County: HARRISON Highway: US 80 Date: 10/03/2017 (7 years ago) Engineer's Estimate: $922,000 Control Number: 0096-07-049
Project: STP 2018(194)HES District: ATLANTA Time: 155 WORKING DAYS Type: UPGRADE MBGF

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $922,000.00
B & E CONSTRUCTION INC   $951,647.73 1
3.22% | $29,647.73
ODUM SERVICES, L.P.   $986,190.00 2
6.96% | $64,190.00
3.63% | $34,542.27
3LW CIVIL LLC   $999,125.80 3
8.37% | $77,125.80
4.99% | $47,478.07
1.31% | $12,935.80
EAST TEXAS BRIDGE, INC.   $1,126,765.12 4
22.21% | $204,765.12
18.4% | $175,117.39
12.78% | $127,639.32
VANN/ELLI, INC.   $1,243,923.50 5
34.92% | $321,923.50
30.71% | $292,275.77
10.40% | $117,158.38
FNH CONSTRUCTION, LLC   $1,304,442.50 6
41.48% | $382,442.50
37.07% | $352,794.77
4.87% | $60,519.00

Bid Items

Items: 15, 0 filtered
HARRISON US 80  |  ATLANTA  |  0096-07-049  |  10/03/2017  |  $922,000  |  STP 2018(194)HES  |  UPGRADE MBGF  |  155 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate B & E CONSTRUCTION INC ODUM SERVICES, L.P. 3LW CIVIL LLC EAST TEXAS BRIDGE, INC. VANN/ELLI, INC. FNH CONSTRUCTION, LLC
104 6054 REMOVING CONCRETE(MOW STRIP) LF 3,803.000 $7.000 $8.000 $6.000 $8.920 $10.000 $10.000 $15.000
132 6001 EMBANKMENT (FINAL)(ORD COMP)(TY A) CY 200.000 $15.000 $10.000 $28.000 $36.000 $30.000 $36.000 $30.000
432 6045 RIPRAP (MOW STRIP)(4 IN) CY 610.000 $550.000 $515.000 $550.000 $500.000 $500.000 $550.000 $550.000
451 6019 RETROFIT RAIL (TY T631) LF 1,192.000 $95.000 $75.000 $80.000 $91.830 $80.000 $106.000 $110.000
500 6001 MOBILIZATION LS 1.000 $85,567.750 $86,513.430 $75,000.000 $50,000.000 $100,000.000 $125,000.000 $120,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 10.000 $2,500.000 $2,571.250 $3,500.000 $10,000.000 $13,000.000 $8,000.000 $8,500.000
540 6001 MTL W-BEAM GD FEN (TIM POST) LF 10,440.000 $20.000 $16.800 $19.000 $18.000 $20.000 $24.000 $22.000
540 6002 MTL W-BEAM GD FEN (STEEL POST) LF 176.000 $75.000 $70.350 $87.000 $33.180 $75.000 $66.000 $35.000
540 6006 MTL BEAM GD FEN TRANS (THRIE-BEAM) EA 4.000 $1,500.000 $1,286.250 $1,450.000 $1,695.000 $1,500.000 $1,875.000 $1,850.000
540 6016 DOWNSTREAM ANCHOR TERMINAL SECTION EA 13.000 $1,200.000 $924.000 $1,225.000 $1,089.000 $1,200.000 $1,275.000 $1,850.000
542 6001 REMOVE METAL BEAM GUARD FENCE LF 10,912.500 $2.900 $2.100 $2.000 $2.000 $2.250 $3.000 $3.000
542 6002 REMOVE TERMINAL ANCHOR SECTION EA 60.000 $300.000 $210.000 $110.000 $200.000 $225.000 $200.000 $500.000
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 69.000 $300.000 $2,205.000 $2,050.000 $2,000.000 $2,375.000 $2,750.000 $2,850.000
544 6003 GUARDRAIL END TREATMENT (REMOVE) EA 16.000 $300.000 $315.000 $250.000 $200.000 $225.000 $300.000 $1,500.000
658 6062 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) EA 191.000 $75.000 $30.450 $40.000 $20.000 $17.000 $33.000 $100.000
Totals: $922,000.00 $951,647.73 $986,190.00 $999,125.80 $1,126,765.13 $1,243,923.50 $1,304,442.50