.000 $195.000 $130.000 $140.000
530 6028 DRIVEWAYS (CONC)(TYPE 2) SY 334.000 $120.000 $135.000 $140.000 $195.000 $160.000 $165.000
6185 6002 TMA (STATIONARY) DAY 197.000 $250.000 $250.000 $200.000 $500.000 $390.000 $350.000
Totals: $4,104,966.05 $3,492,422.90 $3,874,251.69 $3,903,346.75 $4,144,326.96 $4,487,812.63