Show Job Controls
Bid Cobra

HARRISON US 80 (0096-09-080)

Items: 35

County: HARRISON
Length: N/A
Highway: US 80
District: ATLANTA
Control Number: 0096-09-080
DBE Goal: N/A
Project: F 2022(217)
Guaranty: N/A
Time: 111 WORKING DAYS
Engineer's Estimate: $2,920,534.68
Date: 11/04/2021 (4 years ago)
Contract Number: N/A
Type: OVERLAY OF AN EXISTING ROADWAY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Documents:
Bidders (4)
E
Engineer's Estimate
$2,920,534.68
$2,903,146.62
Over/Under Est: -0.6% -$17,388.06
Over/Under Est: -0.11% -$3,191.21
Amt Left: 0.49% $14,196.85
Over/Under Est: 14.92% $435,741.18
Amt Left: 15.61% $453,129.24
Delta: -15.05% -$438,932.39
Over/Under Est: 26.96% $787,243.27
Amt Left: 27.72% $804,631.33
Delta: -10.47% -$351,502.09

Bid Items & Bid Tabulations

35 Total 0 of 35
HARRISON  |  US 80  |  ATLANTA  |  0096-09-080  |  11/04/2021  |  $2,920,534.68  |  F 2022(217)  |  OVERLAY OF AN EXIST ROADWAY  |  111 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
MADDEN CONTRACTING COMPANY, LLC.
L. S. EQUIPMENT CO., INC.
LONGVIEW BRIDGE AND ROAD, LTD.
EAST TEXAS BRIDGE, INC.
PREPARING ROW
AC 14.300 $8,636.000 $18,000.000 $18,000.000 $20,000.000 $20,000.000
REMOVING CONC (PAV)
SY 459.000 $25.000 $50.000 $25.000 $38.000 $35.000
REMOVING CONCRETE(MOW STRIP)
LF 3,225.000 $10.000 $8.000 $5.000 $16.500 $15.000
EMBANKMENT (VEHICLE)(ORD COMP)(TY C)
CY 120.000 $25.000 $40.000 $25.000 $34.000 $60.000
BACKFILL (TY A)
STA 241.000 $216.000 $275.000 $275.000 $265.000 $250.000
BOND FBR MTRX SEED (PERM)(RURAL)(SAND)
SY 75,801.000 $1.000 $0.580 $0.380 $0.650 $0.650
BONDED FBR MTRX SEED (TEMP)(WARM)
SY 52,334.000 $1.000 $0.520 $0.380 $0.660 $0.550
BONDED FBR MTRX SEED (TEMP)(COOL)
SY 52,334.000 $1.000 $0.520 $0.380 $0.630 $0.550
VEGETATIVE WATERING
MG 1,212.800 $15.000 $10.000 $1.000 $2.000 $15.000
ASPH (TIER II)
GAL 38,433.000 $3.000 $3.050 $3.250 $4.150 $5.000
AGGR(TY-PB GR-3 SAC-B)
CY 998.000 $130.000 $119.000 $125.000 $180.000 $190.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(18")
SY 642.000 $100.000 $180.000 $195.000 $200.000 $240.000
PLANE ASPH CONC PAV (1")
SY 109,805.000 $0.920 $1.000 $1.250 $1.300 $2.000
PLANE ASPH CONC PAV(1" TO 2")
SY 888.000 $0.930 $1.000 $4.000 $8.000 $4.000
RIPRAP (MOW STRIP)(4 IN)
CY 198.800 $490.000 $550.000 $500.000 $525.000 $500.000
MOBILIZATION
LS 1.000 $347,000.000 $124,500.000 $135,000.000 $300,000.000 $300,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 7.000 $6,500.000 $3,000.000 $3,000.000 $4,500.000 $15,000.000
MTL W-BEAM GD FEN (TIM POST)
LF 2,950.000 $21.000 $25.500 $29.000 $28.000 $28.000
MTL W-BEAM GD FEN (STEEL POST)
LF 25.000 $40.000 $85.000 $125.000 $95.000 $110.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 16.000 $1,800.000 $1,700.000 $2,000.000 $1,900.000 $2,000.000
REMOVE METAL BEAM GUARD FENCE
LF 2,025.000 $3.500 $2.500 $5.000 $2.800 $3.000
GUARDRAIL END TREATMENT (INSTALL)
EA 24.000 $2,700.000 $3,225.000 $3,500.000 $3,500.000 $3,700.000
GUARDRAIL END TREATMENT (REMOVE)
EA 24.000 $350.000 $200.000 $250.000 $220.000 $250.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 36.000 $40.000 $35.000 $50.000 $40.000 $40.000
WK ZN PAV MRK REMOV (Y)4"(BRK)
LF 4,691.000 $0.870 $1.550 $3.000 $1.400 $2.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 2,346.000 $1.400 $1.000 $1.000 $1.200 $2.000
REFL PAV MRKR TY II-A-A
EA 562.000 $3.500 $4.250 $4.000 $4.500 $5.000
SP MIXES SP-C PG70-22
TON 12,131.000 $104.000 $115.000 $111.000 $115.000 $125.000
PREFORMED IN-LANE(TRANS) RUMBLE STRIP
LF 12,022.000 $2.570 $2.500 $3.150 $3.400 $3.300
PREFORMED CENTERLINE RUMBLE STRIP
LF 6,011.000 $2.570 $2.500 $3.150 $3.400 $3.300
REFL PAV MRK AWT (W) 4" (SLD) (100MIL)
LF 48,084.000 $0.490 $0.380 $0.500 $0.550 $0.550
REFL PAV MRK AWT (Y) 4" (SLD) (100MIL)
LF 51,492.000 $0.750 $0.380 $0.500 $0.550 $0.550
REFL PAV MRK AWT (Y) 4" (BRK) (100MIL)
LF 3,984.000 $1.000 $0.400 $0.500 $0.550 $0.550
TMA (MOBILE OPERATION)
HR 168.000 $78.000 $1.000 $60.000 $25.000 $30.000
TMA (MOBILE OPERATION)
DAY 90.000 $317.260 $150.000 $175.000 $200.000 $300.000
Totals: $2,920,534.680 $2,903,146.620 $2,917,343.470 $3,356,275.860 $3,707,777.950